The Martin Tire Rubber Co. v. the Kelly Tire Rubber

122 A. 102, 99 Conn. 396, 1923 Conn. LEXIS 106
Supreme Court of Connecticut·Decided July 27, 1923·Published·Cited by 26 cases

Opinion

Wheeler, C. J.

Defendant claims that the facts stated in paragraphs eight and eleven of the finding should be corrected because they are inconsistent and found without evidence. The petitioner, on the other hand, says that these are findings of fact made upon undisputed evidence. The statement in paragraph eight, that the petitioner continued to furnish services in the completion of the contract for the construction of the building, we regard as a mixed conclu *399 sion of law and fact; that the conclusion of fact must have been found from the other facts in the finding, and hence the conclusion is reviewable. The statement in paragraph eleven, that the services of the superintendent were rendered in completion of the contract for the construction of the building, is the same sort of conclusion. Both of these conclusions depend upon the conclusion to be drawn from the subordinate facts together with a construction of the building contract, and the application of the subordinate facts to the contract so construed.

The defendant rests its appeal upon what it holds to be two principles of our law of mechanics liens which make the lien of the petitioner invalid. First, that since the building had been substantially completed on March 9th, the lien began to run from that date, and hence the sixty-day period in which the lien could be filed had expired. Second, that the only services detailed in the finding rendered after March 9th were for the civil engineer, who was the superintendent on the job, and for a carpenter for one day, and did not entitle the petitioner to a mechanic’s lien. The defendant misconceives the proper application of the rule of substantial completion in determining the time from which the sixty-day period should be computed. The period for filing the lien under our statute (§§ 5217, 5218) “for material furnished or services rendered in the construction, raising, removal or repairs of any building, ” will be computed, ordinarily, from the date of the last item of material furnished or services rendered. The rule is one to be applied fairly to both the lienor and the owner. If, after the work is substantially done, the claimant for the material furnished or services rendered shall unreasonably delay the completion of the work, the date of beginning of the sixty-day period will be taken *400 as the date when the work was substantially done. No trivial or inconsequential service or work done after the substantial completion of the building will extend the time for claiming the lien, or revive an expired lien when an unreasonable period has elapsed since the substantial completion. If the article furnished or the service rendered be trivial, but be required by the terms of the contract of building, this fact will be taken into consideration in determining whether the elapsed period be unreasonable or not. And “where a service is performed or material furnished at the request of the owner, it will extend the time for claiming a lien or will revive an expired lien, as to a contract . . . substantially performed.” 35 L. R. A. (N. S.) 904 note. Thus in Nichols v. Culver, 51 Conn. 177, it is held that trivial work done or material furnished will be sufficient to extend the time for filing the lien if done at the request of the owner, and not for the mere purpose of saving his lien.

We have held in Flint v. Raymond, 41 Conn. 510, and Sanford v. Frost, 41 Conn. 617, that there must be no unreasonable delay in completing work which has been substantially done, and that “work done after such delay will not be considered in fixing the sixty days allowed for recording the lien.” In the first of these cases the delay was nine months and the work done covered three hours’ work, and in the second the delay was six months, and the work done of trifling value. In Cole v. Uhle, 46 Conn. 296, the work was substantially completed November 15th, except as to two items, one of which was done on December 1st and the other February 27th, and in distinguishing this case from Flint v. Raymond and Sanford v. Frost, we said: “We think the case at bar is distinguishable from both of the cases above mentioned, not only in that the amount of work done after the *401 time for fulfilling the contract was greater, while the delay was comparatively short, but more especially in the fact that the reason for the delay must be regarded as sufficient against the original party to the contract, at whose special instance and request the work was so postponed.” In Peck v. Brush, 90 Conn. 651, 656, 98 Atl. 561, we say: “We have held that the time for filing the certificate of lien begins to run from the substantial completion of the furnishing materials or services, and is not extended by trivial work deferred, or by work or materials furnished for the same building under a new contract with a different contractor and completed after such substantial completion.” See, also, Nichols v. Culver, 51 Conn. 177, 183; note, 35 L. R. A. (N. S.) 904; Phillips on Mechanics’ Liens, § 229; Boisot on Mechanics’ Liens, § 481; 27 Cyc. 144; 18 R. C. L. § 62, p. 931.

To determine whether the period of the running of the mechanic’s lien should begin with the date of the substantial completion of the contract, we must first ascertain the date of substantial completion. No express finding has been made in the instant case on this point. In its absence, defendant wishes us to draw the conclusion that there had been a substantial completion on March 9th, 1921. Assuming that this was a conclusion which we were entitled to draw upon the finding before us, we could not conclude that there had been an unreasonable delay in finishing the contract, or that the work done and services rendered after March 9th were trivial.

Free access — add to your briefcase to read the full text and ask questions with AI

The Martin Tire Rubber Co. v. the Kelly Tire Rubber, 122 A. 102, 99 Conn. 396, 1923 Conn. LEXIS 106 (Colo. 1923).

122 A. 102 (The Martin Tire Rubber Co. v. the Kelly Tire Rubber) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cianci v. ORIGINALWERKS, LLC
16 A.3d 705 (Connecticut Appellate Court, 2011)
Tougher Industries v. Learning Corridor, No. Cv 02-0819779s (Mar. 19, 2003)
2003 Conn. Super. Ct. 3729 (Connecticut Superior Court, 2003)
Carmel Homes v. Bednar, No. Cv 99-0079393 S (Oct. 1, 2001)
2001 Conn. Super. Ct. 13475 (Connecticut Superior Court, 2001)
Piazza v. Hadley Sutherland, No. Cv 00 83296 (Jan. 17, 2001)
2001 Conn. Super. Ct. 893 (Connecticut Superior Court, 2001)
Interior Technology v. Baker Prop. Ld., No. Cv96 0053588s (Feb. 9, 1999)
1999 Conn. Super. Ct. 1483 (Connecticut Superior Court, 1999)
F. B. Mattson Co. v. Tarte
719 A.2d 1158 (Supreme Court of Connecticut, 1998)
Anthony Julian Railroad Construction Co. v. Mary Ellen Drive Associates
717 A.2d 294 (Connecticut Appellate Court, 1998)
F. B. Mattson Co. v. Tarte
704 A.2d 813 (Connecticut Appellate Court, 1997)
Jackson v. Fortunato, No. Cv 88-0096695 (Apr. 8, 1997)
1997 Conn. Super. Ct. 3925 (Connecticut Superior Court, 1997)
F.B. Mattson Co. v. Tarte, No. Cv96-0131291 (Feb. 7, 1997)
1997 Conn. Super. Ct. 1041 (Connecticut Superior Court, 1997)
Gilbane Building Co. v. Stamford Towers, No. Cv91 0118788 S (Nov. 18, 1996)
1996 Conn. Super. Ct. 9029 (Connecticut Superior Court, 1996)
Glover v. Homeside Court Development, No. Cv 91-0315349 (Nov. 17, 1995)
1995 Conn. Super. Ct. 12520-P (Connecticut Superior Court, 1995)
Erickson v. Real Drywall, Inc., No. Cv 94-0073607s (Sep. 15, 1995)
1995 Conn. Super. Ct. 9985 (Connecticut Superior Court, 1995)
Torrington Lumber Company v. Hobson, No. 0059377 (Aug. 25, 1992)
1992 Conn. Super. Ct. 7983 (Connecticut Superior Court, 1992)
Connecticut Bank Tr. v. Ralto Developers, No. 300841 (May 15, 1992)
1992 Conn. Super. Ct. 4437 (Connecticut Superior Court, 1992)
H. G. Bass Associates, Inc. v. Ethan Allen, Inc.
601 A.2d 1040 (Connecticut Appellate Court, 1992)
Atenasio v. Modern Counter Top Cab., No. Cv90-0701176 (Nov. 8, 1991)
1991 Conn. Super. Ct. 10806 (Connecticut Superior Court, 1991)
Coastal Plumbing-Heating v. Habetz, No. Cv90-030922 (Aug. 28, 1991)
1991 Conn. Super. Ct. 7116 (Connecticut Superior Court, 1991)
McKechnie v. Vendever, No. Cv-88-27 80 73 (Jul. 25, 1990)
1990 Conn. Super. Ct. 742 (Connecticut Superior Court, 1990)