Champlain Parkway SW Discharge Permit - Decision on Motions

CourtVermont Superior Court
DecidedAugust 21, 2019
Docket151-11-17 Vtec 76-7-19 Vtec
StatusPublished

This text of Champlain Parkway SW Discharge Permit - Decision on Motions (Champlain Parkway SW Discharge Permit - Decision on Motions) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Champlain Parkway SW Discharge Permit - Decision on Motions, (Vt. Ct. App. 2019).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Docket No. 76-7-18 Vtec

Champlain Parkway SW Discharge Permit DECISION ON MOTIONS

The City of Burlington (“City”) seeks to renew its stormwater discharge permit for the Champlain Parkway highway project (“Project”) in Burlington, Vermont. Fortieth Burlington, LLC (“Fortieth”), a nearby property owner, appeals the Vermont Agency of Natural Resources’ (“ANR”) decision to issue the City a renewed permit. The Court here considers the City’s and ANR’s motions for partial summary judgment. The motions relate to two discrete issues raised by Fortieth in its Statement of Questions. First, the City and ANR move on the issue of whether the City’s application for renewal must be denied as untimely. The City alone moves on the second issue, asserting that it has the option of choosing whether the regulatory standards of the 2002 or the 2017 Vermont Stormwater Management Manual (“2002 VSMM” and “2017 VSMM,” respectively) apply to the Project. Fortieth opposes the motions on both issues. Judith L. Dillon, Esq., represents Fortieth in this matter. Hannah W. Smith, Esq., and Randy J. Miller II, Esq., represent ANR. Jonathan T. Rose, Esq., and Brian S. Dunkiel, Esq., appear on behalf of the City. Legal Standard This Court grants a motion for summary judgment when there is no genuine dispute over the material facts and the moving party is entitled to judgment as a matter of law. V.R.C.P. 56(a). The Court takes all of the nonmoving party’s factual allegations as true if they are supported by affidavits or other evidentiary material. V.R.C.P. 56(c); White v. Quechee Lakes Landowners’ Ass’n, Inc., 170 Vt. 25, 28 (1999) (citation omitted). Further, we draw all reasonable inferences and resolve all reasonable doubts in favor of the nonmovant. DeBartolo v. Underwriters at Lloyd’s of London, 2007 VT 31, ¶ 8, 181 Vt. 609 (citation omitted). However, nonmovants must make a specific and supported showing that a fact is genuinely disputed; bare allegations of a

1 dispute do not foreclose the possibility of summary judgment. See In re Morrill House, LLC, 2011 VT 117, ¶ 7, 190 Vt. 652; see also Webb v. Leclair, 2007 VT 65, ¶ 14, 182 Vt. 559 (citing Morais v. Yee, 162 Vt. 366, 372 (1994)). Factual Background The following facts inform the Court’s present decision on summary judgment. They are not factual findings, which must be established by trial. See Fritzeen v. Trudell Consulting Eng’rs, Inc., 170 Vt. 632, 633 (2000) (citing Booska v. Hubbard Ins. Agency, Inc., 160 Vt. 305, 309 (1993)). 1. The Champlain Parkway is a proposed public transportation project designed to connect I-189 and U.S. Route 7 to Lakeside Avenue, and to then follow Lakeside Avenue and Pine Street to Main Street, with the highway terminating in downtown Burlington, Vermont. 2. Fortieth owns property along Lakeside Avenue. 3. The Project involves the construction of new road, a shared-use path, and a variety of other traffic- and pedestrian-related features. 4. The Project is a joint effort between the City and the Vermont Agency of Transportation (“VTrans”). The Federal Highway Administration is contributing to the funding. The Timeliness of the City’s Renewal Application 5. The City originally obtained a stormwater permit for the Project from ANR in 2004. 6. After a renewal of the original permit in 2010, ANR approved the City’s application to amend the permit on October 11, 2012 (“2012 Permit”). 7. By its terms, the 2012 Permit lasted for five years, until October 11, 2017. This is the permit the City seeks to renew here. 8. The 2012 Permit and ANR’s Stormwater Management Rule for Stormwater-Impaired Waters (“Stormwater Management Rule”) contained a provision stating that applicants for renewal “shall” file their applications at least 90 days prior to the expiration of the permit. See Stormwater Management Rule § 22-309(k)(1). 9. The City submitted its application for renewal on September 15, 2017, about one month before the 2012 Permit was set to expire. 10. Through the years, ANR has consistently accepted renewal applications filed after the 90- day term has passed.

2 11. ANR’s practice is to accept applications as timely as long as they are submitted before the expiration of the active permit. 12. Jenna Olson, who supplied an affidavit bearing on this issue, submitted the City’s renewal application in her role as the Stormwater Program Manager for the City of Burlington. She has held this position since November 2016. Prior thereto, she worked as an Environmental Analyst and Stormwater District Manager in ANR’s Stormwater Program. In this capacity, she processed hundreds of renewal applications for ANR. Ms. Olson does not recall a single instance where the 90-day provision resulted in denial or dismissal of an application. 13. Padraic Monks, who has served as the Program Manager of ANR’s Stormwater Program since 2007, corroborated Ms. Olson’s statements in his May 3, 2019 affidavit. 14. ANR revised the Stormwater Management Rule through the formal rule-making process in 2019. The new version of the Rule (effective February 25, 2019) does not contain the 90-day term or any specific term related to the submission of renewal applications.1 The 2002 and 2017 VSMM 15. The 2017 VSMM provides that applicants proposing a public transportation project who “initiated right-of-way valuation activities” before January 1, 2017, to acquire land for their project can choose whether the 2002 or the 2017 VSMM applies to the project. See 2017 VSMM § 1.4. 16. Various valuation and condemnation efforts took place in the 1980s to secure land for what was called the “Southern Connector.” The current Project makes use of this land but also requires additional land acquisition. 17. VTrans began certain valuation and acquisition activities related to the Project on March 14, 2016, and possibly before. These activities included initiating appraisals and waiver valuations. 18. VTrans began negotiating with property owners on or before August 2, 2016. 19. VTrans began billing for these activities in early- to mid-2016.

1 Unless otherwise indicated, any reference to the Stormwater Management Rule in this Decision connotes the former Stormwater Management Rule in effect at the time the City applied for renewal in 2017—the version that still included the 90-day term.

3 20. VTrans finalized its supplemental right-of-way plan on April 18, 2018. It did so anticipating a May 21, 2018 necessity hearing on the land acquisition proposal. (These terms are discussed in greater detail below.) 21. Norman J. Baldwin, P.E., serves as the City of Burlington Engineer and Surveyor, as well as the Assistant Director of Public Works. Mr. Baldwin oversees the Project for the City. 22. Bruce Melvin is the Right-of-Way Acquisition Chief in VTrans’ Right-of-Way Section. He has held this position for almost eleven years and has worked in the Right-of-Way Section in various other capacities since 1979. As Right-of-Way Acquisition Chief, Mr. Melvin oversees VTrans’ right-of-way valuation and acquisition activities related to the Project. The Present Renewal Application 23. After receiving the City’s September 15, 2017 renewal application, ANR deemed the application administratively complete on September 18, 2017. 24. Beginning January 3, 2018, the application underwent public comment. 25. Fortieth submitted written comments to ANR on February 2, 2018. 26. After considering Fortieth’s comments, ANR decided to issue the City the renewal permit on June 19, 2018. 27. Fortieth appealed ANR’s decision to this Court on July 18, 2018. Discussion As indicated, the City’s and ANR’s motions require this Court to address two issues. The first involves a requirement in the City’s 2012 Permit and ANR’s Stormwater Management Rule that applications for permit renewals be submitted 90 days before the expiration of the active permit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Accardi v. Shaughnessy
347 U.S. 260 (Supreme Court, 1954)
American Farm Lines v. Black Ball Freight Service
397 U.S. 532 (Supreme Court, 1970)
Morton v. Ruiz
415 U.S. 199 (Supreme Court, 1974)
Brock v. Pierce County
476 U.S. 253 (Supreme Court, 1986)
United States v. James Daniel Good Real Property
510 U.S. 43 (Supreme Court, 1993)
Barnhart v. Peabody Coal Co.
537 U.S. 149 (Supreme Court, 2003)
Leslie v. Attorney General of US
611 F.3d 171 (Third Circuit, 2010)
In re Stowe Highlands Merger/Subdivision Application
2013 VT 4 (Supreme Court of Vermont, 2013)
Clayton v. Unsworth
2010 VT 84 (Supreme Court of Vermont, 2010)
In Re Stowe Club Highlands
668 A.2d 1271 (Supreme Court of Vermont, 1995)
In Re 1650 Cases of Seized Liquor
721 A.2d 100 (Supreme Court of Vermont, 1998)
Smith v. Winhall Planning Commission
436 A.2d 760 (Supreme Court of Vermont, 1981)
Morais v. Yee
648 A.2d 405 (Supreme Court of Vermont, 1994)
In Re Kostenblatt
640 A.2d 39 (Supreme Court of Vermont, 1994)
In Re Conway
567 A.2d 1145 (Supreme Court of Vermont, 1989)
Bacon v. Lascelles
678 A.2d 902 (Supreme Court of Vermont, 1996)
Conservation Law Foundation v. Burke
645 A.2d 495 (Supreme Court of Vermont, 1993)
In Re Mullestein
531 A.2d 890 (Supreme Court of Vermont, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Champlain Parkway SW Discharge Permit - Decision on Motions, Counsel Stack Legal Research, https://law.counselstack.com/opinion/champlain-parkway-sw-discharge-permit-decision-on-motions-vtsuperct-2019.