This text of 211 F.2d 347 (State of Oregon v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Oregon v. Federal Power Commission, 211 F.2d 347 (9th Cir. 1954).

Opinions

STEPHENS, Circuit Judge.

The Portland General Electric Company, an Oregon non-governmental public utility corporation, applied for and has been granted a license1 by the Fed[349]*349eral Power Commission to construct, operate and maintain a hydro-electric plant known as the Pelton Project, numbered 2030, on the Deschutes River2 in Oregon. The Project is to be located downstream from where Crooked River and Metolius River, two principal tributaries to the Deschutes, flow into the latter. The Project is designed to consist of a concrete dam approximately two hundred five feet high in connection with a powerhouse containing three 36,000 kilowatt generators and is to be built across the river on United States land. Included in the Project, and three miles below the power dam, a “re-regulating” dam is to be constructed which is designed to equate the flow of water as it is released from the upper dam. It is not claimed that the lower dam will be located upon federal land or federally controlled land. Without it the flow below the power dam would be subject to extremes as the water would be released from the power dam in much greater quantity when peak loads of electric energy were required. There will be no diversion of water from the stream, as it will flow, undiminished, through or over the dams and continue down the natural bed. The impounding of water above the upper dam will create a relatively narrow lake in mountainous terrain of five or six miles in length.

We quote from respondent Federal Power Commission’s brief (at pages 1 and 2):

“The project, if constructed, would occupy lands of the United States set aside on the west side of the Deschutes River by treaty in 1855 as the Warm Springs Indian Reservation, and additional lands of the United States on the east side of the river. All of the lands of the United States on both sides of the river which would be occupied by the project have been withdrawn from entry, location or other disposal under the public land laws and reserved for power purposes. In addition to these lands, some private lands would be affected by the project.
“The high power dam, and the powerhouse immediately below, will be located entirely upon lands of the United States set aside and reserved for power purposes. * *

The State of Oregon, The Fish Commission of Oregon, and The Oregon State Game Commission appeared before the Federal Power Commission hearing and registered objections to the granting of the license on the grounds that the dams would prevent the ascent , of anadromous fish to their spawning grounds above the dam sites, and would result in the serious curtailment of the fish population and prevent its increase, and would impair the productivity and usefulness of the extensive State Fish Hatchery on the Metolius River. They further contended that the Commission was without authority to grant the license applied for since the applicant had failed to obtain a permit from the Hydro-Electric Commission of Oregon 3 and had not complied with the Oregon law as to fish in the [350]*350river,4 as required by § 9 (b) of the Federal Power Act.5

Having been unsuccessful in their contentions before the Commission, as aggrieved persons, the objectors have petitioned this court for review of the order issued 6 and upon such review to set aside the order granting the license.

The Izaak Walton League of America (Oregon Division) filed a brief with us as amicus curiae in support of the objectors’ plea that the license granted should be set aside.

There is conflict in the evidence as to the probable effect of the proposed Project upon the fish population of the streams affected as well as to the need for the power which the Project is designed to produce. However, there is substantial evidence in support of the Commission’s findings as to the need for power, but in our opinion the evidence practically demonstrates that the Project would seriously affect the normal population of the fish in the river and the usefulness of the State Fish Hatchery. Whether the jurisdiction of the Federal Power Commission was broad enough to authorize such findings as binding against the State of Oregon, if supported by the evidence, will presently be considered.

The Commission, in its consideration of the application for the license, based its jurisdiction to entertain and grant the application solely upon the fact that the principal or upper dam is to be built upon and affects land reservations 7 of the United States,8 inclusive of the lands of the Warm Springs Indian Res[351]*351ervation.9 The Indians of the Reservation have given their consent to the construction of the Project.

Since Congress has delegated to the Federal Power Commission the authority to license power producing dams which will occupy or affect United States land and land reservations, it is incontrovertible that a Federal Power Commission license is necessary to the construction of the proposed Project by the applicant. The extent of the right which the federal license which has been granted carries or purports to carry, is in issue here.

The aggrieved parties argue that the Commission has no legal power to grant a license unless and until the applicant has shown the Commission that it has complied with all applicable state laws, and they cite instances of conflict between the Project as it is contemplated, and Oregon state law. In support of their contention they cite § 9(b) of the Federal Power Act which reads as follows:

"Satisfactory evidence that the applicant has complied with the requirements of the laws of the State or States within which the proposed project is to be located with respect to bed and banks and to the appropriation, diversion, and use of water for power purposes and with respect to the right to engage in the business of developing, transmitting, and distributing power, and in any other business necessary to effect the purposes of a license under this Act.” 41 Stat. 1068.

The application of the quoted section of the Federal Power Act, § 9(b), to the point has been negatived by the Supreme Court in the case of First Iowa HydroElectric Coop. v. Federal Power Comm., 1946, 328 U.S. 152, 177, 178, 66 S.Ct. 906, 918, 90 L.Ed. 1143, wherein the court said: “It [§ 9(b) ] does not itself require compliance with any state laws. Its reference to state laws is by way of suggestion to the Federal Power Commission of subjects as to which the Commission may wish some proof submitted to it of the applicant’s progress. * * The need for compliance with applicable state laws, if any, arises not from this federal statute but from the effectiveness of the state statutes themselves.”

We hold that § 9(b) neither enlarges nor limits the Federal Power Commission so far as the authority to grant the application for license is concerned. It specifically gives the Commission the right to ascertain needed information which would affect the Commission’s discretion in granting or withholding the license and as to details concerning the Project, its construction, capacity, and desirability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
211 F.2d 347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-oregon-v-federal-power-commission-ca9-1954.