Westar Energy, Inc. v. Federal Energy Regulatory Commission

473 F.3d 1239, 374 U.S. App. D.C. 256, 2007 U.S. App. LEXIS 844, 2007 WL 92698
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 16, 2007
Docket05-1193
StatusPublished
Cited by36 cases

This text of 473 F.3d 1239 (Westar Energy, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westar Energy, Inc. v. Federal Energy Regulatory Commission, 473 F.3d 1239, 374 U.S. App. D.C. 256, 2007 U.S. App. LEXIS 844, 2007 WL 92698 (D.C. Cir. 2007).

Opinion

Opinion for the Court filed by Chief Judge GINSBURG.

GINSBURG, Chief Judge.

Westar Energy, Inc. and its subsidiary Kansas Gas and Electric Company (collectively Westar) sought permission from the Federal Energy Regulatory Commission to file corrected transmission data for 2001 after the December 31, 2002 deadline for doing so. The Commission denied the request, even though it had accepted another utility’s similarly corrected filing after the deadline. Westar petitions for review, contending the Commission could not permissibly deny its request for a waiver of the deadline after it had allowed the other company to file late. Because the Commission did not meaningfully distinguish the prior case, we grant the petition for review and remand this matter for the Commission’s further consideration.

I. Background

The Commission is required by law to charge regulated entities an annual fee calculated to recoup its cost of regulating them. 42 U.S.C. § 7178. The fee charged *1241 a public utility is based upon its share of the megawatt-hours transmitted in interstate commerce by all public utilities. 18 C.F.R. § 382.201(a)-(b). The Commission requires each public utility to 'file a Form 582 by April 30 reporting the number of megawatt-hours it transmitted in interstate commerce in the preceding year and permits the utility to correct its report until the end of the calendar year in which the report was filed. Id. § 382.201(c).

On November 21, 2002 the Commission notified Kansas City Power and Light Company (KCPL) it had been selected for examination as part of an industry-wide audit of the annual fees assessed by the Commission. On August 14, 2003 the Commission issued its final report on the KCPL audit, which concluded the utility had overstated its transmission volume for 2001. The auditors recommended, and the Commission accordingly ordered, that KCPL file a corrected Form 582 for 2001. The audit report also included a July 7, 2003 letter from KCPL noting it had reviewed a draft of the report, agreed with its findings and recommendations, and had submitted on March 3, 2003 — more than two months after the filing deadline and five months before the audit was completed — a Form 582 corrected “in accordance with the findings and recommendations outlined in the ... audit.”

After learning about KCPL’s erroneous filing and its belated correction, Westar reviewed its own filings and discovered that, because of errors similar to those made by KCPL, it too had overstated its transmission volumes. On December 18, 2003 Westar filed revised Forms 582 for both 2001 and 2002 and requested a waiver of the December 31, 2002 deadline for correcting the 2001 data. The Commission accepted the revised 2002 report but refused to accept the revised 2001 report because it was filed after the deadline. Westar sought rehearing, which the Commission denied, and then petitioned this court for review.

II. Analysis

We will set aside a final decision of the Commission only if it is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). The Commission’s insistence upon strict adherence to its rules is, therefore, permissible unless its reason for refusing to waive a rule is arbitrary, capricious, or “so insubstantial as to render that denial an abuse of discretion.” Mountain Solutions, Ltd. v. FCC, 197 F.3d 512, 517 (D.C.Cir.1999) (quoting Green Country Mobilephone, Inc. v. FCC, 765 F.2d 235, 238 (D.C.Cir.1985)).

A fundamental norm of administrative procedure requires an agency to treat like cases alike. If the agency makes an exception in one case, then it must either make an exception in a similar case or point to a relevant distinction between the two cases. Green Country, 765 F.2d at 237-38; NLRB v. Washington Star Co., 732 F.2d 974, 977 (D.C.Cir.1984); cf. Colo. Interstate Gas Co. v. FERC, 850 F.2d 769, 774 (D.C.Cir.1988) (“[T]he Commission’s dissimilar treatment of evidently identical cases ... seems the quintessence of arbitrariness and caprice”).

When the Commission denied Westar’s request for a waiver, it made four points: First, “the Commission’s regulations expressly provide that corrections of the information filed on Form No. 582 must be made promptly, by the end of the calendar year in which the information was originally filed.” Second, waiving the deadline would “require the recalculation and re-billing of annual charges” and “prompt other utilities to take the same action,” thereby “undermin[ing] the certainty ... that annual charges would not *1242 be indefinitely subject to change.” Third, Westar overreads a statement the Commission made in the course of denying a petition for rulemaking, Midwest Indep. Transmission Sys. Operator, Inc., 103 F.E.R.C. ¶ 61,048, at 61,180 (2003) (“Should an audit reveal errors ... or should public utilities provide corrected data, the Commission adjusts the annual charges in the next fiscal year up or down, as appropriate”); the Commission never suggested it would “ignore the deadline expressly spelled out in its regulations.” Finally, and most important for the present proceeding, the Commission said denying Westar a waiver was not inconsistent with its allowing KCPL to make a late filing, reasoning as follows:

[T]he Commission’s auditors delayed KCPL’s filing because of their ongoing investigation. In those very different circumstances, where the Commission itself caused the late filing, it would have been inequitable to penalize the company. Westar, however, was subject to no such delay.

Westar correctly notes the Commission’s first three points apply with equal force to Westar and to KCPL — indeed to all utilities regulated by the Commission. Any one of the three might, and the three taken together certainly would, explain a Commission policy never to accept a corrected Form 582 after the deadline specified by regulation; neither singly nor in the aggregate, however, do they explain why the Commission allowed KCPL but not Westar to make a late filing.

At oral argument, Commission counsel offered (for the first time) that the Commission’s interest in finality was not adversely affected by KCPL’s late filing because the Commission does not actually issue a bill, reflecting appropriate debits and credits associated with any corrected filings, until the summer — that is, until after it had received KCPL’s revised filing but before it received Westar’s.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Butterfly Kisses Child Care Center, Inc. and Cindy Boyce
2025 VT 46 (Supreme Court of Vermont, 2025)
Kingdom v. Trump
District of Columbia, 2025
In Re Simone McNamer
2024 VT 50 (Supreme Court of Vermont, 2024)
Wilderness Society v. Haaland
District of Columbia, 2024
Baxter v. Becerra
E.D. Virginia, 2024
Grayscale Investments, LLC v. SEC
82 F.4th 1239 (D.C. Circuit, 2023)
Shawnee Tribe v. Yellen
District of Columbia, 2022
Gary Kirk v. Commissioner of SSA
987 F.3d 314 (Fourth Circuit, 2021)
Manua's, Inc. v. Eugene Scalia
948 F.3d 401 (D.C. Circuit, 2020)
Tingzi Wang v. U.S. Citizenship & Immigration Servs.
375 F. Supp. 3d 22 (D.C. Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
473 F.3d 1239, 374 U.S. App. D.C. 256, 2007 U.S. App. LEXIS 844, 2007 WL 92698, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westar-energy-inc-v-federal-energy-regulatory-commission-cadc-2007.