TC Ravenswood, LLC v. Federal Energy Regulatory Commission

741 F.3d 112, 408 U.S. App. D.C. 171, 2013 WL 6509470, 2013 U.S. App. LEXIS 24748
Court of Appeals for the D.C. Circuit·Decided December 13, 2013·No. 19-5139·Published·Cited by 8 cases

Opinion

Opinion for the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge:

Utilizing administratively determined “demand curves,” the New York Independent System Operator (NYISO) holds monthly auctions to set the price of electrical power capacity in New York. Petitioners, owners and operators of electrical power generation facilities, challenge several Federal Energy Regulatory Commission orders concerning the creation of the 2011-2014 demand curves. According to petitioners, the Commission exceeded its statutory authority by suspending NYI-SO’s proposed demand curves for more than five months and acted arbitrarily and capriciously by failing to follow its own precedent requiring only a nominal suspension. Petitioners also challenge several technical aspects of the proposed curves. For the reasons set forth in this opinion, we deny the petitions for review.

I.

The not-for-profit NYISO manages the flow of electricity over New York’s electrical grid. One of NYISO’s challenges is to maintain an adequate supply of electrical power to meet consumer demand. To accomplish this, NYISO works to ensure that power generators have sufficient incentives to build new power plants when the grid needs additional supply. The cost of power plant construction and fluctuations in price and consumer demand complicate this task. Fearing that unexpected decreases in price or demand might thwart cost recovery, power generators may forgo desirable investment in new generation. If needed development fails to occur, supply will eventually dip below demand, leaving consumers in the dark.

NYISO utilizes monthly capacity auctions to reduce such uncertainties and encourage desirable investment. Unlike the electricity market, in which generators sell actual power to retailers, the capacity market trades in the future supply of electrical power. NYISO’s capacity market encourages infrastructure investment by linking the price of capacity to the price needed to recoup the cost of building a hypothetical new “peaker” power plant, i.e., a plant that operates only in times of high demand.

Here’s how it works. Capacity suppliers bid a quantity of capacity into the auction, and the total amount of capacity bid creates a supply curve, which intersects with a predetermined demand curve. The intersection of the two curves establishes the available quantity of capacity and the price for this capacity. See Electricity Consumers Resource Council v. FERC, 407 F.3d 1232, 1235-36 (D.C.Cir.2005) (describing use of demand curves in capacity auctions). Power retailers then purchase capacity at that price. In theory, this market design encourages desirable investment by signaling the need for more generation and by enabling power generators to recoup their costs in the capacity market.

*115 Pursuant to its Market Administration and Control Area Services Tariff, NYISO files new demand curves with the Commission every three years. The curve-design process focuses on estimating the “cost of new entry” for a hypothetical new peaker plant. In Commission lingo, this requires calculating the “localized levelized cost per kW-month to develop a new peaking unit with energy and ancillary services revenues subtracted.” See New York Independent System Operator, Inc. (“January Order”), 134 FERC ¶ 61,058, at P 6 (2011). In plain English, the cost of new entry equals the hypothetical plant’s total cost of producing a unit of electricity — the cost of constructing and operating a plant divided by its expected lifetime energy output— minus what the plant will receive for selling this electricity. Because curves are set for three years, NYISO also establishes an “escalation factor,” which it uses to adjust the curves each year for inflation.

In November 2010, NYISO filed its 2011-2014 demand curves (the “Proposed Curves”) with the Commission. The Proposed Curves were to take effect in the May 2011 auction following expiration of the then-in-effect curves on April 30, 2011 (the “Preexisting Curves”). Relevant to this appeal, the Proposed Curves excluded the cost of property taxes from the cost of new entry, included a 1.7% escalation factor based on a general inflation index, and estimated the energy and ancillary services revenues (“E & AS revenues”) using a regression model based on three years of data.

On January 28, 2011, the Commission approved the escalation factor and E & AS revenues estimate but found the property tax exclusion unreasonable. January Order, 134 FERC ¶ 61,058 at PP 88-90, 136, 150. Believing that the Proposed Curves might not be “just and reasonable” as required by section 205(a) of the Federal Power Act, 16 U.S.C. § 824d(a), the Commission exercised its section 205(e) authority to suspend the proposed rates for up to five months, id. § 824d(e), and suspended the Proposed Curves “for five months, to become effective the earlier of June 28, 2011, or a date set by a subsequent Commission order.” January Order, 134 FERC ¶ 61,058 at P 168. The order also directed NYISO to make a further compliance filing to correct the problems identified in the order, id. at P 1, and to inform the Commission of “the date it anticipates implementing the new demand curves,” provided such “date should be no later than November 1, 2011,” id. at P 168. “[T]he currently effective demand curves,” the order concluded, “will remain in effect until superseded.” Id. at P 168.

In response, NYISO asked the Commission whether it should apply an escalation factor to the “currently effective demand curves” during the suspension period, and several petitioners sought rehearing of the Commission’s imposition of the maximum five-month suspension period. Rejecting both requests, the Commission ruled that the January Order “clearfly] and unambiguously]” did not provide for escalation, and justified the suspension length citing the “unique nature and purpose of the rates filed” and the need for market participants to “have the actual re-calculated rates before them when they bid in the ICAP auctions.” New York Independent System Operator, Inc. (“Suspension Rehearing Order”), 134 FERC ¶ 61,178 at PP 16-18 & n. 13 (2011).

NYISO responded with two new filings. In the first, submitted March 28, NYISO sought to “establish that the currently effective ICAP Demand Curves will be in effect as of May 1, 2011 and reflect that they will remain in effect until a date established by Commission order.” Compliance Filing to State Currently Effective *116 ICAP Demand Curves, March 28, 2011, Joint Appendix (J.A.) 856. Accepted by the Commission on April 4, this filing enabled the Preexisting Curves to remain in place beyond the end of the suspension period. See New York Independent System Operator, Inc. (“April Order”), 135 FERC ¶ 61,002 at P 10 (Apr. 4, 2011), reh’g denied, 137 FERC ¶ 61,218 (2011). In the second filing, NYISO submitted revised curves that implemented the changes the Commission required in its January Order (“the Compliance Curves”).

Free access — add to your briefcase to read the full text and ask questions with AI

TC Ravenswood, LLC v. Federal Energy Regulatory Commission, 741 F.3d 112, 408 U.S. App. D.C. 171, 2013 WL 6509470, 2013 U.S. App. LEXIS 24748 (D.C. Cir. 2013).

741 F.3d 112 (TC Ravenswood, LLC v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related