Oklahoma Gas & Electric Co. v. Federal Energy Regulatory Commission

827 F.3d 75, 423 U.S. App. D.C. 433, 2016 U.S. App. LEXIS 12118, 2016 WL 3568086
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 1, 2016
Docket14-1281
StatusPublished
Cited by6 cases

This text of 827 F.3d 75 (Oklahoma Gas & Electric Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oklahoma Gas & Electric Co. v. Federal Energy Regulatory Commission, 827 F.3d 75, 423 U.S. App. D.C. 433, 2016 U.S. App. LEXIS 12118, 2016 WL 3568086 (D.C. Cir. 2016).

Opinion

WILKINS, Circuit Judge:

Until recently, incumbent public utilities were free to include in their tariffs and agreements “the option to construct any new transmission facilities in their particular service areas, even if the proposal for new construction came from a third party.” S.C. Pub. Serv. Auth. v. FERC (South Carolina), 762 F.3d 41, 72 (D.C. Cir. 2014) (per curiam). In practice, the incumbent utilities were likely to exercise these “rights of first refusal” — a convention that had certain downsides according to the Federal Energy Regulatory Commission (“FERC” or “the Commission”). See id. Fearful of deterring non-incumbents from proposing much-needed infrastructure reforms, discouraging competition within the industry, and potentially driving up the cost of rates charged for wholesale electricity service, the Commission ordered utilities to remove rights of first refusal from their existing tariffs and agreements. See id. at 53, 72 (citing Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, F.E.R.C. Stats. & Regs. ¶ 31,323, 76 Fed. Reg. 49,842 (2011)) [hereinafter Order No. 1000].

In South Carolina, we upheld the Commission’s removal mandate. 762 F.3d at 71-81. In so doing, we found it premature to address those petitioners’ argument that FERC could not make them eliminate such provisions without violating the Mobile-Sierra doctrine. Id. at 81. Under Mobile-Sierra, FERC must presume a contract rate for wholesale energy is just and reasonable and cannot set aside the rate unless it is contrary to the public interest. See New England Power Generators Ass’n, Inc. v. FERC, 707 F.3d 364, 366 (D.C. Cir. 2013) (citing United Gas Pipe Line Co. v. Mobile Gas Serv. Corp. (Mobile ), 350 U.S. 332, 76 S.Ct. 373, 100 L.Ed. 373 (1956), and Fed. Power Comm’n v. Sierra Pac. Power Co. (Sierra), 350 U.S. 348, 76 S.Ct. 368, 100 L.Ed. 388 (1956)).

The Commission had reserved judgment on whether to apply this presumption to the rights of first refusal until evaluating the individual utilities’ compliance filings, and therefore so did we. South Carolina, 762 F.3d at 81. Utility Petitioner Oklahoma Gas and Electric Company (“OG&E”), as well as several Intervenors (collectively, “Petitioners”) 1 now petition *77 for review from FERC’s determination at the compliance stage. They urge that the Commission erred in concluding that Mobile-Sierra does not in fact protect their rights of first refusal contained in their Regional Transmission Organization (“RTO”) Membership Agreement. We hold that the Commission painted with a broader brush than necessary in applying potentially applicable Supreme Court precedent, but we deny the petition nonetheless because nothing in the Mobile-Sierra doctrine requires its extension to the anti-competitive rights of first refusal at issue here.

I.

Petitioners are members of the RTO, Southwest Power Pool, Inc. (“Southwest Power Pool”), which provides transmission service to approximately 6 million households across portions of eight states. Although public utilities previously were vertically integrated — meaning they generated, transmitted, as well as distributed electricity — FERC in the past two decades has undertaken a number of structural reforms to unbundle the wholesale sale of power from its transmission, and to require utilities to provide open access to transmission lines in a nondiscriminatory fashion. See Atlantic City Elec. Co. v. FERC, 295 F.3d 1, 4 (D.C. Cir. 2002). One of these reforms encouraged the formation of RTOs like Southwest Power Pool. See Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1, 554 U.S. 527, 536, 128 S.Ct. 2733, 171 L.Ed.2d 607 (2008). RTOs are independent entities to which transmission-owning utilities have given operational control of their facilities. See id.; Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1364 (D.C. Cir. 2004) (explaining that placing control of transmission lines in RTOs was expected to promote competition and overcome inefficiencies).

Yet another reform was Order No. 1000, which required the removal from utilities’ tariffs and agreements of federal rights of first refusal to construct transmission facilities in the regional transmission plan. See Order No. 1000, ¶ 268, 76 Fed. Reg. at 49,888. Tariffs are the mechanism through which regulated utilities unilaterally set their rates and terms of service. See Morgan Stanley, 554 U.S. at 531, 128 S.Ct. 2733; South Carolina, 762 F.3d at 71 n. 5. In contrast, rates and terms can also be set by agreement with individual electricity purchasers, through bilateral contracts. See Morgan Stanley, 554 U.S. at 531, 128 S.Ct. 2733 (citing 16 U.S.C. § 824d(c), (d)). Both tariffs and contracts must be filed with the Commission before they go into effect. Id. Not only rates, but also “any rule, regulation, practice, or contract affecting such rate[s],” 16 U.S.C. § 824e(a), are subject to FERC review to ensure they are “just and reasonable,” id. § 824d(a). If found unjust or unreasonable, FERC may replace the unlawful rate, practice, or contract with a lawful one. See id. § 824e(a); Morgan Stanley, 554 U.S. at 532, 128 S.Ct. 2733. In South Carolina, we held that the Commission properly exercised its authority under the Federal Power Act (“FPA”) to regulate the rights of first refusal as a practice affecting a rate. 762 F.3d at 76; see also id. at 76-81 (finding FERC supported its conclusion that *78 the rights were unjust or unreasonable with substantial evidence, and that the ban on rights of first refusal was not otherwise arbitrary or capricious on its face).

At issue here is a portion of the Membership Agreement Petitioners executed with Southwest Power Pool to join the RTO. Petitioners’ refusal rights were contained in Section 3.3 of their Agreement. Order No. 1000’s removal mandate thus obligated Southwest Power Pool to revise that provision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shell Energy North America (US), L.P. v. FERC
107 F.4th 981 (D.C. Circuit, 2024)
Advanced Energy United, Inc. v. FERC
82 F.4th 1095 (D.C. Circuit, 2023)
Wabash Valley Power Association, Inc. v. FERC
45 F.4th 115 (D.C. Circuit, 2022)
Missouri River Energy Services v. F.E.R.C.
918 F.3d 954 (D.C. Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
827 F.3d 75, 423 U.S. App. D.C. 433, 2016 U.S. App. LEXIS 12118, 2016 WL 3568086, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oklahoma-gas-electric-co-v-federal-energy-regulatory-commission-cadc-2016.