Tougher Industries v. Learning Corridor, No. Cv 02-0819779s (Mar. 19, 2003)

2003 Conn. Super. Ct. 3729, 34 Conn. L. Rptr. 433
CourtConnecticut Superior Court
DecidedMarch 19, 2003
DocketNo. CV 02-0819779S
StatusUnpublished

This text of 2003 Conn. Super. Ct. 3729 (Tougher Industries v. Learning Corridor, No. Cv 02-0819779s (Mar. 19, 2003)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tougher Industries v. Learning Corridor, No. Cv 02-0819779s (Mar. 19, 2003), 2003 Conn. Super. Ct. 3729, 34 Conn. L. Rptr. 433 (Colo. Ct. App. 2003).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The plaintiff, Tougher Industries, Inc. (Tougher), is a New York mechanical contractor which contracted with general contractor, Gilbane Building Company (Gilbane), in April 1999, to perform mechanical work for the defendant, The Learning Corridor Corporation (LCC), in connection with the construction of a public school facility in Hartford, Connecticut known as the Learning Corridor project. The Learning Corridor is a site of approximately 33 acres which, as constructed, consists of a magnet math, science and technology high school, middle school, Montessori elementary school, magnet theater and performing arts high school, commons building, parking garage and retail space beneath the garage. Pursuant to the contract between Gilbane and LCC, dated October 3, 1997, Tougher was to be paid the sum of $10,440,000 for its work, which it began in the spring of 1999.

The city of Hartford took title to the site on or about March 5, 1999 and, on August 17, 2000, the city entered into a master lease with LCC for the site. By the fall of 2000, the schools were operational. On September 24, 2001, Tougher filed a mechanic's lien in the amount of $5,382,295 against LCC's leasehold interest, pursuant to General Statutes § 49-33.1 On or about September 20, 2002, Tougher commenced an action seeking to foreclose upon the lien and, on October 2, 2002, LCC filed the instant motion to discharge the lien. By agreement of the parties, a hearing was held to determine the validity of the lien. If the lien is found to be valid, the parties will further address the amount of the lien.2

LCC claims that the mechanic's lien is invalid for six reasons. LCC claims (1) that because no work was performed within 90 days of the placement of the lien, it fails to comply with the requirements of General Statutes § 49-343; (2) that Tougher waived its right to lien the property pursuant to Article 3.6 of the contract; (3) that Tougher waived its right to file a mechanic's lien by executing periodic lien waivers to Gilbane throughout the course of the project; (4) that because on March CT Page 3730 31, 1999, the date when Tougher commenced work on the project, LCC was not a lessee of the property, the lien constitutes a lien on after-acquired property; (5) that the city owns the underlying fee interest in the site and public policy precludes the placement of a mechanic's lien on public property; and (6) that § 49-33 (h), the statutory provision permitting the placement of a mechanic's lien on a leasehold interest, does not apply to the present contract because the contract was entered into prior to October 1, 1999, the effective date of the statute.

LCC seeks to discharge the lien pursuant to General Statutes § 49-35a which states that "if an action for foreclosure of the lien is pending before any court, any party to that action may, at any time, prior to trial . . . move that the lien be discharged or reduced." Section 49-35a (c) provides, in pertinent part, that: "Upon the hearing held on the application or motion set forth in Section 49-35a, the lienor shall first be required to establish that there is probable cause to sustain the validity of his lien. Any person entitled to notice under Section 49-35a may appear, be heard and prove by clear and convincing evidence that the validity of the lien should not be sustained." As noted by Tougher, the probable cause standard is the same as that utilized in prejudgment remedy hearings. See Pero Building Co., Inc. v. Smith, 6 Conn. App. 180,182-83, 504 A.2d 524 (1986).

1.
LCC's first argument is that the lien is invalid because it fails to meet the statutory requirement that the lien be placed within 90 days after work ceases. See General Statutes § 49-34 (1). In the present case, Tougher's certificate and notice of lien states that the last day of work was June 27, 2001. The lien was filed with the Hartford town clerk on September 24, 2001, 89 days later.

According to Tougher's President, William H. Tougher, Jr., the work performed on June 27, 2001 consisted of the installation of two victaulic couplings to connect two pipes together, due to Tougher having previously installed the wrong couplings causing the pipe to leak. Mr. Tougher also testified that, notwithstanding the notice and certificate, other work had been done after June 27, 2001, by Tougher's subcontractor, Johnson Controls, Inc. Edward Carvalho, a representative of Johnson Controls, testified that the controls had been installed in 2000 and his company's work performed after May 2001 was related to software programming to operate a chill water system.

In Martin Tire Rubber Co. v. Kelly Tire Rubber Co., CT Page 373199 Conn. 396, 399, 122 A. 102 (1923), the court held that "[i]f, after the work is substantially done, the claimant for the material furnished or services rendered shall unreasonably delay the completion of the work, the date of beginning of the sixty-day period will be taken as the date when the work was substantially done. No trivial or inconsequentialservice or work done after the substantial completion of the buildingwill extend the time for claiming the lien, or revive an expired lien when an unreasonable period has elapsed since the substantial completion. If the article furnished or the service rendered be trivial, but be required by the terms of the contract of building, this fact will be taken into consideration in determining whether the elapsed period be unreasonable or not. And where a service is performed or material furnished at the request of the owner, it will extend the time for claiming a lien or will revive an expired lien, as to a contract . . . substantially performed. Thus . . . it is held that trivial work done or material furnished will be sufficient to extend the time for filing the lien if done, at the request of the owner, and not for the mere purpose of saving his lien." (Citations omitted; emphasis added; internal quotation marks omitted). This rule was later discussed in F.B. MattsonCompany, Inc. v. Tarte, 247 Conn. 234, 239, 719 A.2d 1158 (1998), where the Supreme Court held that the removal of a contractor's roofing brackets and scaffolding done some five weeks after substantial completion did indeed constitute a lienable service not only because the work was performed at the request of the owner but also because the work itself, that is, the removal of the brackets, constituted a repair of the building.

In Mattson, the court held that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Martin Tire Rubber Co. v. the Kelly Tire Rubber
122 A. 102 (Supreme Court of Connecticut, 1923)
National Fireproofing Co. v. Town of Huntington
71 A. 911 (Supreme Court of Connecticut, 1909)
Diamond National Corp. v. Dwelle
325 A.2d 259 (Supreme Court of Connecticut, 1973)
Bialowans v. Minor
550 A.2d 637 (Supreme Court of Connecticut, 1988)
Centerbrook, Architects & Planners v. Laurel Nursing Services, Inc.
620 A.2d 127 (Supreme Court of Connecticut, 1993)
Thompson & Peck, Inc. v. Division Drywall, Inc.
696 A.2d 326 (Supreme Court of Connecticut, 1997)
New England Savings Bank v. Meadow Lakes Realty Co.
706 A.2d 465 (Supreme Court of Connecticut, 1998)
Toise v. Rowe
707 A.2d 25 (Supreme Court of Connecticut, 1998)
F. B. Mattson Co. v. Tarte
719 A.2d 1158 (Supreme Court of Connecticut, 1998)
Tallmadge Bros. v. Iroquois Gas Transmission System, L.P.
746 A.2d 1277 (Supreme Court of Connecticut, 2000)
Johnson v. Commissioner of Correction
786 A.2d 1091 (Supreme Court of Connecticut, 2002)
Pero Building Co. v. Smith
504 A.2d 524 (Connecticut Appellate Court, 1986)
Christ-Janer v. A.F. Conte & Co.
511 A.2d 1017 (Connecticut Appellate Court, 1986)
Snydergeneral Corp. v. Lee Parcel 6 Associates Ltd. Partnership
681 A.2d 1008 (Connecticut Appellate Court, 1996)
Connair v. City of New Haven
737 A.2d 971 (Connecticut Appellate Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2003 Conn. Super. Ct. 3729, 34 Conn. L. Rptr. 433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tougher-industries-v-learning-corridor-no-cv-02-0819779s-mar-19-2003-connsuperct-2003.