Tallmadge Bros. v. Iroquois Gas Transmission System, L.P.

746 A.2d 1277, 252 Conn. 479, 2000 Conn. LEXIS 89
CourtSupreme Court of Connecticut
DecidedMarch 15, 2000
DocketSC 16201
StatusPublished
Cited by221 cases

This text of 746 A.2d 1277 (Tallmadge Bros. v. Iroquois Gas Transmission System, L.P.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tallmadge Bros. v. Iroquois Gas Transmission System, L.P., 746 A.2d 1277, 252 Conn. 479, 2000 Conn. LEXIS 89 (Colo. 2000).

Opinions

Opinion

PETERS, J.

The dispositive issue in this appeal is whether a general release and merger clause contained in contracts between commercial parties operates to preclude any future claims of contractual liability against the party for whose benefit the general release was executed. We conclude that, under the circumstances of this case, the unambiguous language of the parties’ contracts precludes any such claims of liability. Accordingly, we reverse the judgment of the trial court.

The plaintiffs, Tallmadge Brothers, Inc. (Tallmadge Brothers), and Robert J. Sabo, filed a ten count complaint against the defendant, Iroquois Gas Transmission System, L.P. The complaint contained, inter alia, claims for detrimental reliance, breach of contract, unfair trade practices, trespass and fraudulent misrepresentation. [482]*482Subsequent to the filing of the plaintiffs’ complaint, the parties agreed, pursuant to General Statutes § 52-425,1 to submit their case to a committee of the Superior Court, which would hear evidence, find facts and offer its legal recommendations to the court. The committee, former Superior Court Judge Nicholas A. Cioffi, recommended a finding in favor of the plaintiffs on the breach of contract counts and damages awards in the amount of $282,345 for Tallmadge Brothers and $54,000 for Sabo. Thereafter, the trial court, Lewis, J., modified the committee’s findings and awards. The court rendered a judgment in favor of the plaintiffs in the amount of $3,203,852 for Tallmadge Brothers, and $355,388 for Sabo. The defendants appealed and the plaintiffs cross appealed from the judgment to the Appellate Court, and we transferred the case to this court pursuant to General Statutes § 51-199 (c) and Practice Book § 65-1.

The record reveals the following relevant facts. The plaintiffs operate shellfisheries in Long Island Sound, from which they harvest oysters and clams.2 Tallmadge Brothers, holds perpetual franchises3 to approximately 20,000 acres of shellfish grounds throughout Long Island Sound, and Sabo has a contractual interest in [483]*483163 acres of shellfish grounds. The defendant is the owner and operator of the Iroquois Natural Gas Transmission Pipeline (pipeline), which runs from the Canadian border, through New York and Connecticut, across Long Island Sound, to its terminus on Long Island.

In 1986, the defendant met with the plaintiffs and state and federal officials to discuss its proposal to build the pipeline across shellfish grounds operated by Tallmadge Brothers,4 and the possible impact that pipeline construction might have on the plaintiffs’ shell-fisheries.5 Negotiations among the parties did not resume in earnest until January, 1990, at which time Sabo expressed his desire that the pipeline be moved from his shellfish grounds to those of Tallmadge Brothers. In the latter part of 1990, employees of the defendant and the plaintiffs conducted samplings of the shellfish grounds that lay in the various possible paths of the pipeline in order to determine the shellfish density in those areas. In November, 1990, the coastal resources management division of the state department of environmental protection issued, pursuant to federal environmental regulations, a consistency certification letter, which stated that “the proposed [pipeline is] consistent with Connecticut’s federally-approved coastal management program, subject to strict adherence to the following conditions as agreed to by [the defendant] and the [department of [environmental [protection.”6

[484]*484On December 6, 1990, the parties held a meeting attended by, among others, Sabo, Hillard Bloom, the president of Tallmadge Brothers, and Ross Milne, the defendant’s representative during the course of the negotiations. At that meeting, Milne informed all present that the pipeline would be constructed in a 200 foot corridor across Long Island Sound, and that within that corridor “there would be a 100% devastation of shellfish . . . .” Although the parties anticipated that there would be incidental damage caused by the pipeline construction beyond that 200 foot area, they were unable to agree as to the likely extent of that incidental destruction. Subsequent to that meeting, the defendant sent to various contractors bid packages, for the construction of the pipeline. In those packages the defendant described the work area as being 300 feet wide, and the construction specifications called for the dragging of a heavy smoothing beam along a 300 foot wide corridor.7 The plaintiffs were not informed about the discrepancy between the width of the work area described in the bid packages and that represented to them by the defendant in their negotiations.

On January 30,1991, the parties held another meeting, at which the defendant offered TaUmadge Brothers $1,704,540 and Sabo $757,000 as compensation for the expected damage from the pipeline construction.8 The [485]*485defendant subsequently increased these amounts slightly, to $1,730,768 for Tallmadge Brothers, and $769,231 for Sabo, and, in addition, promised to pay damages to be calculated after postconstruction testing of the shellfisheries. Alternatively, the defendant offered the plaintiffs double those amounts as a full and final settlement for all damage caused by, or incident to, construction.

Between February 5 and March 1, the parties exchanged a series of draft settlement contracts. During this period, Tallmadge Brothers was represented by Attorney Joseph Richichi and the defendant was represented by Attorney Anthony Fitzgerald. Sabo did not retain the services of counsel. In the usual manner of commercial negotiations, each party attempted to word the contracts in the manner most favorable to its respective interests.

On February 25, Sabo and the defendant executed the final settlement agreement that is at issue in this case.9 Tallmadge Brothers and the defendant did the [488]*488same on March l.10 As compensation for a complete [489]*489release of the defendant from any and all liability “inci[490]*490dent to the construction of the Pipeline,” Tallmadge [491]*491Brothers received $3,661,536, and Sabo received $1,538,462.

Construction of the pipeline began on March 1, 1991, and continued into May of that year-. In May, Bloom and Sabo each noticed that the smoothing beam was being dragged well outside the 200 foot work area described in the portion of the settlement agreements restricting the plaintiffs’ shellfishing during the construction period. On May 16, Richichi mentioned to Fitzgerald that the defendant was exceeding the scope of the work area. Fitzgerald then spoke with the defendant, and in that conversation learned, for the first time, of the discrepancy between the size of the work area as defined by the restriction on the plaintiffs’ shellfishing activities, and the size of the work area as specified in the agreement between the defendant and its contractors. Fitzgerald also learned at that time that the larger work area was required by federal and state agencies for environmental reasons.

In March, 1993, the plaintiffs filed the ten count, amended complaint that is the operative complaint for the purposes of this appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SMDV 1, LLC v. 459-461 Pacific Street, LLC
Connecticut Appellate Court, 2025
Nation-Bailey v. Bailey
Supreme Court of Connecticut, 2015
Thoma v. Oxford Performance Materials, Inc.
Connecticut Appellate Court, 2014
Stevens v. Landmark Partners, Inc.
574 F. App'x 32 (Second Circuit, 2014)
Meadowbrook Center, Inc. v. Buchman
Connecticut Appellate Court, 2014
Sakon v. MANAGER
969 A.2d 781 (Connecticut Appellate Court, 2009)
Connecticut Light & Power Co. v. NRG Power Marketing Inc.
497 F. Supp. 2d 352 (D. Connecticut, 2007)
United States Fidelity & Guaranty Co. v. S.B. Phillips Co.
359 F. Supp. 2d 189 (D. Connecticut, 2005)
Parrot v. Guardian Life Insurance Co. of America
866 A.2d 1273 (Supreme Court of Connecticut, 2005)
Sartor v. Town of Manchester
312 F. Supp. 2d 238 (D. Connecticut, 2004)
Executive Airlines v. Electric Boat Corp.
271 F. Supp. 2d 392 (D. Connecticut, 2003)
Alstrom Power, Inc. v. Balcke-Durr, No. Cv 02 0068171 S (Mar. 25, 2003)
2003 Conn. Super. Ct. 4233 (Connecticut Superior Court, 2003)
Automotive Technologies, Inc. v. Snet, No. Cv 98-0578664 S (Mar. 20, 2003)
2003 Conn. Super. Ct. 3823 (Connecticut Superior Court, 2003)
Tougher Industries v. Learning Corridor, No. Cv 02-0819779s (Mar. 19, 2003)
2003 Conn. Super. Ct. 3729 (Connecticut Superior Court, 2003)
Scandura v. Middletown, No. Cv 01 0094798s (Feb. 27, 2003)
2003 Conn. Super. Ct. 2801 (Connecticut Superior Court, 2003)
Hillis v. Hillis, No. Fa00 0179465s (Feb. 19, 2003)
2003 Conn. Super. Ct. 2303 (Connecticut Superior Court, 2003)
Breiter v. Breiter, No. Fa 99-0720705s (Jan. 21, 2003)
2003 Conn. Super. Ct. 1116 (Connecticut Superior Court, 2003)
Kazlon Commc'n v. Am. Golfer, No. Cv01 0186424 S (Jan. 21, 2003)
2003 Conn. Super. Ct. 1730 (Connecticut Superior Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
746 A.2d 1277, 252 Conn. 479, 2000 Conn. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tallmadge-bros-v-iroquois-gas-transmission-system-lp-conn-2000.