Natural Gas Pipeline Company of America v. Federal Energy Regulatory Commission

765 F.2d 1155, 247 U.S. App. D.C. 1, 1985 U.S. App. LEXIS 30780
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 5, 1985
Docket84-1351
StatusPublished
Cited by11 cases

This text of 765 F.2d 1155 (Natural Gas Pipeline Company of America v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natural Gas Pipeline Company of America v. Federal Energy Regulatory Commission, 765 F.2d 1155, 247 U.S. App. D.C. 1, 1985 U.S. App. LEXIS 30780 (D.C. Cir. 1985).

Opinion

WALD, Circuit Judge:

Natural Gas Pipeline Company of America (Natural) challenges an order of the Federal Energy Regulatory Commission that rejected Natural’s efforts to recover from its ratepayers, through its cost of service, about 13 million dollars Natural spent in pursuit of three unsuccessful gas supply projects. See Natural Gas Pipeline Co. of Am., 27 F.E.R.C. ¶ 61,201 (1984). Although Natural never achieved any natural gas production from these projects and ultimately abandoned its investments in them, Natural claims that it acted prudently in attempting to develop these new sources of supply in a time of natural gas shortages. According to Natural, it should therefore be allowed to recover certain costs from these projects, amortized over five years, from its ratepayers. Natural does not seek to include the project in its rate base and has thus forgone any return on its investment or recovery of debt. It seeks only its out-of-pocket costs.

The Commission replies that a utility may ordinarily recover the costs of natural gas production projects only if the projects are “used and useful” in serving the public and the project costs consequently qualify for inclusion in rate base. See, e.g., Tennessee Gas Pipeline Co. v. FERC, 606 F.2d 1094, 1109 & n. 53 (D.C.Cir.1979), cert. denied, 445 U.S. 920, 100 S.Ct. 1284, 63 L.Ed.2d 605 and 447 U.S. 922, 100 S.Ct. 3012, 65 L.Ed.2d 1113 (1980). Production projects that never produce any natural gas are not, in the Commission’s view, “used and useful” in this sense. Similarly, the Commission has refused to consider non-recurring capital expenditures for unconventional gas production projects that fail in early stages as operating expenses. It therefore will not allow recovery from ratepayers of those expenditures through a utility’s cost of service. Money lost on such projects thus generally comes out of a utility's approved rate of return. The Commission treats the costs of failed electrical generation projects differently, but it argues that the rationale for this policy does not apply to the natural gas industry. We find the Commission’s order to be a reasoned exercise of its discretion under section 4 of the Natural Gas Act, 15 U.S.C. § 717c. We therefore deny the petition for review.

I. Background

A. The Used and Useful Standard

The Natural Gas Act permits the Commission 1 to approve charges for natural gas subject to the Commission’s jurisdiction only if those charges are “just and reasonable.” Natural Gas Act, § 4(a), 15 U.S.C. § 717c(a). In reviewing rates to de *1157 cide whether they are just and reasonable, the Commission decides what the utility’s cost of service should be, assuming that the utility is prudently managed.- In calculating the utility’s cost of service, the Commission includes its operating expenses, depreciation expenses, taxes, and a reasonable return on the net valuation of the property devoted to the public service. See P. Garfield & W. Lovejoy, Public Utility Economics 56 (1964). The Commission decides what property is devoted to the public service by asking whether the property is “used and useful” in serving the public.

As this court has frequently noted, the “used and useful” standard derives from the Supreme Court’s opinion in Smyth v. Ames, 169 U.S. 466, 18 S.Ct. 418, 42 L.Ed. 819 (1898). 2 In Smyth,

the Supreme Court articulated the guiding principle that “the basis of all calculations as to the reasonableness of rates to be charged by a [public utility] must be the fair value of the property being used by it for the convenience of the public." [Smyth, 169 U.S. at 546, 18 S.Ct. at 434 (emphasis added).] Although methods for determining values of rate base items have evolved since Smyth v. Ames, the precept endures that an item may be included in a rate base only when it is “used and useful” in providing service. In other words, current rate payers should bear only legitimate costs of providing service to them. The [Commission] early adopted the “used and useful” standard and has not departed from it without careful consideration of the wisdom of requiring current rate payers to bear costs of providing future service.

Tennessee Gas Pipeline Co. v. FERC, 606 F.2d 1094, 1109 (D.C.Cir.1979) (footnotes omitted), cert. denied, 445 U.S. 920, 100 S.Ct. 1284, 63 L.Ed.2d 605 and 447 U.S. 922, 100 S.Ct. 3012, 65 L.Ed.2d 1113 (1980). In this case, Natural does not seek to include the challenged expenses in its rate base, on which the utility’s rate of return is calculated. That step would have the effect of allowing Natural a return on its investment in failed projects, which Natural does not seek. Instead, it wishes to amortize its out-of-pocket costs, without debt or carrying charges, over five years, and then add those amortized charges to its cost of service. Thus, over five years Natural would recover the disputed costs dollar for dollar from ratepayers. 3 Of course, the exclusion of debt and carrying charges means that Natural would not completely recover its real costs. The difference between those real costs and the charges Natural proposed to include in its cost of service would be paid out of Natural’s rate of return, and consequently would be borne by Natural’s shareholders. 4 Natural correctly points out that for this reason, its proposed rate shared the risk of the failed projects between shareholders and ratepayers.

In essence, Natural argues that it should be allowed to recover, through its cost of *1158 service, prudently incurred expenses for failed gas supply projects. Because Natural acted blamelessly in incurring these expenditures, it believes the expenditures should be included in the utility’s routine cost of service. The Commission maintains that the expenditures were not used and useful to ratepayers, and are properly seen as nonrecurring capital expenditures that, under Commission precedents, may not ordinarily be included in a utility’s cost of service. In the Commission’s view, they are therefore a risk to be shouldered by the shareholders.

B. Natural’s Proposed Rate Filing

Natural is a pipeline company which transports natural gas through an elaborate interstate system.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Automobile Club of New York, Inc. v. Port Authority
887 F.2d 417 (Second Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
765 F.2d 1155, 247 U.S. App. D.C. 1, 1985 U.S. App. LEXIS 30780, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natural-gas-pipeline-company-of-america-v-federal-energy-regulatory-cadc-1985.