Brock v. Pierce County

476 U.S. 253, 106 S. Ct. 1834, 90 L. Ed. 2d 248, 1986 U.S. LEXIS 156, 54 U.S.L.W. 4476
Supreme Court of the United States·Decided May 19, 1986·No. 85-385·Published·Cited by 391 cases

Opinion

Justice Marshall

delivered the opinion of the Court.

Section 106(b) of the Comprehensive Employment and Training Act (CETA), 92 Stat. 1926, 29 U. S. C. § 816(b) (1976 ed., Supp. V), provides that the Secretary of Labor *255 (Secretary) “shall” issue a final determination as to the misuse of CETA funds by a grant recipient within 120 days after receiving a complaint alleging such misuse. The question presented in this case is whether the Secretary loses the power to recover misused CETA funds after that 120-day period has expired.

I

Before its repeal in 1982, 1 CETA provided for grants of federal funds to certain qualified entities known as “prime sponsors,” principally state and local governments, for programs “providing] job training and employment opportunities for economically disadvantaged, unemployed, or underemployed persons,” 29 U. S. C. §801 (1976 ed., Supp. V). 2 The statute contains detailed requirements concerning the operation of a CETA program and the training, pay, and terms of employment of participants in a program, see § § 823-827. A prime sponsor must submit to the Secretary a plan detailing the operation of the proposed program and containing assurances that the program will comply with the statute and with the Secretary’s regulations, § 813.

CETA grants the Secretary broad authority to ensure that CETA funds are used in accordance with the statute and regulations. The Secretary may audit a grant recipient, and in connection with such an audit may inspect records, question employees, and enter any premises upon which the program is conducted. § 835(a)(2). Any interested person, such as a participating employee, may file a complaint with the Secretary alleging that a grant recipient is failing to comply with the applicable standards. § 816.

Section 106(b), 29 U. S. C. § 816(b), which is the provision at issue in this lawsuit, requires that whenever the Secretary *256 has reason to believe, through a complaint, an audit, or otherwise, that any grant recipient is misusing CETA funds or violating any statutory or regulatory standards, the Secretary “shall investigate the matter.” 3 The same section goes on to require that the Secretary “shall” determine “the truth of the allegation or belief involved, not later than 120 days after receiving the complaint.”

II

Respondent is a county in the State of Washington that received CETA funds from 1974 through 1977 pursuant to two separate grants. On September 19, 1978, the Labor Department’s Office of Special Investigations filed an audit report concerning respondent’s first grant. That Department’s Grant Officer issued a final determination on February 13, 1981, disallowing approximately $110,000 in costs incurred by respondent on the grounds that those costs related to employees who were not eligible to participate in a CETA program. On December 11, 1978, the Department’s Office of the Inspector General filed an audit report with respect to the second grant, again raising questions concerning ineligi *257 ble participants. On April 22, 1981, the Grant Officer issued a final determination which he corrected on May 22, 1981, finally disallowing $373,000 in costs arising out of the second grant.

Respondent sought review of both final determinations before an Administrative Law Judge (ALJ) of the Labor Department. The ALJ disallowed the smaller sums of $108,000 and $265,000, respectively, in the two cases. In both cases, respondent argued that the Secretary could not order respondent to repay these sums because the Grant Officer’s final determination had been issued considerably more than 120 days after submission of the initial audit report. While conceding that the Secretary did not lose jurisdiction to make a determination after 120 days had passed, respondent argued that it had suffered prejudice because of the lengthy delay. The ALJ rejected this claim in both cases, finding no specific instances of prejudice.

The Court of Appeals for the Ninth Circuit reversed. Pierce County v. United States, By and Through Dept. of Labor, 759 F. 2d 1398 (1985). That court had previously decided, in City of Edmonds v. United States Dept. of Labor, 749 F. 2d 1419 (1985), that Congress, in enacting § 106(b), had intended to prevent the Secretary from acting on a complaint unless the Secretary’s final determination was issued within 120 days from his receipt of the complaint. In the present case, the Court of Appeals decided that the statutory command to the Secretary to issue a final determination “not later than 120 days after receiving the complaint” also required the Secretary to make a determination within 120 days when the allegation or belief is a result of the Secretary’s own audit rather than a third-party complaint. 4 This *258 decision conflicts with decisions of the Second, Seventh, and Eighth Circuits. 5 We granted certiorari to resolve the conflict, 474 U. S. 944 (1985), and we now reverse.

Ill

As Judge Friendly noted in a case raising the identical issue, the proposition that Congress intended the Secretary to lose the authority to recover misspent funds 120 days after learning of the misuse “is not, to say the least, of the sort that commands instant assent.” St. Regis Mohawk Tribe, New York v. Brock, 769 F. 2d 37, 41 (CA2 1985) (footnote omitted), cert, pending, No. 85-949. We must therefore examine carefully the statutory language and legislative history to determine whether Congress did indeed desire this somewhat incongruous result.

A

The Ninth Circuit held that the plain meaning of the statutory command that the Secretary “shall” take action within 120 days was sufficient to demonstrate that Congress meant to bar further action after that period had expired. City of Edmonds, 749 F. 2d, at 1421. Noting that “[statutory language is generally construed according to the plain meaning of the words used by Congress ‘absent a clearly expressed *259 legislative intention to the contrary/” ibid, (quoting Consumer Product Safety Comm’n v. GTE Sylvania, Inc., 447 U. S. 102, 108 (1980)), and finding no such contrary legislative intent, the Ninth Circuit held that the 120-day limit was jurisdictional.

Free access — add to your briefcase to read the full text and ask questions with AI

Brock v. Pierce County, 476 U.S. 253, 106 S. Ct. 1834, 90 L. Ed. 2d 248, 1986 U.S. LEXIS 156, 54 U.S.L.W. 4476 (1986).

476 U.S. 253 (Brock v. Pierce County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Olmos v. Holder
780 F.3d 1313 (Tenth Circuit, 2015)
John Loscombe v. City of Scranton
600 F. App'x 847 (Third Circuit, 2015)
Sierra Club v. U.S. Environmental Protection Agency
762 F.3d 971 (Ninth Circuit, 2014)
Preap v. Johnson
303 F.R.D. 566 (N.D. California, 2014)
United States v. Great American Insurance
738 F.3d 1320 (Federal Circuit, 2013)
Suntec Industries Co. v. United States
951 F. Supp. 2d 1341 (Court of International Trade, 2013)
Marine Polymer Technologies, Inc. v. Hemcon, Inc.
672 F.3d 1350 (Federal Circuit, 2012)
United States v. American Home Assurance Co.
2011 CIT 57 (Court of International Trade, 2011)
Lifestyle Enterprise, Inc. v. United States
768 F. Supp. 2d 1286 (Court of International Trade, 2011)
Catholic Charities CYO v. Chertoff
622 F. Supp. 2d 865 (N.D. California, 2008)
Saleem v. Keisler
520 F. Supp. 2d 1048 (W.D. Wisconsin, 2007)
Liu v. Novak
509 F. Supp. 2d 1 (District of Columbia, 2007)
Weininger v. Castro
462 F. Supp. 2d 457 (S.D. New York, 2006)