Consolidated Edison Co. of New York, Inc. v. Federal Energy Regulatory Commission

510 F.3d 333, 379 U.S. App. D.C. 105, 2007 U.S. App. LEXIS 29213
Court of Appeals for the D.C. Circuit·Decided December 18, 2007·No. 19-1175·Published·Cited by 12 cases

Opinion

Opinion for the Court filed by Circuit Judge ROGERS.

ROGERS, Circuit Judge:

In these consolidated cases, the Petitioners challenge two orders of the Federal Energy Regulatory Commission (“FERC”) following our decision in Consolidated Edison Co. of New York v. FERC, 347 F.3d 964 (D.C.Cir.2003). In Con Edison, the court remanded two issues to FERC for further explanation in connection with the remedies available for electric service providers that experienced substantial price increases in January-March 2000 as a result of failures in a deregulated energy market. Id. at 966-67; 972-73. In the challenged orders, FERC explained its reasoning for not invoking temporary emergency procedures (“TEP”) of the New York Independent System Operator, Inc. (“NYISO”) that allowed rebilling, and for not ordering refunds despite the NYI-SO’s violation of its tariff when pricing different types of power reserves. N.Y. Indep. Sys. Operator, Inc., 110 F.E.R.C. ¶ 61,244, 62,005-11 (2005) (“Remand Order”); N.Y. Indep. Sys. Operator, Inc., 113 F.E.R.C. ¶ 61,155, 61,609-16 (2005) (“Rehearing Order”). In view of the deference due to FERC’s determinations that the NYISO had acted reasonably in not implementing TEP because problems in the reserves market did not rise to the level of a market design flaw, and that retroactive refunds were not an appropriate remedy *336 for NYISO’s tariff violation because its pricing system protected system reliability, we conclude that FERC’s denial of a remedy was not arbitrary and capricious or contrary to law, and we deny the petitions.

I.

The issues before the court arise out of events occurring approximately two months after the NYISO began operations. Con Edison, 347 F.3d at 966-68. Between January and March 2000, transmission facility owners — i.e., load-serving entities (“LSEs”) — experienced dramatic price increases for non-spinning reserve (“NSR”) in markets administered by the NYISO. NSR is a power reserve that can be synchronized within ten minutes and is of lower quality than spinning reserve (“SR”), which is available almost immediately. In response to these price increases, NYISO presented a number of requests to FERC, including immediately suspending market-based bids and authorizing a cap for NSR bids. The LSEs complained to FERC that the NYISO had violated its tariff and “operated under several market design flaws” by failing to accept bids from other qualified suppliers, and sought correction of these practices and refunds; they also sought to compel the NYISO to invoke TEP’s remedial measures. FERC found no withholding of capacity by any supplier, but inasmuch as the market was not operating properly, approved the NSR bid cap while concluding that it lacked authority to grant retroactive relief, that the NYISO had not violated its tariff, and that it would not require the NYISO to implement TEP. Upon the LSEs’ petitions for review, this court agreed that FERC lacked authority to revise rates retroactively under the Federal Power Act (“FPA”), § 205(d), 16 U.S.C. § 824d(d), but held that FERC had not adequately explained why TEP was unavailable and had incorrectly concluded that the NYISO had not violated its tariff by linking the prices of SR and NSR reserves. The court remanded to FERC, requiring additional explanation concerning why the NYISO’s TEP tariff mechanism should not be implemented, and whether refunds should be provided for the NYISO’s violations of its tariff when pricing operating reserves. Id. at 972-73.

A.

The TEP process was established, and approved by FERC, in order to “address market design flaws, transitional abnormalities and severe operational difficulties. ...” N.Y. Indep. Sys. Operator, Inc., 88 F.E.R.C. ¶ 61,228, 61,752 (1999) (“TEP Order”). In instances where the NYISO declares that a market design flaw or transitional abnormality is occurring, extraordinary corrective actions can be taken on an interim basis, such as recalculation “of clearing prices to the level that would have been reached if a market design flaw or transitional abnormality had not arisen.... ” Id. at 61,752-755. A possible indicator of a “market design flaw” is excluding a lower-cost resource for no “valid reason.” Remand Order, 110 F.E.R.C. at 62,006. TEP requires, where possible, pri- or notice of any such actions by the NYI-SO. TEP Order, 88 F.E.R.C. at 61,753.

Free access — add to your briefcase to read the full text and ask questions with AI

Consolidated Edison Co. of New York, Inc. v. Federal Energy Regulatory Commission, 510 F.3d 333, 379 U.S. App. D.C. 105, 2007 U.S. App. LEXIS 29213 (D.C. Cir. 2007).

510 F.3d 333 (Consolidated Edison Co. of New York, Inc. v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related