Independent Power Producers of New York, Inc. v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 9, 2022
Docket21-1166
StatusUnpublished

This text of Independent Power Producers of New York, Inc. v. FERC (Independent Power Producers of New York, Inc. v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Independent Power Producers of New York, Inc. v. FERC, (D.C. Cir. 2022).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 21-1166 September Term, 2021 Filed On: August 9, 2022 INDEPENDENT POWER PRODUCERS OF NEW YORK, INC., PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

MULTIPLE INTERVENORS, INTERVENOR

On Petition for Review of an Order of the Federal Energy Regulatory Commission

Before: TATEL, ∗ MILLETT and RAO, Circuit Judges.

JUDGMENT This case was considered on the record and on the briefs and oral arguments of the parties. The court has afforded the issues full consideration and determined that they do not warrant a published opinion. See D.C. Cir. R. 36(d). For the following reasons, it is ORDERED AND ADJUDGED that the petition for review be GRANTED. Independent Power Producers of New York, Inc. (“Independent Power”), a trade association of electricity generators, petitions for review of an order of the Federal Energy Regulatory Commission (“FERC”) denying in part a rate filing submitted by the New York Independent System Operator, Inc. (“NYISO”). We hold that FERC’s order was insufficiently reasoned and must be set aside. I. NYISO oversees the New York electricity transmission grid and manages the State’s wholesale electricity marketplace. It conducts monthly capacity auctions at which electricity

∗ Judge Tatel assumed senior status after this case was argued and before the date of this judgment. 1 providers (e.g., generators) bid for the right to supply wholesale electricity to consumers (e.g., utilities) in the future. At these auctions the price of capacity turns, in large part, on NYISO’s estimate of the net annual cost of a hypothetical “peaking plant” in New York. 1 See TC Ravenswood, LLC v. FERC, 741 F.3d 112, 114–15 (D.C. Cir. 2013). To calculate this net annual cost, NYISO’s Services Tariff requires it to estimate the total lifetime cost of building and operating a peaking plant, divide that figure by the projected number of years such a plant will remain operational, and then subtract the plant’s expected annual revenues. See NYISO Tariff § 5.14.1.2.2. NYISO refers to the resulting sum as the plant’s “cost of new entry.” The price of capacity at auction increases as NYISO’s cost of new entry estimate increases. See Elec. Consumers Res. Council v. FERC (“ELCON”), 407 F.3d 1232, 1235 (D.C. Cir. 2005). NYISO’s Tariff requires it to submit a current estimate of the cost of new entry for this hypothetical peaking plant to FERC every four years. NYISO Tariff § 5.14.1.2.2. This case centers on NYISO’s filing for the 2021–2025 period, which it submitted in November 2020. As in past years, NYISO used a gas-fired peaking plant as the model for its cost of new entry calculation. 2 But whereas in previous years it estimated that such a resource would have an “amortization period” (i.e., average commercial lifespan) of twenty years, in its 2020 filing, NYISO shortened its estimate to seventeen years. As NYISO pointed out, New York had recently passed the Climate Leadership and Community Protection Act (“Climate Act”). See 2019 N.Y. Sess. Laws ch. 106 (McKinney) (codified in relevant part at N.Y. PUB. SERV. LAW § 66-p). The Climate Act directed that, by June 30, 2021, New York’s Public Service Commission (“PSC”) “shall establish a program to require that … by the year two thousand forty … the statewide electrical demand system will be zero emissions.” N.Y. PUB. SERV. LAW § 66-p(2). In other words, the Act required the PSC to introduce regulations to ensure that, by 2040, the consumption of electricity throughout the State will produce zero carbon emissions. In crafting these regulations, the Act authorized the PSC to “modify the obligations of jurisdictional load serving entities and/or the [Act’s emission] targets” if they impede the delivery of “safe and adequate electric service.” Id. It also permitted the PSC to “temporarily suspend or modify the [regulatory] obligations” placed on power plants if they are “imped[ing] the provision of safe and adequate electric service.” Id. § 66-p(4). In its 2020 filing, NYISO explained that, in light of the Climate Act and the PSC’s impending regulations, a gas-fired peaking plant was unlikely to remain in service beyond 2039. Although the Act did not expressly require “all existing fossil-fired generation [to] cease operation” by 2040 and although “retrofitting options” to convert fossil-fueled plants into non- emitting ones might one day become available, the PSC had not clarified what steps fossil-fueled plants could take to remain in operation after 2039, nor had it exercised its discretion to modify the Act’s target. In NYISO’s view, the Climate Act therefore “requires electricity demand in New York to be served by 100% zero-emission resources by January 1, 2040.” “Thus the developer of a fossil peaking plant would face substantial uncertainty about the financial returns of a fossil peaking plant … starting in 2040.” NYISO concluded that a gas-fired plant built between 2021 and 2025 would have, on average, a seventeen-year lifespan.

1 A peaking plant is one built to provide electricity only in moments of maximum grid usage. NYISO Tariff § 5.14.1.2.2. 2 No party to this case contests NYISO’s decision to model the cost of new entry on a gas-fired plant. 2 After considering NYISO’s filing alongside comments from NYISO’s Market Monitoring Unit (“MMU”), among others, FERC rejected NYISO’s proposed amortization period because it was “premised on the speculative assumption that all fossil-fueled resources will cease operation in 2040.” N.Y. Indep. Sys. Operator, Inc., 175 FERC ¶ 61,012 at P 161 (2021) [Demand Curve Order]. FERC directed NYISO to submit an amended filing, substituting a twenty-year amortization period for its seventeen-year one. See id. at P 2. Independent Power requested rehearing. FERC did not revisit its initial order within thirty days, so it became final by operation of law. See 16 U.S.C. § 825l(a). Independent Power then timely petitioned for review, arguing that FERC’s order was “arbitrary, capricious, [and] not in accordance with law” in violation of the Administrative Procedure Act. 5 U.S.C. § 706(2)(A). An association of New York electricity consumers intervened on behalf of FERC. We have jurisdiction under 16 U.S.C. § 825l(b). II. A. Under Section 205 of the Federal Power Act, NYISO bore the burden of showing that its filing was “just and reasonable.” Id. § 824d(e); see Ala. Power Co. v. FERC, 993 F.2d 1557, 1571 (D.C. Cir. 1993). FERC had previously approved NYISO’s decision to index the price of capacity to the net cost of a peaking plant as just and reasonable. See ELCON, 407 F.3d at 1233–35. Therefore, NYISO needed to show that its amortization period represented a reasonable estimate of the number of years that an investor would expect a gas-fired plant built in New York between 2021 and 2025 to remain commercially viable. FERC’s “authority to review rates [under Section 205 is] limited to an inquiry into whether the rates proposed … are reasonable—and not … whether a proposed rate schedule is more or less reasonable than alternative rate designs.” City of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984). A “just and reasonable rate is one that falls within” a “zone of reasonableness.” Me. Pub. Utils. Comm’n v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Independent Power Producers of New York, Inc. v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/independent-power-producers-of-new-york-inc-v-ferc-cadc-2022.