Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission

589 F.2d 186, 47 A.L.R. Fed. 817, 1979 U.S. App. LEXIS 17080
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 6, 1979
Docket78-1426
StatusPublished
Cited by17 cases

This text of 589 F.2d 186 (Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission, 589 F.2d 186, 47 A.L.R. Fed. 817, 1979 U.S. App. LEXIS 17080 (5th Cir. 1979).

Opinion

COLEMAN, Circuit Judge.

In this case Transcontinental Gas Pipe Line Corporation (Transco) petitions for review of a Federal Energy Regulatory Commission (the Commission) 1 order granting Transco a certificate of public convenience and necessity to construct and operate a major extension of its natural gas transmission network off the coast of Louisiana in the Gulf of Mexico. The certificate was subject to the condition that Transco comply with § 2.65(b) of the Commission’s General Policy and Interpretations, 15 C.F.R. § 2.65(b), which attempts to insure pipeline utilization of at least 60% of capacity by denying the company recovery of pipeline costs if the 60% load factor required by that regulation is not achieved. The legality of the 60% condition is the major issue presented in this petition, but the Commission also argues that review is premature at this time because Transco has not been “aggrieved” within the meaning of the statute which governs judicial review, 15 U.S.C. § 717r(b).

The Facts

On June 21, 1977, Transco applied for authorization to construct and operate a major extension of one of its natural gas pipelines in the Gulf of Mexico off the Louisiana coast. The estimated cost of the extension was $52,000,000, and the estimated maximum daily capacity of the extension was 240,475 million cubic feet of natural gas. Transco estimated that the load factor utilization for the second year of operation would be 65.45% of maximum capacity; for the 1978-79 winter season, 80.26%; and for the fifth year of operation, 38%. 2 Since there was no opposition to Transco’s application, the Commission held an abbreviated hearing, as it was permitted to do in such cases, and issued the certificate that same day. The authorization, however, was “subject to compliance with ... [15 C.F.R. § 2.65(b)]”, which provides:

*188 It is the intention of the Commission to enforce the [60%] requirement [of § 2.65(a)(4)] by permitting offshore pipeline facilities, certificated after the date of this order, to be included in Applicant’s cost-of-service in future rate proceedings at an average unit cost predicated upon load factors of not less than 60 percent of the annual capacity available.

Both parties agree that the import of this condition in the certificate is a requirement that Transco operate the pipeline at 60% capacity or be unable to recover part of its costs. 3 Section 2.65(a)(4) of the Commission’s General Policy and Interpretations requires an applicant to demonstrate

that its proposed facilities will be utilized, either by it individually or jointly with other pipeline companies,- at a minimum annual load factor of 60 percent of the annual capacity available by the end of a 12-month period following the installation thereof, unless a waiver is issued.

Literally, this section allows a one-year start-up period and then seems to require 60% utilization in the next year only. Neither party has adopted such an interpretation of the regulation, however, and Transco concedes that the Commission has consistently interpreted the regulation to require 60% utilization in succeeding years. Although the Commission might well clarify the wording of this regulation, deference is due an administrative agency’s interpretation of its own regulations, see, e. g., Pillsbury Co. v. FTC, 5 Cir. 1966, 354 F.2d 952, 963; and this reading of the regulation is not unreasonable.

The only other fact of apparent importance to the resolution of this case is the depreciation rate. Transco asserts in its brief, at 22, that its latest approved composite depreciation rate is 4.5%, a rate which would mean that, if straight-line depreciation were employed, the pipeline must remain in the rate base for 22 years for the company to recover its investment. The Commission responds that Transco used a depreciation rate of 10% in its application. Brief for Respondent at 38. In its reply brief, at 16-17, Transco asserts that

The 10 percent rate, however, was used to develop a price for transporting gas for others through the new pipeline. Such rate is not used as a basis for recovering the investment in the authorized facilities, since the revenues generated from the transportation services for others are credited to Transco’s overall cost-of-service in its rate proceedings.

A 10% depreciation rate implies full recovery, under straight-line depreciation, in 10 years. Because Transco asserts that utilization will drop below 10% by the fifth year of operation, any injury that it may suffer will not depend upon a depreciation rate of 4.5% or 10%.

Reviewability

Analysis of the reviewability issue must begin with the language of the statute. 15 U.S.C. § 717r(b) provides that “[a]ny party to a proceeding under this chapter aggrieved by an order issued by the Commission in such proceeding may obtain a review of such order in the court of appeals . . . .” Transco is clearly a party to the proceeding, and it is not necessary under the statute that the order be “final”. In our view, the reviewability question boils down to whether or not Transco has sustained an “injury in fact”.

The Commission’s position is that Transco has not been injured by the inclusion of this condition in the certificate and that it will not be injured, if at all, until the issuance of an order which sets just and reasonable rates. It notes that waivers are available, but there is no indication of the criteria used to evaluate waiver requests nor of the frequency with which they are granted. 4 *189 Furthermore, if the condition had not been included in the certificate, the Commission would still be free to apply the policy at the § 4 or § 5 rate proceeding.

Transco’s argument that it has been “aggrieved” proceeds along these lines: (1) its data predict a utilization of less than 60% within five years, (2) if the Commission accepts that data (and there is no indication to the contrary), then its refusal to issue a certificate without the 60% condition must mean that it does not intend to waive the condition later, (3) although there is always the possibility of a change in attitude or personnel at the Commission, this chance is somewhat remote and Transco must assume that it will not be granted a waiver, and (4) the increased risk of non-recovery of part of Transco’s $52,000,000 investment because of the uncertainty in administrative action in the future is substantial and generates an immediate injury.

The case law does not provide an easy solution to this question of reviewability. The Commission quotes language from Rochester Telephone Corp. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anr Pipeline Company v. Federal Energy Regulatory Commission, Tennessee Gas Pipeline Co., Union Gas Limited, Progas Limited, Northern Minnesota Utilities, Long Island Lighting Company, Northridge Petroleum Marketing, Inc., Great Lakes Gas Transmission Co., Texas Eastern Transmission Corporation, Intervenors. Tennessee Gas Pipeline Company v. Federal Energy Regulatory Commission, Texas Eastern Transmission Corporation, Union Gas Limited, Progas Limited, Anr Pipeline Company, Great Lakes Gas Transmission Co., Northridge Petroleum Marketing, Inc., Northern Minnesota Utilities, Intervenors. Texas Eastern Transmission Corporation v. Federal Energy Regulatory Commission, Progas Limited, Northern Minnesota Utilities, Tennessee Gas Pipeline Co., Great Lakes Gas Transmission Co., Northridge Petroleum Marketing, Inc., Anr Pipeline Company, Long Island Lighting Company, Intervenors. Great Lakes Gas Transmission Company v. Federal Energy Regulatory Commission, Tennessee Gas Pipeline Co., Texas Eastern Transmission Corporation, Anr Pipeline Company, Progas Limited, Michigan Gas Company, Long Island Lighting Company, Northridge Petroleum Marketing, Inc., Northern Minneso Ta Utilities, Independent Petroleum Association of America, Intervenors. Independent Petroleum Association of America v. Federal Energy Regulatory Commission, Texas Eastern Transmission Corporation, Tennessee Gas Pipeline Co., Progas Limited, Northern Minnesota Utilities, Transcanada Pipeline Limited, Northridge Petroleum Marketing, Inc., Great Lakes Gas Transmission Co., Union Gas Limited, Intervenors
876 F.2d 124 (D.C. Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
589 F.2d 186, 47 A.L.R. Fed. 817, 1979 U.S. App. LEXIS 17080, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcontinental-gas-pipe-line-corp-v-federal-energy-regulatory-ca5-1979.