PJM Transmission Owners v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedJune 5, 2026
Docket25-1064
StatusUnpublished

This text of PJM Transmission Owners v. FERC (PJM Transmission Owners v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PJM Transmission Owners v. FERC, (D.C. Cir. 2026).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 25-1064 September Term, 2025 FILED ON: JUNE 5, 2026

PJM TRANSMISSION OWNERS, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

PJM INTERCONNECTION, L.L.C., ET AL., INTERVENORS

Consolidated with 25-1100

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Before: SRINIVASAN, Chief Judge, PAN and GARCIA, Circuit Judges

JUDGMENT

These petitions for review were considered on the record from the Federal Energy Regulatory Commission, the briefs and oral arguments of the parties, and the briefs of amici. The court has afforded the issues full consideration and has determined that they do not warrant a published opinion. See D.C. Cir. R. 36(d). For the reasons stated below, it is:

ORDERED and ADJUDGED that the petitions for review be DENIED.

* * *

PJM Interconnection, L.L.C. (“PJM”) is a Regional Transmission Organization (“RTO”) that operates power transmission facilities serving the Mid-Atlantic states and the District of Columbia. The Planning Protocol that governs regional expansions and improvements to PJM’s electrical grid is contained in PJM’s Operating Agreement. The Operating Agreement requires planning decisions to be approved by a Members Committee, comprising representatives from five sectors of market participants: generation owners, other suppliers, electric distributors, end-use customers, and transmission owners.

In response to a proposal from some of its Transmission Owners, PJM sought to streamline the grid-planning process by moving the Planning Protocol from the Operating Agreement to PJM’s Tariff, which would allow PJM to make planning decisions unilaterally, subject only to approval by the Federal Energy Regulatory Commission (“FERC”). To implement that change, PJM and the Transmission Owners proposed to amend the Operating Agreement, the Tariff, and the Owners Agreement (the contract under which the Transmission Owners consent to PJM’s operation of their transmission facilities). PJM and the Transmission Owners first presented their proposal to the Members Committee, which soundly rejected it.

Undeterred, PJM and the Transmission Owners presented their proposal to FERC. PJM filed (1) a complaint under section 206 of the Federal Power Act (“FPA”) arguing that it was unreasonable for the Planning Protocol to be in the Operating Agreement, 16 U.S.C. § 824e(a); and (2) an FPA section 205 filing proposing to add the Planning Protocol to the Tariff, id. § 824d. The Transmission Owners made a third filing, seeking various changes to the Owners Agreement under section 205. PJM and the Transmission Owners submitted the three filings as a package deal, underscoring that “acceptance of the [Owners Agreement] Amendments is a ‘prerequisite’ to granting the relief” sought by PJM’s filings related to the Operating Agreement and the Tariff. J.A. 73. They further stressed that the “Amendments [to the Owners Agreement] are a carefully negotiated integrated package of reforms that are not severable.” J.A. 10 n.48.

FERC rejected the package of reforms. The Commission determined that eight of the proposed amendments to the Owners Agreement were not just and reasonable. And it explained that because the deal was an “integrated package,” the disapproval of even one of those amendments was sufficient to doom the entire proposal. J.A. 10. FERC separately concluded that PJM had not carried its burden to show that the placement of the Planning Protocol in the Operating Agreement was unjust and unreasonable.

PJM and the Transmission Owners sought rehearing, which FERC granted in part. FERC reaffirmed its determinations about the eight Owners Agreement amendments, but held that the dispute about the location of the Planning Protocol was moot because FERC’s rejection of the Owners Agreement amendments required it to reject the whole package of filings.

The Transmission Owners petitioned this court for review. Most transmission owners petitioned together, but Public Service Electric and Gas Co. filed its own petition, No. 25-1100. We consolidated the Transmission Owners’ petitions, and PJM intervened on their side. Various other PJM members, led by American Municipal Power, Inc., intervened in support of Respondent FERC. We have jurisdiction under 16 U.S.C. § 825l(b).

Because we conclude that FERC’s disapproval of at least one of the proposed amendments to the Owners Agreement was not arbitrary and capricious, we uphold FERC’s rejection of the integrated package of reforms and deny the petitions for review.

I.

In rejecting the Transmission Owners’ plan to amend the Owners Agreement, FERC examined and disapproved eight proposed changes to different aspects of the existing Agreement. To prevail in this court, the Transmission Owners must “run the table” and persuade us to set aside all eight of FERC’s determinations. That is because the Transmission Owners presented an integrated, non-severable package of reforms, meaning that any single defect in the plan brings down the entire package. See J.A. 73 (noting that the Transmission Owners characterized the Owners Agreement amendments as a “prerequisite” to approval of the Planning Protocol transfer); J.A. 10 n.48 (describing the Owners Agreement amendments as a “carefully negotiated integrated package of reforms that are not severable”).

To amend the Owners Agreement, the Transmission Owners proceeded under section 205 of the FPA, which allows utilities to alter their rates and terms with FERC’s approval. When conducting a section 205 review of a filing by an RTO or utility, FERC plays only a “passive and reactive role.” Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017) (citation omitted). Nevertheless, the Transmission Owners bore the burden of demonstrating to FERC that their proposed changes to the Owners Agreement were “just and reasonable.” Me. Pub. Utils. Comm’n v. FERC, 454 F.3d 278, 283 (D.C. Cir. 2006) (quoting 16 U.S.C. § 824d(a)). Moreover, FERC was required to ensure that PJM, as an RTO, remained “independent of any market participant[s],” including its Transmission Owners. 18 C.F.R. § 35.34(j)(1). Notably, even after a section 205 approval, the amended Owners Agreement would be subject to FERC’s review under section 206 if a third party filed a complaint arguing that the approved amendments were “unjust, unreasonable, unduly discriminatory or preferential.” 16 U.S.C. § 824e(a).

In reviewing FERC’s actions, we will hold unlawful and set aside a determination that is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). “A decision is not arbitrary if it is reasonable and reasonably explained.” City of Salisbury v. FERC, 36 F.4th 1164, 1170 (D.C. Cir. 2022) (cleaned up).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
PJM Transmission Owners v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pjm-transmission-owners-v-ferc-cadc-2026.