Alstrom Power, Inc. v. Balcke-Durr, No. Cv 02 0068171 S (Mar. 25, 2003)

2003 Conn. Super. Ct. 4233
CourtConnecticut Superior Court
DecidedMarch 25, 2003
DocketNo. CV 02 0068171 S
StatusUnpublished

This text of 2003 Conn. Super. Ct. 4233 (Alstrom Power, Inc. v. Balcke-Durr, No. Cv 02 0068171 S (Mar. 25, 2003)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alstrom Power, Inc. v. Balcke-Durr, No. Cv 02 0068171 S (Mar. 25, 2003), 2003 Conn. Super. Ct. 4233 (Colo. Ct. App. 2003).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION ON MOTION FOR DISCHARGE OF MECHANIC'S LIEN
Alstom Power seeks an order of this court discharging the $17,004,142.82 mechanic's lien filed by the defendant Balcke-Durr Inc. (BD or BDI). It asserts that BD waived its right to file a mechanic's lien under the express terms of the contract between the parties. BD asserts, inter alia, that since the agreement was not reached until after October 1, 1999, that the lien waiver language was rendered "void and of no effect" pursuant to 42 C.G.S. 158l (a) which became effective on October 1, 1999.

I
FACTS
A summary of facts and procedural history are as follows. On July 5, 1998, ABB Power Generation, Ltd., the predecessor-in-interest of the plaintiff, Alstom Power Inc., entered into a Long Term Supply Agreement (LTSA) with Balcke-Durr GmbH, the predecessor of the defendant, Balcke-Durr, Inc. The LTSA was in essence an agreement to agree. It set certain standards and parameters relating to the air cooled condensers and other equipment BD was to supply to Alstom for Alstom's use in several power plant construction projects in the United States and other countries. Each individual project would be commenced with a separate purchase order issued by the plaintiff and acknowledged by the defendant.

By the summer of 2000, a number of purchase orders had been issued pursuant to the LTSA and disputes had arisen between the parties. One of these purchase orders was for a project on Lake Road in Killingly, Connecticut (Lake Road). In accordance with the LTSA and a subsequent Memorandum of Agreement, arbitration proceedings concerning the disputes on all projects was commenced under the Arbitration Rules of the Zurich Chamber of Commerce. On February 12, 2002, after the arbitration process commenced, RD recorded a mechanic's lien against the Lake Road property, CT Page 4234 to secure payment for labor, material and services, in the amount of $17,004,142.82. Pursuant to General Statutes § 49-37, the plaintiff then posted a surety bond in the amount of $20,400,000.00, as a substitute for the lien and commenced an application proceeding in this court to either discharge the lien or reduce its amount. The defendant moved to stay the plaintiff's application for discharge based upon pending arbitration, pursuant to General Statutes § 52-409.

The court granted the defendant's motion to stay, in part, and denied it, in part. The court held that the question of the validity of the mechanic's lien is ultimately a decision for the court. The stay was granted with respect to any claims for a reduction of the lien.

The court heard argument on the matter on January 7, 2003. At the hearing, the plaintiff filed additional documentary exhibits and presented a witness, Lambert Kerschbaumer, the plaintiff's purchasing manager.

II
LAW
Pursuant to General Statutes § 49-35b (b), in order for this court to discharge a mechanic's lien, the plaintiff must show, by clear and convincing evidence, that the mechanic's lien is invalid. See Johnson v.De Toledo, 61 Conn. App. 156, 161, 763 A.2d 28 (2000).

Alstom points to the express language of the LTSA as establishing the grounds for the discharge of BD's lien. Section 19.2 of the LTSA provides in relevant part:

to the full extent permissible by local law, [BDI] hereby waives for himself, his successors in interest and assigns, and for all subcontractors, vendors, suppliers, etc., their successors in interest and assigns for all claim or right of lien upon [Alstom's] or theEmployer's property or any part thereof as a result of the furnishing oflabor and/or material under the terms of the Agreement.

(Emphasis added.) (LTSA at p. 17).

The plaintiff produced evidence that BD started work on the Lake Road project prior to October 1, 1999, and was paid for work performed as of September 1, 1999. It claims that therefore, the contract was accepted by BD and was in force and effect prior to the effective date of the Fairness in Construction Financing Act, General Statutes § 42-158i, CT Page 4235 et seq.

The defendant counters the assertions of the plaintiff with a number of defenses. The defendant relies upon the Fairness in Construction Financing Act which provides that as of October 1, 1999:

(A)ny provision in a construction contract or any periodic lien waiver issued pursuant to a construction contract that purports to waive or release the right of a contractor, subcontractor or supplier engaged to perform services, perform labor or furnish materials under the construction contract to (1) claim a mechanic's lien or (2) make a claim against a payment bond, for services, labor or materials which have not yet been performed and paid for shall be void and of no effect.

(Emphasis added.) General Statutes § 42-158l (a).

Importantly, the lien waiver prohibition in the Fairness Act applies to contracts entered into "on or after October 1, 1999," pursuant to General Statutes § 42-158i.1 BD claims that the agreement between the parties with respect to the Lake Road Project did not come into effect until October 15, 1999 at the very earliest and therefore, the lien waiver language of the LTSA was void and of no effect. It further claimed the flaws in the lien waiver precluded its enforcement. Finally BD renewed its previously rejected argument that the issues of the validity of the lien and lien waiver should be resolved by the pending arbitration.

The parties submitted to the court the LTSA, the Purchase Order for the Lake Road Project dated September 27, 1999, the Purchase Order acknowledgment dated October 15, 1999, and Limited Notices to Proceed (LNTP) dated August 27, 1999 and September 14, 1999. The defendant submitted a "Terms of Payment" memorandum which indicated payment milestones under the contract. The plaintiff submitted a payment invoice from the defendant dated October 12, 1999, requesting payment of 10% of the contract value as Milestone 1 with a notation that "the 45 day payment period started on 9/1/99." The plaintiff also submitted various minutes of the parties' meetings that occurred in August and September of 1999.

In order to ascertain the effective date, the court must determine the dates and interplay of the operative documents that make up the agreement, as a whole. "[The Supreme Court] long [has] held that when the parties have deliberately put their engagements into writing, in such terms as import a legal obligation, without any uncertainty as to the object or extent of such engagement, it is conclusively presumed, that CT Page 4236 the whole engagement of the parties, and the extent and manner of their understanding, was reduced to writing. After this, to permit oral testimony, or prior or contemporaneous conversations, or circumstances, or usages [etc.], in order to learn what was intended, or to contradict what is written, would be dangerous and unjust in the extreme." (Internal quotation marks omitted.) Tallmadge Bros., Inc. v. Iroquois GasTransmission System, L.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HLO Land Ownership Associates Ltd. Partnership v. City of Hartford
727 A.2d 1260 (Supreme Court of Connecticut, 1999)
Tallmadge Bros. v. Iroquois Gas Transmission System, L.P.
746 A.2d 1277 (Supreme Court of Connecticut, 2000)
Lyon v. Adgraphics, Inc.
540 A.2d 398 (Connecticut Appellate Court, 1988)
Lembo v. Schlesinger
543 A.2d 780 (Connecticut Appellate Court, 1988)
Johnson v. De Toledo
763 A.2d 28 (Connecticut Appellate Court, 2000)
United Coastal Industries, Inc. v. Clearheart Construction Co.
802 A.2d 901 (Connecticut Appellate Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2003 Conn. Super. Ct. 4233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alstrom-power-inc-v-balcke-durr-no-cv-02-0068171-s-mar-25-2003-connsuperct-2003.