Elec Consum Resrc v. FERC

407 F.3d 1232
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 13, 2005
Docket03-1449
StatusPublished

This text of 407 F.3d 1232 (Elec Consum Resrc v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elec Consum Resrc v. FERC, 407 F.3d 1232 (D.C. Cir. 2005).

Opinion

407 F.3d 1232

ELECTRICITY CONSUMERS RESOURCE COUNCIL, Petitioner
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent
Consolidated Edison Company of New York, Inc., et al., Intervenors

No. 03-1449.

United States Court of Appeals, District of Columbia Circuit.

Argued April 11, 2005.

Decided May 13, 2005.

On Petition for Review of Orders of the Federal Energy Regulatory Commission.

Sara D. Schotland argued the cause for petitioner. With her on the briefs was Robert A. Weishaar, Jr.

Lona T. Perry, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Cynthia A. Marlette, General Counsel, and Dennis Lane, Solicitor.

Jonathan D. Feinberg was on the brief for intervenor Public Service Commission of the State of New York.

William F. Young and Susan E. Dove were on the brief for intervenor New York Independent System Operator, Inc. Arnold H. Quint entered an appearance.

Frederick W. Morris, James J. Bertrand, Brian M. Meloy, Debra R. Bolton, Scott G. Silverstein, Mary M. Fabic, and Kenneth R. Carretta were on the brief for intervenors NRG Companies, et al.

Before: SENTELLE, ROGERS and TATEL, Circuit Judges.

Opinion for the Court filed by Circuit Judge ROGERS.

ROGERS, Circuit Judge.

The Electricity Consumers Resource Council ("ELCON") challenges two orders of the Federal Energy Regulatory Commission approving a rate design for the installed capacity market administered by the New York Independent System Operator, Inc. ("NYISO"). See N.Y. Indep. Sys. Operator, Inc., 2003 WL 21155022, 103 F.E.R.C. ¶ 61,201 (2003) ("Initial Order"); NY Indep. Sys. Operator, Inc., 2003 WL 22422351, 105 F.E.R.C. ¶ 61,108 (2003) ("Rehearing Order"). While maintaining that the Commission's orders violate both the "just and reasonable" ratemaking standard of the Federal Power Act ("FPA"), 16 U.S.C. § 824d(a) (2000), and the arbitrary and capricious standard of the Administrative Procedure Act ("APA"), 5 U.S.C. § 706(2)(A) (2000), ELCON urges a heightened standard of review for "incentive ratemaking" requiring the Commission to demonstrate that the rate increase is no more than necessary to achieve its purpose of encouraging investment in new generation facilities in New York State. Because we conclude that the rate design does not impose an incremental rate increase above traditional cost-based rates but rather seeks to stabilize rates to promote the development and retention of installed capacity, there is no basis for applying a heightened standard of review. Upon applying the usual APA standard, we conclude that the Commission's approval of the rate design is supported by substantial evidence in the record and is not otherwise arbitrary and capricious. Accordingly, we deny the petition for review.

I.

To prevent electricity shortages during periods of peak demand, the New York State Reliability Council required retail utilities, known as load serving entities ("LSEs"), to purchase installed capacity ("ICAP") equal to 118% of their peak loads. See Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,750. If an LSE failed to procure the required amount of ICAP through its own supply or through bilateral contracts, it was required to purchase the deficient quantity through NYISO auctions, at which the price equaled a "deficiency charge" of $255 per kilowatt-year, or three times the annualized cost of installing a new "peaker" power plant. See id. This rate design resulted in a vertical demand curve for ICAP, with the price equal to $255 for all quantities up to 118%, and $0 for all quantities exceeding 118%. See id. & fig.1. According to NYISO, the vertical demand curve caused extreme volatility in ICAP prices, thus discouraging investment in new generation facilities and creating "the potential for a capacity deficiency" in New York State. Id. at 61,751.

Figure 1: Vertical Demand Curve

NOTE: OPINION CONTAINING TABLE OR OTHER DATA THAT IS NOT VIEWABLE To address this problem, NYISO applied to the Commission for approval of amendments to its tariff to incorporate a new rate design replacing the vertical demand curve with a sloped "ICAP Demand Curve," which would be used in monthly auctions to determine both the quantity and price of required ICAP. See id. For 118% of peak load, the price would equal the annualized cost of a new peaker plant. See id. As supply increased above 118%, the price would gradually decrease until it reached zero for 132% of peak load, and as supply decreased below 118%, the price would gradually increase until it reached a maximum of two times the annualized cost of a new peaker plant. See id. & fig.2.

Figure 2: Sloped ICAP Demand Curve

NOTE: OPINION CONTAINING TABLE OR OTHER DATA THAT IS NOT VIEWABLE

Each month, capacity suppliers, including LSEs with excess capacity, would bid into an ICAP auction and create the supply curve; the point of intersection between the supply curve and the ICAP Demand Curve would determine the quantity and price of required ICAP. See id. at 61,752. If the monthly auction yielded a quantity less than 118% of peak load, NYISO would purchase the deficient amount outside the auction market and charge each LSE a "supplemental supply fee" equal to 1.5 times the annualized cost of a new peaker plant. See id. at 61,753. NYISO also proposed a "periodic independent review of the Demand Curve every three years to determine whether adjustments are warranted." Id.

ELCON, which represents industrial consumers of electricity, intervened and protested the new rate design, arguing that it would increase electricity prices for consumers without spurring investment in new generation capacity, and that it violated incentive ratemaking case law because the ICAP Demand Curve was not carefully calibrated to increase investment in new generation facilities without granting a windfall to existing capacity suppliers. The Commission approved NYISO's rate design with modifications, finding that it would "benefit customers because it [would] provide better price signals to investors for construction of new generation, encourage the formation of long-term bilateral transactions, and reduce incentives to withhold capacity." Id. at 61,750. The Commission agreed with NYISO that the ICAP Demand Curve would "encourage greater investment in generation capacity and thus improve reliability, by reducing the volatility of ICAP revenues," and concluded that it would "provide net benefits especially compared with the existing vertical demand curve." Id. at 61,753-54. The Commission eliminated the supplemental supply fee based on the concern that suppliers would withhold capacity from the monthly ICAP auction in order to sell capacity at the higher price of the supplemental supply fee. See id. at 61,761.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
407 F.3d 1232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elec-consum-resrc-v-ferc-cadc-2005.