Algonquin Gas Transmission Company v. Federal Energy Regulatory Commission, Bay State Gas Company, Intervenors

809 F.2d 136, 1987 U.S. App. LEXIS 905
CourtCourt of Appeals for the First Circuit
DecidedJanuary 13, 1987
Docket85-2021
StatusPublished

This text of 809 F.2d 136 (Algonquin Gas Transmission Company v. Federal Energy Regulatory Commission, Bay State Gas Company, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Algonquin Gas Transmission Company v. Federal Energy Regulatory Commission, Bay State Gas Company, Intervenors, 809 F.2d 136, 1987 U.S. App. LEXIS 905 (1st Cir. 1987).

Opinion

JOHN R. BROWN, Senior Circuit Judge.

Petitioner Algonquin Gas Transmission Company (Algonquin) brings this petition for review, challenging an order by respondent Federal Energy Regulatory Commission. The Commission denied Algonquin’s request for a rate increase to its customers to recover $900,000 in expenses it incurred in an unsuccessful development of the Eascogas Liquified Natural Gas import project (Eascogas). See Algonquin Gas Transmission Co., 31 FERC II 61,221 (1985). The Commission properly applied its long-standing policy of denying recovery of costs for unsuccessful gas supply projects. Accordingly, we deny the petition for review.

Algeria and the Energy Crisis

Algonquin is a pipeline company that sells natural gas for resale in interstate commerce. Therefore, the rates Algonquin charges for those services are subject to the Commission’s jurisdiction under Sections 4 and 5 of the Natural Gas Act, 15 U.S.C. §§ 717c and 717d (1982). 1 The question here is whether Algonquin may properly charge its customers under those provisions for a gas supply project that was never completed.

Eascogas was a corporation created and jointly owned by Algonquin and other companies. Eascogas had proposed to import Liquified Natural Gas (LNG) from Algeria and deliver it to its own facilities in Staten Island, New York, and Providence, Rhode Island. From there, it would be stored, regasified, and sold to United States customers for subsequent resale in New Jersey and New England. Of the proposed import volume, twenty-eight percent was to be sold to Algonquin’s customers.

*138 The feasibility of the Eascogas project depended on the purchase of Algerian gas under low price contracts. These contracts, however, were contingent on the sponsors getting Commission approval by January 1, 1974, for at least the importation and sale aspects of the project. Absent that approval, the project could be terminated and the gas purchase contracts renegotiated at a much higher price. Based on its perception of a crisis in the world’s natural gas supply, the Commission granted to Eascogas (i) a limited authorization under Section 3 of the Natural Gas Act, 15 U.S.C. § 717b (1982), to import the LNG from Algeria, and (ii) a limited certificate of public convenience and necessity for the sale for resale of LNG. Eascogas LNG, Inc., et al, 50 FPC 2075, 2093-94 (1973). It conditioned final certification, however, on “further comprehensive and conclusive evaluations of all issues,” and made clear that it did not “endorse the economic feasibility of the entire Eascogas project.” 50 FPC at 2091.

The Eascogas project was actually a series of projects: buying, importing and selling LNG; providing transport ships to bring the gas to terminal and storage facilities; building those facilities; and providing all the attendant distribution lines. When completed, Eascogas was to have imported, over a 22-year period, some 4.76 billion MMBtu’s of Algerian LNG. 2 See Eascogas LNG, Inc. et al., 50 FPC 1921 (1973).

Unfortunately, the Algerian Connection was not to be. The contract between Algonquin and Algeria included price escalation provisions pegged to world oil prices. When the price of oil later skyrocketed, the LNG project became economically impossible. In 1977, Algonquin terminated the project. No Eascogas LNG was ever imported or sold. The only “facility” actually built for the LNG import project was the excess capacity that was included in the LNG storage facilities built for Providence Gas.

Providence in Providence

As one small part of the massive import project, Algonquin negotiated an agreement with Providence Gas Company (Providence), a local distribution company in Rhode Island. Originally, Providence had planned to construct a large 348,000 barrel storage tank as part of its distribution system. Algonquin persuaded Providence to change its plans and allow Algonquin to build its own 600,000 barrel storage tank on the site. Algonquin’s primary aim was to acquire a deep-water LNG terminal site in Rhode Island for its baseload LNG import project. In return, Algonquin guaranteed Providence 348,000 barrels of storage capacity in the 600,000 barrel tank, reserved for and subject to Providence’s use. Algonquin agreed to build the facilities and provide the services for thirty years.

Algonquin completed the storage tank facility in late 1973. Although Providence began storing its gas there, there was no Eascogas LNG to store. Algonquin prudently found alternative users for the excess capacity. Algonquin sought and received a temporary Commission authorization, valid for one year, allowing it to use that excess capacity for jurisdictional, i.e., interstate, storage services for other companies and to collect rates for such use. Algonquin LNG, Inc. & Algonquin Gas Transmission Co., 52 FPC 731 (1974). This was renewed on a yearly basis until 1982, when Algonquin received a ten-year authorization to use the excess capacity for jurisdictional storage services, Algonquin LNG, Inc. & Algonquin Gas Transmission Co., 19 FERC ¶ 61,265 (1982). It is this single storage operation that Algonquin claims has magically transformed 3 *139 the aborted Eascogas import project into a success, and thereby made Algonquin eligible for the recovery of its costs.

Algonquin Goes to Washington

In January 1980, Algonquin filed with the Commission, under Section 4 of the NGA, a request for $17.1 million per year rate increase for service to customers in New England, New York and New Jersey. Algonquin sought to recover approximately $1.5 million in Eascogas costs as “normal regulatory expenses” through an amortization allowance in its cost of service rate increase. 4 Subsequently, this amount has been scaled down to $900,000. Algonquin gave only a general description of the expenses; it did not differentiate as to costs for the excess capacity for the Providence tank. 5 Significantly, facility construction costs for the Providence storage tank were not included.

In December 1981, the AU issued her decision on Algonquin’s rate case. 17 FERC 1163,063 (1981). Relying on the prevailing Commission policy, the AU disallowed Algonquin’s Eascogas claim on the grounds that (i) the costs incurred for an unsuccessful gas supply project could not be recovered from ratepayers, but must instead be borne by stockholders, and (ii) Algonquin had not, in any event, borne its burden of showing that it had spent the money on otherwise lawful expenses. 17 FERC at 65,300.

In early 1983, the Commission announced its review of the AU’s decisions. 22 FERC H 61,279 (1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
809 F.2d 136, 1987 U.S. App. LEXIS 905, Counsel Stack Legal Research, https://law.counselstack.com/opinion/algonquin-gas-transmission-company-v-federal-energy-regulatory-commission-ca1-1987.