Tenneco, Inc. And Tennessee Gas Pipeline Company v. Federal Energy Regulatory Commission

688 F.2d 1018, 1982 U.S. App. LEXIS 24834, 1982 WL 893089
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 14, 1982
Docket81-4049
StatusPublished
Cited by14 cases

This text of 688 F.2d 1018 (Tenneco, Inc. And Tennessee Gas Pipeline Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tenneco, Inc. And Tennessee Gas Pipeline Company v. Federal Energy Regulatory Commission, 688 F.2d 1018, 1982 U.S. App. LEXIS 24834, 1982 WL 893089 (5th Cir. 1982).

Opinion

CLARK, Chief Judge:

This matter started when Tenneco Inc. petitioned the Federal Power Commission (FPC) for a declaratory order validating certain natural gas transactions. The FPC’s successor, the Federal Energy Regulatory Commission (“the Commission”) eventually dismissed Tenneco’s petition, but ordered its newly formed Office of Enforcement to continue investigating all matters raised in the petition. Tenneco filed a petition for review of the dismissal order in this court. Because we conclude that Tenneco is not an “aggrieved” party as that term is used in Section 19(b) of the Natural Gas Act, 15 U.S.C. § 717r(b), we dismiss Tenneco’s petition for review.

Tenneco petitioned the FPC for a declaratory order 1 which asked it to determine whether sixty-four independent producers had obtained proper certificate and abandonment authorization under Section 7 of the Natural Gas Act, 15 U.S.C. §§ 717f(b) and (c) to permit natural gas under contract to Tennessee Gas Pipeline Company, a division of Tenneco, to be released to Channel Industries Gas Co., a subsidiary of Tenneco. The FPC responded by issuing an “Order Instituting Investigation” with respect to the matters set forth in Tenneco’s petition. The affected producers were ordered to respond to all issues raised in Tenneco’s pleading.

The FPC next issued an “Order Setting Investigation for Hearing and Granting Interventions.” That order determined that the issues raised by Tenneco’s petition could not be resolved without a full evidentiary proceeding. An administrative law judge was appointed and the matter was set for hearing. Each of the affected producers was named as a respondent in the case. Pursuant to its normal practice at that *1020 time, the FPC made no provision for a preliminary administrative investigation.

On October 1, 1977, the Federal Power Commission became the Federal Energy Regulatory Commission. See 42 U.S.C. § 7101 et seq. In response to charges that the administrative process had become “overjudicialized,” see Scenic Hudson Preservation Conference v. F.P.C., 354 F.2d 608, 620 (2d Cir. 1965), cert. denied, 407 U.S. 926, 92 S.Ct. 2453, 32 L.Ed.2d 813 (1972), the new Commission created an Office of Enforcement and prescribed rules governing the Office’s investigative duties.

After the hearing scheduled by the administrative law judge had proceeded for eight days and had been continued, it appeared that the case might be resolved by settlement. At the parties’ request, the ALJ suspended the procedural dates established for the remainder of the hearings. Settlement negotiations continued for several months without success. Meanwhile, investigators from the Office of Enforcement had been conducting a preliminary investigation into the case. In January, 1979, the Commission issued one order suspending the adjudicatory proceedings and another order directing the newly created Office of Enforcement to conduct an investigation into all matters originally dealt with in the adjudicatory proceeding. Tenneco and other parties involved in the case unsuccessfully petitioned for a rehearing. In a written opinion the Commissioners stated: “Had Tenneco’s petition for a declaratory order been filed in 1979 rather than 1977, we should in all probability have referred it in short order to the Office of Enforcement for a private investigation to precede such subsequent adjudicatory proceedings . . . . ” (emphasis original) The Commission concluded that an adequate record could not be developed without a thorough investigation by the Office of Enforcement, and that maintaining dual investigations into the same matters would result in a needless duplication of staff effort. It therefore suspended the adjudicatory proceedings until an enforcement staff investigation could be conducted.

Tenneco petitioned this court to review the Commission’s orders. The Commission moved to dismiss Tenneco’s petition, arguing that the orders were interlocutory and did not aggrieve Tenneco. We dismissed Tenneco’s petition for review. Tenneco Inc. v. Federal Energy Regulatory Commission, No. 79-2910 (April 21, 1980).

While all this was going on, the Commission brought a separate action in United States District Court for the District of Columbia against Mobil Oil Corporation, one of the respondents in the Tenneco proceeding. That suit involved gas purchases unrelated to the investigation pending before the Commission. Mobil and the Commission entered into settlement negotiations concerning both the case before the district court and any matters which might come before the Commission. Tenneco sought to intervene in the Mobil district court action and participate in the ongoing settlement negotiations. The district court concluded that Tenneco had failed to show “a cognizable legal interest in the subject matter of the action” and denied Tenneco’s motion to intervene. The court did, however, permit Tenneco to appear as an amicus curiae.

The District of Columbia district court approved a consent agreement presented by the Commission and Mobil. Subsequently, the Commission entered an order pursuant to that consent agreement severing and terminating all proceedings before it as to Mobil. Tenneco petitioned for a rehearing of the Commission’s order. The Commission rejected the petition. It held that Tenneco was not aggrieved by the order.

The Commission dismissed the adjudicatory proceeding against Tenneco, but expressly stated that all matters raised in that docket would continue to be investigated by the Office of Enforcement. The Commission stated its expectation “that the Office of Enforcement will carefully and expeditiously recommend resolution” of the issues. The Commission pointed out that the order was not intended to affect the parties’ substantive rights, adjudicate any facts, determine that anyone had violated the law, or *1021 require any person to perform any act. It concluded that “[sjhould the need arise for further Commission adjudicatory proceedings, we will be free to do so.”

Tenneco petitioned for a rehearing of the dismissal order. The Commission entered its response in an “order Denying in Part and Rejecting in Part Petition for Rehearing.” The Commission reaffirmed its decision to terminate the adjudicatory proceeding pending the outcome of the investigation. It concluded that, given the Office of Enforcement’s ongoing investigation, Tenneco was not aggrieved by the decision to dismiss the adjudicatory proceedings.

Tenneco then filed a petition requesting this court to review all orders the Commission had issued in the case. We ordered that the Commission’s motion to dismiss the petition on the ground that Tenneco was not aggrieved by the Commission’s order be carried with the case. We now hold that Tenneco was not aggrieved by the Commission’s order and dismiss Tenneco’s petition for review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Gas & Elec v. FERC
Fifth Circuit, 1997
New Mexico Energy v. FERC
Fifth Circuit, 1997
People's Counsel v. Public Service Commission
474 A.2d 1274 (District of Columbia Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
688 F.2d 1018, 1982 U.S. App. LEXIS 24834, 1982 WL 893089, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tenneco-inc-and-tennessee-gas-pipeline-company-v-federal-energy-ca5-1982.