Public Service Commission v. Federal Energy Regulatory Commission

866 F.2d 487, 275 U.S. App. D.C. 286
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 27, 1989
DocketNos. 87-1706, 88-1007
StatusPublished
Cited by1 cases

This text of 866 F.2d 487 (Public Service Commission v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Service Commission v. Federal Energy Regulatory Commission, 866 F.2d 487, 275 U.S. App. D.C. 286 (D.C. Cir. 1989).

Opinion

Opinion for the Court filed by Circuit Judge STEPHEN F. WILLIAMS.

STEPHEN F. WILLIAMS, Circuit Judge:

The Natural Gas Act, 15 U.S.C. §§ 717 et seq. (1982), sets up a carefully balanced mechanism for the Federal Energy Regulatory Commission’s supervision of natural gas company rates. Under § 4, 15 U.S.C. § 717c, a company may file rate changes, but these are subject to Commission review to determine whether they are “just and reasonable.” Under § 5, 15 U.S.C. § 717d, the Commission may take the initiative and determine that rates already filed are not just and reasonable and may issue an order changing them.

The two modes of Commission review entail quite different procedures. Under § 4 the company has the burden of showing that the proposed rates are just and reasonable, while under § 5 the Commission must show that the rates it would alter are not just and reasonable, and that the ones it seeks to impose are. The unifying principle is that the proponent of change bears the burden. Under § 4, moreover, the Commission may suspend the rates for up to five months while deciding the issue; even after the end of any suspension period, if the company has filed increased rates, the Commission may order them collected under bond and may order refunds if it ultimately rejects the company’s proposed rates. Under § 5 there is no provision for refund of rates collected while the Commission hears the matter.

On four occasions in the last three years this court has reviewed Commission efforts to compromise § 5’s limits on its power to [288]*288revise rates. On each the court has repelled the Commission’s gambit. This is number five.

I.

Ozark Gas Transmission System is a partnership that transports natural gas for its partners through an interstate pipeline in southeastern Oklahoma and northeastern Arkansas. It neither purchases nor resells gas. In July 1981 FERC issued a certificate of public convenience and necessity to Ozark, pursuant to § 7 of the Act, 15 U.S.C. § 717f. It approved a demand rate that would recover Ozark’s operating and maintenance expenses, certain taxes, and amortization and interest on its debt. But as Ozark’s rate base was expected to decline through depreciation, there was concern that a fixed commodity rate would lead to an unreasonable return on equity. Accordingly FERC rejected permanent rates for Ozark. Instead it established interim rates, with the requirement that Ozark file a rate case under § 4 within two years of the start of service. Ozark Gas Transmission System, Opinion No. 125, 16 F.E.R.C. 1161,099 at 61,198-99 (1981).1 This court affirmed. Public Service Commission of New York v. FERC, 680 F.2d 252 (D.C.Cir.1982) {per curiam).

On March 1, 1984 Ozark filed under § 4, proposing to retain its original rates. The Commission staff objected that Ozark should be compelled to refile its rates under § 4 every three years, giving the Commission an opportunity for periodic rate review under § 4’s favorable procedural provisions. Public Service Commission of New York (“PSCNY”) agreed with the staff, but sought an additional protection. Rather than using the book value of the relevant assets at the start of the relevant period, PSCNY sought to require Ozark to use an “average” rate base, i.e., a value reflecting the expected decline of the rate base through depreciation over the period the rates were to be in effect.

The administrative law judge approved Ozark’s rates and, on the ground that FERC did not have the authority to sidestep the strictures of §§ 4 and 5, refused to follow the staffs refiling recommendation. Ozark Gas Transmission System (Initial Decision), 32 F.E.R.C. ¶ 63,019 (1985). The opinion noted, however, that concerns regarding the declining rate base were “legitimate and worthy of full consideration.” Id. at 65,053. The AU suggested that in their exceptions to the initial decision the parties might consider, as a device for addressing the declining rate base, a “cost-of-service” commodity rate, i.e., one under which a pipeline recovers its actual costs plus an allowed return. Id.

The Commission set aside the AU’s disposition, and approved Ozark’s proposed rates, subject to a requirement that Ozark file rates under § 4 every three years. Ozark Gas Transmission System, Opinion No. 273, 39 F.E.R.C. ¶ 61,142 (1987). FERC held that its authority under § 5 provided “insufficient protection by itself, to protect consumers from the payment of excessive rates for periods prior to the completion of a section 5 proceeding,” id. at 61,512, and concluded that “good cause” existed to require periodic § 4 refilings, id. It also rejected PSCNY’s proposal that Ozark be required to use an average rate base.

On rehearing, the Commission referred to statutory provisions that, in its view, justified the refiling requirement: §§ 10, 14 and 16 of the Act, 15 U.S.C. §§ 717i, 717m, 717o. Ozark Gas Transmission System, Opinion No. 273-A, 41 F.E.R.C. 1161,207 at 61,566 (1987). § 16 gives the Commission power to perform “acts ... necessary or appropriate to carry out the provisions” of the Act, and also to specify forms to be filed, together with the information they must contain and their due dates. The other two sections invoked— which respectively give the Commission authority to require the filing of periodic reports on specified subjects and to investigate potential statutory violations — are now only marginally relevant, as the Commission here abandons any claim that either of them independently authorizes its [289]*289action in this case and asserts only that they “underscore[ ]” its authority under § 16. See Respondent’s Brief at 29 n. 13.

Ozark petitions for review on the ground that FERC’s § 4 refiling requirement cannot stand. We agree. PSCNY petitions on the ground that the Commission was arbitrary and capricious in rejecting its average rate base proposal. As that aspect of the Commission’s decision was plainly based on its view that the refiling requirement was an adequate solution, we remand the case for the Commission to assess the problem and consider appropriate and lawful solutions.

II.

Section 16 is a broad grant of authority ancillary to FERC’s basic powers under the Natural Gas Act. It provides in pertinent part:

The Commission shall have power to perform any and all acts, and to prescribe, issue, make, amend, and rescind such orders, rules, and regulations as it may find necessary or appropriate to carry out the provisions of this chapter. Among other things, such rules and regulations may define accounting, technical, and trade terms used in this chapter; and may prescribe the form or forms of all statements, declarations, applications, and reports to be filed with the Commission, the information which they shall contain, and the time within which they shall be filed____

15 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
866 F.2d 487, 275 U.S. App. D.C. 286, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-commission-v-federal-energy-regulatory-commission-cadc-1989.