Transwestern Pipeline Company v. Federal Energy Regulatory Commission

784 F.2d 609, 1986 U.S. App. LEXIS 22804
CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 7, 1986
Docket84-4753
StatusPublished

This text of 784 F.2d 609 (Transwestern Pipeline Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transwestern Pipeline Company v. Federal Energy Regulatory Commission, 784 F.2d 609, 1986 U.S. App. LEXIS 22804 (5th Cir. 1986).

Opinion

CLARK, Chief Judge:

Transwestern Pipeline Company (Transwestern) challenges an order of the Federal Energy Regulatory Commission (the Commission) denying Transwestern’s attempt to recover costs incurred in developing an unsuccessful synthetic gas project by including these costs in its rates over a five-year period. Finding that Transwestern is barred from recovering these costs by the certificates of public convenience and necessity which authorized the synthetic gas project, we deny the petition for review.

I

Transwestern is engaged in the transportation and sale for resale of natural gas in interstate commerce and is regulated by the Commission under the Natural Gas Act of 1938. See 15 U.S.C. § 717(b) (1982). It purchases the majority of its gas through transmission facilities located in Texas, Oklahoma, New Mexico and Arizona, and makes sales to two principal customers, Pacific Lighting Gas Supply (PLGS) and Northwest Central Pipeline Company (NWC).

In response to the threat of an increasingly inadequate gas supply in the early 1970s, Transwestern and PLGS developed a joint venture called the Western Coal Gasification Company (WESCO). The purpose of WESCO was to construct a plant that would convert coal into synthetic gas.

On February 7, 1973, WESCO applied to the Commission for certificates of public convenience and necessity to authorize construction and operation of coal gasification facilities in San Juan County, New Mexico and the sale of approximately 250,000 Mcf per day of gas derived from the coal gasification project. Transwestern concurrently filed for authorization to construct and operate approximately sixty-seven miles of pipeline and appurtenances for the transportation of the coal gas and the resale of coal gas in a comingled stream in -interstate commerce. However, the Commission refused to issue any of the required certificates because it determined that the WES-CO project would produce artificial gas within the meaning of Section 2(5) of the Natural Gas Act, 15 U.S.C. § 717a(5) (1982), and that, therefore, the coal gasification plant, the facilities for the transportation of the artificial gas when unmixed with natural gas and the sale of this unmixed gas were all outside the Commission’s jurisdiction.

WESCO then filed an amended application seeking authorization for the sale of comingled synthetic and natural gas to *611 Transwestern customers. In Transwestern Pipeline Company, 53 FPC 1287 (“Opinion No. 728”), is modified 54 FPC 2418 (1975) (“Opinion No. 728-A”), aff'd on other grounds sub. nom. Silentman v. FPC, 566 F.2d 237 (D.C.Cir.1977), the Commission concluded that although it lacked jurisdiction over the project itself it could nonetheless assert jurisdiction over the rate to be charged for the sale of comingled gas. It also found that the WESCO project was “an absolute necessity for the consumers in California and the Midwest, absent the availability of equivalent sources.” The Commission issued certificates authorizing the WESCO sponsors “to make the transfers, sales and deliveries, and to build, connect, maintain and operate the facilities proposed and required to effectuate the transfers, sales, deliveries and transportation so authorized.” In Opinion No. 728-A the Commission gave the WES-CO applicants six months within which to accept the certificates; during this time the applicants were to seek the necessary financing and approval from the California Public Utilities Commission (CPUC).

The principal issue in both Opinions No. 728 and 728-A was the pricing of the gas to be produced by the WESCO project. The WESCO applicants sought Commission approval of a tariff that would pay "the sellers’ total cost of service, including a 15% return on equity, regardless of the amount of gas delivered.” They maintained that the only way to obtain financing for an expensive and experimental project such as WESCO was through a full cost of service tariff.

The Commission did not adopt a full cost of service tariff. Instead, in Opinion No. 728, it adopted the proposal submitted by CPUC. Under this scheme all WESCO gas produced during the first six months of the plant’s operations would be sold at a price of $1.38 per Mcf. Following this period, there would be a Section 4 proceeding 1 in which new rates would be established; these new rates would be such as to allow the applicants to recover all costs which they could show had been reasonably and prudently incurred. The Commission further determined that neither a minimum bill provision (i.e., a provision allowing the seller to bill the buyer for certain expenses despite a total failure of deliveries) nor a penalty provision (i.e., a provision penalizing the seller for falling short of expected production) should be established at that time, but it indicated that it would consider the merits of such provisions at the time that the WESCO plant began testing operations. Finally, the Commission found that the proper rate of return for the project was 15%, as the WESCO applicants urged, rather than the 13% return suggested by CPUC and the Commission staff.

The WESCO participants, in their application for rehearing, vigorously objected to Opinion No. 728. They flatly stated that the cost recovery mechanism adopted by the Commission would not permit financing of the project. The essential defect of Opinion No. 728, in their view, was that the new rates would not be set until a Section 4 hearing was held; this left the investors exposed to all the risks of regulatory lag, including the possibility that the price set in the Section 4 hearing would be based on a production level which the seller would subsequently be unable to meet due to factors “such as strikes, congressional limitations on strip mining and mechanical breakdown of facilities.” Furthermore, the Commission's refusal to decide the minimum bill and penalty provision questions before the plant was constructed was seen by the applicants as unrealistic. They argued that “[n]o responsible investor can reasonably be expected to commit funds to a project of this nature, which to use the Commission’s expression is ‘experimental,’ where the Commission has undertaken to reserve determination on whether and to what extent the recovery will be allowed of funds which have already been committed and expended.” The applicants concluded that it would only be possible to continue the project if the Commission approved a per Mcf rate adequate to recover all costs *612 at the expected production level. This rate would supersede the start-up rate and could be suspended only for one day for a hearing to determine if the costs in question had been reasonably and prudently incurred. The applicants also submitted minimum bill and penalty provisions that they indicated might reduce investors’ risk to an acceptable level.

In Opinion No. 728-A the Commission responded to the concerns raised by the WESCO applicants. It raised the start-up rate from $1.38 to $2.50 per Mcf. It also reduced the suspension period of the new rates (i.e., the rates proposed by applicants to replace the start-up rates at the end of the testing period) to one day, as requested by applicants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
784 F.2d 609, 1986 U.S. App. LEXIS 22804, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transwestern-pipeline-company-v-federal-energy-regulatory-commission-ca5-1986.