New Jersey Board of Public Utilities v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 9, 2022
Docket20-1079
StatusPublished

This text of New Jersey Board of Public Utilities v. FERC (New Jersey Board of Public Utilities v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Jersey Board of Public Utilities v. FERC, (D.C. Cir. 2022).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued March 14, 2022 Decided August 9, 2022

No. 15-1183

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC., PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

HUDSON TRANSMISSION PARTNERS, LLC, ET AL., INTERVENORS

Consolidated with 15-1188, 16-1153, 19-1002, 20-1074, 20- 1077, 20-1082, 20-1269, 20-1351, 20-1382

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Richard P. Bress argued the cause for petitioners. With him on the joint briefs were Neil H. Butterklee, Susan J. LoFrumento, Sebrina M. Greene, Gary D. Levenson, William R. Hollaway, Lucas C. Townsend, David L. Schwartz, Eric J. Konopka, Shannon M. Grammel, Lawrence G. Acker, Gary D. Bachman, and Michael Diamond. Elias G. Farrah and Andrew F. Neuman entered appearances. 2 Kevin M. Lang, John Sipos, John C. Graham, and Alina Buccella were on the joint brief for intervenors City of New York and New York State Public Service Commission in support of petitioners.

Elizabeth E. Rylander, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, Robert H. Solomon, Solicitor, and Susanna Y. Chu, Attorney.

David M. Gossett argued the cause for intervenors American Electric Power Service Corporation, et al. in support of respondent. With him on the joint brief were John Longstreth, Donald A. Kaplan, Richard P. Sparling, Stacey Burbure, Cara J. Lewis, and Steven M. Nadel. Kenneth R. Carretta, Amanda R. Conner, Vilna W. Gaston, William M. Keyser III, Morgan Parke, Bradley Miliauskas, and P. Nikhil Rao entered appearances.

No. 20-1079

NEW JERSEY BOARD OF PUBLIC UTILITIES, PETITIONER

PUBLIC SERVICE ELECTRIC AND GAS COMPANY, ET AL., INTERVENORS

Consolidated with 20-1080, 20-1081 3

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Alec Schierenbeck, Deputy State Solicitor, Office of the Attorney General for the State of New Jersey, argued the cause for petitioner. With him on the briefs were Andrew J. Bruck, Acting Attorney General, and Paul Youchak and Nathaniel Levy, Deputy Attorneys General. Alex Moreau, Deputy Attorney General, entered an appearance.

Susanna Y. Chu, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, Robert H. Solomon, Solicitor, and Elizabeth E. Rylander, Attorney.

Lucas C. Townsend argued the cause for intervenors Consolidated Edison Company of New York, Inc., et al. in support of respondent. With him on the brief were Neil H. Butterklee, Susan J. LoFrumento, Richard P. Bress, David L. Schwartz, Eric J. Konopka, Gary D. Levenson, William R. Hollaway, Lawrence G. Acker, Gary D. Bachman, and Brian M. Zimmet.

Before: KATSAS and RAO, Circuit Judges, and SILBERMAN, Senior Circuit Judge.

Opinion for the Court filed PER CURIAM.

PER CURIAM: Part of the electricity transmission grid in northern New Jersey was aging, storm-damaged, and vulnerable to short circuits. In response, PJM Interconnection, LLC (“PJM”)—the regional transmission organization 4 responsible for managing the grid in New Jersey—authorized a series of upgrades to facilities owned by the Public Service Electric and Gas Company (“PSE&G”). One set of improvements centered on the transmission corridor between PSE&G’s Bergen and Linden switching stations; a second involved repairs to and around PSE&G’s Sewaren substation. Together, these two projects cost around $1.3 billion. Initially, PJM assigned most of the projects’ costs to entities that reroute electricity from northern New Jersey into the New York market. Thereafter, the New York-based entities gave up their rights to withdraw electricity from New Jersey, and PJM reassigned their costs to PSE&G.

The Federal Energy Regulatory Commission (“FERC” or “the Commission”) approved both rounds of cost allocations. The petitions for review in these two cases are about whether these cost allocations were “just and reasonable” under the Federal Power Act, 16 U.S.C. §§ 824d(a), 824e(a), and whether FERC’s orders were “arbitrary [and] capricious” in violation of the Administrative Procedure Act (“APA”), 5 U.S.C. § 706(2)(A). In effect, they are about who must pay the bill.

I.

The thirteen petitions for review before us challenge twenty FERC orders, involve numerous parties, implicate a series of related legal issues, and arise from a complex procedural history. We begin by setting out the regulatory and factual background needed to understand these petitions.

A.

The Federal Power Act gives FERC “jurisdiction over facilities that transmit electricity in interstate commerce,” Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. 5 Cir. 2018), and requires that the rates charged for such transmission be “just and reasonable,” 16 U.S.C. § 824d(a). “For decades, the Commission and the courts have understood this requirement to incorporate a ‘cost-causation principle’— the rates charged for electricity should reflect the costs of providing it.” Old Dominion, 898 F.3d at 1255. “[A]lthough the Commission need not allocate costs with exacting precision, the costs assessed against a party must bear some resemblance to the burdens imposed or benefits drawn by that party.” Pub. Serv. Elec. & Gas Co. v. FERC (“Artificial Island”), 989 F.3d 10, 13 (D.C. Cir. 2021) (cleaned up).

Utilities, independent system operators, and regional transmission organizations must seek approval from FERC for new rates through the process outlined in section 205 of the Federal Power Act. See 16 U.S.C. § 824d(d)–(e). Section 206 permits “the Commission [to] investigate—on its own initiative or based on a third-party complaint—whether an existing rate is ‘unjust, unreasonable, [or] unduly discriminatory.’” Artificial Island, 989 F.3d at 13 (quoting 16 U.S.C. § 824e(a)). “[U]ndue discrimination occurs [where] entities [that] are similarly situated” are charged different rates for no discernable reason. Mo. River Energy Servs. v. FERC, 918 F.3d 954, 958 (D.C. Cir. 2019) (cleaned up). In a section 206 proceeding, if FERC finds the existing rate is “unjust, unreasonable, [or] unduly discriminatory,” it must “determine the just and reasonable rate.” 16 U.S.C. § 824e(a).

B.

These petitions arise out of the legal relationships between the parties as well as the FERC-approved method by which PJM allocates the costs of major infrastructure projects on its transmission grid. 6 1.

PJM is the regional transmission organization responsible for coordinating the transmission of electricity in the mid- Atlantic region, which stretches from North Carolina to New Jersey. The dominant electricity provider in northern New Jersey is PJM-member PSE&G. Across the Hudson River, the New York grid is managed by the New York Independent System Operator, Inc. (“NYISO”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norton Ex Rel. Chiles v. Mathews
427 U.S. 524 (Supreme Court, 1976)
Pension Benefit Guaranty Corporation v. LTV Corp.
496 U.S. 633 (Supreme Court, 1990)
Alcoa Inc. v. Federal Energy Regulatory Commission
564 F.3d 1342 (D.C. Circuit, 2009)
Steel Co. v. Citizens for a Better Environment
523 U.S. 83 (Supreme Court, 1998)
Missouri River Energy Services v. F.E.R.C.
918 F.3d 954 (D.C. Circuit, 2019)
Louisiana Public Service Commission v. FERC
10 F.4th 839 (D.C. Circuit, 2021)
Long Island Power Authority v. FERC
27 F.4th 705 (D.C. Circuit, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
New Jersey Board of Public Utilities v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-jersey-board-of-public-utilities-v-ferc-cadc-2022.