Gilbane Building Co. v. Stamford Towers, No. Cv91 0118788 S (Nov. 18, 1996)

1996 Conn. Super. Ct. 9029
CourtConnecticut Superior Court
DecidedNovember 18, 1996
DocketNo. CV91 0118788 S
StatusUnpublished

This text of 1996 Conn. Super. Ct. 9029 (Gilbane Building Co. v. Stamford Towers, No. Cv91 0118788 S (Nov. 18, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gilbane Building Co. v. Stamford Towers, No. Cv91 0118788 S (Nov. 18, 1996), 1996 Conn. Super. Ct. 9029 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION CT Page 9030 In September, 1986, the defendant, Stamford Towers Limited Partnership (hereinafter "STLP"), engaged Edlar Inc. (hereinafter "Edlar") to develop a certain piece of real estate known as Stamford Towers in Stamford, Connecticut, consisting of two high-rise commercial buildings. The contract between STLP and Edlar is known as the Development Agreement. On May of 1987, Edlar contracted with the plaintiff Gilbane Building Company (hereinafter "Gilbane"), to construct the project. The contract between Edlar and Gilbane is known as the Construction Management Agreement, (hereinafter "CMA").

During the course of construction problems developed because Edlar had agreed in the Development Agreement to deliver the two buildings to STLP for a guaranteed maximum price; but in the CMA Edlar had agreed to pay Gilbane the actual costs of construction plus an $850,000 fee.

Edlar's dilemma worsened as the buildings neared completion. Disputes with both STLP and Gilbane. In an effort to complete construction despite these differences, the parties entered into a Recision and Escrow Agreement, under which the three parties resolved to continue the construction without prejudice to their respective legal positions.

A consolidated arbitration of the claims by STLP against Edlar and Edlar against Gilbane was ordered by the New York Supreme Court to take place in New York before a five member arbitration panel. Arbitration hearings commenced on or about September 12, 1989 and continued for the next three years. During the course of the arbitration, construction continued until completion of the project. After 93 evidentiary hearings, 10,000 pages of transcript and 2,700 pre-marked exhibits, the panel issued a single award on January 22, 1993. The panel found for Gilbane and STLP to recover damages from Edlar. Gilbane was awarded $1,906,444.00 against Edlar, $28,326.00 for stenographic services and $620,650.00 for the cost of its appointed arbitrators. STLP was awarded $7,743,185.00 on its claim against Edlar as well as its stenographic costs and appointed arbitrators costs. The panel additionally found that STLP properly terminated Edlar pursuant to the terms of the Development Agreement. Judgment in accordance with the arbitration award was entered on September 7, 1993. Neither Gilbane nor STLP recovered any of their awards from Edlar. Edlar proved to be insolvent and this CT Page 9031 lawsuit followed.

In the instant lawsuit, Gilbane seeks damages from STLP in six counts. The first count is a foreclosure of Gilbane's mechanic's lien; the second count is for breach of contract, specifically, STLP's breach of what has been referred to at trial as the "Recision and Escrow Agreement"; the third count is for unjust enrichment; the fourth count sounds in fraud; the fifth count claims damages under CUTPA; and the sixth count is for breach of the CMA specifically Article XVII therein.

STLP answered Gilbane's complaint denying it was indebted to Gilbane, plead numerous special defenses and counterclaims. Gilbane replied that it didn't owe any monies to STLP.

A third party plaintiff, Moliterno Stone Sales, Inc. (hereinafter Moliterno), a subcontractor of Gilbane seeks by way of a cross-claim to foreclose its own., mechanic's lien.

Moliterno for the contract sum of $1,555,303.00 agreed with Gilbane to perform the "granite work" on the project. This work included the placement of precast concrete "pavers" in specified portions of the plazas.

Moliterno being one of the last of several subcontractors to work on the plazas was owed $155,674.00. This sum represented only the unreleased 10% contractual retainage withheld by STLP.

All of Moliterno's periodic payment requisitions, as submitted through Gilbane, had been approved and paid. Nevertheless, because the Stamford Towers buildings began to leak into the garage below the upper plaza STLP refused to release Moliterno's retainage. Once again STLP denied any duty to release the retainage and claims damages from Moliterno for the costs to repay alleged defective works by Moliterno.

MOLITERNO'S LIEN

By stipulation, Stamford Towers and Moliterno have disposed of many of the potential issues concerning Moliterno's technical compliance with Connecticut's mechanic's lien law (Conn. Gen. Stat. § 49-33, et seq.). Specifically, Stamford Towers and Moliterno have agreed that:

(a) Moliterno performed services and/or furnished CT Page 9032 materials in connection with the Stamford Towers project at 680-750 Washington Boulevard, Stamford, commencing on August 1, 1988, pursuant to a written contract between Moliterno and Gilbane.

(b) Moliterno claims it is owed $155,674.00, plus interest, for services and materials provided pursuant to its contract with Gilbane.

(c) On December 31, 1990, Moliterno filed a Certificate of Mechanic's Lien (Tr. Ex. 52) on the Stamford Land Records, duly executed and sworn to.

(d) Within the time period described, Moliterno served Stamford Towers with a copy of the lien certificate and served Stamford Towers and Gilbane with written notice of its intent to claim a lien.

(e) Moliterno's foreclosure of its lien was brought within one year of the date the lien was filed.

(f) At the time of commencement of the foreclosure, Moliterno filed and served a notice of lis pendens.

Only two issues remain for the trial court. The first is, was the lien filed within "the requisite time period" as required under the statutes and if so, the second issue is to determine the amount of the debt.

THE REQUISITE TIME PERIOD

Conn. Gen. Stat. § 49-34 provides in pertinent part:

"A mechanic's lien is not valid unless the person performing the services or furnishing the materials (1) within ninety days after he has ceased to do so, lodges with the town clerk . . . a certificate in writing. . . ."

Moliterno's mechanic's lien was filed on December 31, 1990. Thus, for its lien to be valid, Moliterno would had to have performed services or furnished materials in connection with the Stamford Towers project on or after October 2, 1990 (the ninetieth day prior to the date of filing of the lien).

The evidence before the court established that Moliterno's CT Page 9033 forces were working on the job at the request of the owner's agent until at least the week ending November 21, 1990 (within the period of time), however, STLP claimed that that work was so trivial or inconsequential as compared to the work performed relative to the entire upper and lower "plazas", that it should not be found to extend the time for filing the lien.

While the court agrees with STLP that the work in question was trivial, nevertheless, the work performed was required under the general contract.

In Martin Tire Rubber Co. v. Kelly Tire Rubber Co.,9 Conn. 396, 122 A. 102 (1923), the owner asserted the then 60-day deadline as barring a lien because the only work performed within the 60-day period, and after "substantial completion," was one carpenter's labor for one day. The Supreme Court offered the following analysis:

"The defendant misconceives the proper application of the rule of substantial completion in determining the time from which the sixty-day period should be computed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Parklane Hosiery Co. v. Shore
439 U.S. 322 (Supreme Court, 1979)
Jim Beam Brands Co. v. Beamish & Crawford Ltd.
937 F.2d 729 (Second Circuit, 1991)
W. J. Megin, Inc. v. State
434 A.2d 306 (Supreme Court of Connecticut, 1980)
Rene Dry Wall Co. v. Strawberry Hill Associates
438 A.2d 774 (Supreme Court of Connecticut, 1980)
Biller v. Harris
161 A.2d 187 (Supreme Court of Connecticut, 1960)
A. Sangivanni & Sons v. F. M. Floryan & Co.
262 A.2d 159 (Supreme Court of Connecticut, 1969)
Conaway v. Prestia
464 A.2d 847 (Supreme Court of Connecticut, 1983)
Southern New England Contracting Co. v. State
345 A.2d 550 (Supreme Court of Connecticut, 1974)
Heslin v. Connecticut Law Clinic of Trantolo & Trantolo
461 A.2d 938 (Supreme Court of Connecticut, 1983)
Cacace v. Morcaldi
435 A.2d 1035 (Connecticut Superior Court, 1981)
The Martin Tire Rubber Co. v. the Kelly Tire Rubber
122 A. 102 (Supreme Court of Connecticut, 1923)
Soule v. Borelli
68 A. 979 (Supreme Court of Connecticut, 1908)
Kelly v. Alling
80 A. 782 (Supreme Court of Connecticut, 1911)
Hubbell, Hall & Randall Co. v. Pentecost
93 A. 672 (Supreme Court of Connecticut, 1915)
Wesleyan University v. Rissil Construction Associates, Inc.
472 A.2d 23 (Connecticut Appellate Court, 1983)
Hunter v. Smith
7 Conn. Super. Ct. 157 (Connecticut Superior Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 9029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gilbane-building-co-v-stamford-towers-no-cv91-0118788-s-nov-18-1996-connsuperct-1996.