Iberdrola Renewables, Inc. v. Federal Energy Regulatory Commission

597 F.3d 1299, 389 U.S. App. D.C. 310, 179 Oil & Gas Rep. 1094, 2010 U.S. App. LEXIS 4032, 2010 WL 668870
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 26, 2010
Docket08-1195
StatusPublished
Cited by6 cases

This text of 597 F.3d 1299 (Iberdrola Renewables, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iberdrola Renewables, Inc. v. Federal Energy Regulatory Commission, 597 F.3d 1299, 389 U.S. App. D.C. 310, 179 Oil & Gas Rep. 1094, 2010 U.S. App. LEXIS 4032, 2010 WL 668870 (D.C. Cir. 2010).

Opinion

Opinion for the Court filed by Circuit Judge GRIFFITH.

GRIFFITH, Circuit Judge.

Although set against the complicated regulatory framework of federal energy law, at the end of the day, this petition for review of Federal Energy Regulatory Commission (FERC) orders requires only our straightforward application of the plain terms of a written contract. The question is whether FERC arbitrarily or capriciously read a contract to allow a pipeline to change its rates without first obtaining FERC’s approval. Because the contract expressly excludes such a role for FERC, we deny the petition.

I.

Intervenor Alliance Pipeline L.P. operates an 887-mile pipeline that transports *1301 natural gas from the North Dakota-Canada border to the Chicago area. Alliance Pipeline L.P., Preliminary Determination on Nonr-Environmental Issues, 80 FERC ¶ 61,149, at 61,590 (1997) [hereinafter Preliminary Determination]. Before Alliance began service on the pipeline, each shipper chose to negotiate the rate it would pay and committed that agreement to a written contract. Any shipper could have chosen a different option, a non-negotiable “recourse rate,” based only on the pipeline’s cost of providing service and a FERC-determined profit margin.

That the shipper in this case, predecessor in interest to Petitioner, Iberdrola Renewables, Inc., selected a negotiated rate is a critical fact that has bearing upon the central issue of this petition: whether FERC must approve changes Alliance made to the negotiated rate. In the exercise of its duty under section 4 of the Natural Gas Act (NGA) to ensure that rates are “just and reasonable,” 15 U.S.C. § 717c(a) (2006), the Commission automatically reviews proposed changes to recourse rates but reviews changes to negotiated rates only when the contract requires it. 1 See Alternatives to Traditional Cost-of-Service Ratemaking for Natural Gas Pipelines, 74 FERC ¶ 61,-076, at 61,241 (1996) [hereinafter Policy Statement ]. This approach reflects FERC’s assumption that sophisticated parties will bargain for rates that are just and reasonable. See id. at 61,241-42. So long as the pipeline adjusts the negotiated rate consistently with the terms of the written agreement, FERC will accept the rate change without reviewing the adjustment for reasonableness. See id. at 61,-238, 61,240. Shippers choosing negotiated rates thus can agree to avoid FERC’s review under section 4 and thereby “remove themselves from any protection the Commission may give customers under recourse rates.” Colo. Gulf Transmission Co., 78 FERC ¶ 61,263, at 62,124 (1997). In effect, the shippers can bargain away the protection of FERC’s prior approval of rate changes in exchange for what they see as more favorable rates.

Of course, negotiated rate customers are not left without redress if they think the rate has become unjust over time. They can always challenge an established rate under section 5 of the NGA on the ground that the rate is “unjust, unreasonable, unduly discriminatory, or preferential.” 15 U.S.C. § 717d(a). A section 5 review differs from a section 4 review in two significant ways. First, section 5 provides for FERC review of a rate only after it has taken effect. By contrast, FERC may only review a rate under section 4 at the time it is filed. See Sea Robin Pipeline Co. v. FERC, 795 F.2d 182, 183-84 (D.C.Cir.1986) (discussing the salient differences between NGA section 4 and section 5). Second, the pipeline bears the burden to show the proposed rate is reasonable in a section 4 action, whereas the shipper bears the burden to show an established rate is not in a section 5 case. Thus, shippers seeking to involve FERC in the review of their rates have three options: ex ante, they can (1) elect a recourse rate, which FERC will automatically review at the time it is filed, or (2) negotiate for FERC approval of rate changes in their contract; ex post, they *1302 can (3) pursue a section 5 action after the negotiated rate has taken effect.

This petition requires the court to determine whether the negotiated contract between Alliance and its shippers calls for FERC approval of a rate change, and the history of the contract bears upon our analysis. The earliest form of the agreement was executed while the pipeline’s application was pending for the certificate of public convenience and necessity that would allow it to operate. In this preliminary contract, called the Precedent Agreement, the parties agreed to a negotiated rate in lieu of a recourse rate. The agreement provided that “[c]hanges in [Alliance’s] operating costs will be reflected in its rates from time to time.” Open Season Precedent Agreement, sched. C., at 3. No language in the Precedent Agreement called for FERC approval of changes to the negotiated rate.

Even so, the proposed tariff Alliance filed with its Certificate Application suggested that Alliance would need FERC’s approval for any changes to the negotiated rate based on changes in its operating costs: “The Negotiated Rates are determined using actual operating and maintenance costs ... approved by the FERC from time to time.” Certificate Application, Pro Forma Sheet 8 (emphasis added). FERC directed Alliance to remove that language from its tariff, explaining that such a provision belongs more appropriately in the parties’ Transportation Agreement, which they would sign after FERC issued Alliance its certificate. Preliminary Determination, 80 FERC at 61,599. Thus, if the parties wished, they could provide for FERC review of negotiated rate changes in their contract. See id. Otherwise, prior approval from FERC would not be forthcoming. After FERC awarded Alliance its certificate, the parties executed the Transportation Agreement, replacing the Precedent Agreement. Alliance and its shippers included no language in that contract providing for FERC review of negotiated rate changes. Rather, the Transportation Agreement simply repeated the language previously agreed to: “Changes in [Alliance’s] operating costs will be reflected in its rates from time to time.” Transportation Agreement, App. B.

Since pipeline service began in 2000, Alliance has charged the negotiated rate, which it has periodically increased — without FERC’s prior approval — to reflect changes in its operating costs. From 2003 to 2007, these annual increases averaged 2.5%. Each year the recourse rate was higher than the negotiated rate, until late 2007 when Alliance sought to increase the negotiated rate by about 6%. For the first time, the negotiated rate exceeded the recourse rate. And for the first time, PPM Energy, Iberdrola’s predecessor in interest, asked FERC to reject the filing on the grounds that Alliance’s proposed rate increase “failed to satisfy both the rate-change requirements under the negotiated rate agreements and FERC’s basic requirements for such filings.” Petitioner’s Br. at 11-12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Association of Realtors v. United States
97 F.4th 951 (D.C. Circuit, 2024)
Fairless Energy, LLC v. FERC
77 F.4th 1140 (D.C. Circuit, 2023)
United States v. Ernest Moore
703 F.3d 562 (D.C. Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
597 F.3d 1299, 389 U.S. App. D.C. 310, 179 Oil & Gas Rep. 1094, 2010 U.S. App. LEXIS 4032, 2010 WL 668870, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iberdrola-renewables-inc-v-federal-energy-regulatory-commission-cadc-2010.