United Coastal Industries, Inc. v. Clearheart Construction Co.

802 A.2d 901, 71 Conn. App. 506, 2002 Conn. App. LEXIS 419
CourtConnecticut Appellate Court
DecidedAugust 13, 2002
DocketAC 21610
StatusPublished
Cited by44 cases

This text of 802 A.2d 901 (United Coastal Industries, Inc. v. Clearheart Construction Co.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Coastal Industries, Inc. v. Clearheart Construction Co., 802 A.2d 901, 71 Conn. App. 506, 2002 Conn. App. LEXIS 419 (Colo. Ct. App. 2002).

Opinion

Opinion

DUPONT, J.

The issues in this appeal are whether the plaintiff subcontractor, in an action against the defendant contractor, can recover as restitution, in quantum meruit or unjust enrichment for work done in partial completion of the work encompassed by their written contract, and, if so, the proper amount of damages. We conclude that the remedy of restitution was proper and that the amount of damages was calculated properly. We therefore affirm the judgment of the trial court.

The defendant contractor, Clearheart Construction Company, Inc. (Clearheart), and the plaintiff subcontractor, United Coastal Industries, Inc. (United), entered into a written contract for the demolition of a building. The plaintiff filed an action against the defendant,1 claiming damages (1) for breach of contract for [508]*508failure to pay the contract price plus change orders or (2) in quantum meruit for the reasonable value of the services rendered or (3) for the unjust enrichment of the defendant or (4) arising from a claimed violation of the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes § 42-110a et seq.2 The defendant filed a counterclaim for damages and alleged that the plaintiff had breached the contract, violated CUTPA and intentionally interfered with a contractual relationship.3 The defendant thereafter impleaded Ronald Walker as a defendant. Walker was an officer, director and shareholder of the plaintiff. The defendant then filed a cross complaint against Walker individually, alleging that he had committed intentional torts against the defendant.

The court rendered judgment for the plaintiff on its quantum meruit and unjust enrichment claims in the amount of $41,125, and rendered judgment for the defendant on the plaintiffs breach of contract and CUTPA claims. The court rendered judgment for the plaintiff and for Walker, and against the defendant on its counterclaim and the cross complaint.4

The court found that there was a written contract under which the plaintiff had agreed to perform demoli[509]*509tion work for a set payment upon completion of that work by a set date, but that the plaintiff had failed to complete the work by the contractual completion date. The court’s other findings in its memorandum of decision were as follows: “A part of the uncompleted work was caused by an unknown, hazardous existing condition covering a wall that was to be removed; that neither patty was aware of the hazardous condition at the time of the execution of the contract. That the remaining work of demolition that [United] failed to carry out by the contractual deadline placed Clearheart in a position of defaulting on its contract or suffering substantial per diem penalties if not carried out immediately. That Clearheart was within its contractual terms in terminating [United’s] demolition involvement at the terminal date of the contract. . . . [Although the plaintiff, [United], failed to complete the demolition set out in the contract, it did provide the defendant, Clearheart, with benefits based upon the portions of the contract it had carried out. . . . Clearheart did complete those portions of the contract that [United] failed to complete to its financial detriment. However, although Clearheart presented evidence as to its expenditures in completing the demolition . . . Clearheart was unable to segregate those expenditures that applied specifically to the uncompleted demolition . . . .” The court found, however, that based on all of the evidence submitted to it, “Clearheart incurred costs of $29,375 to complete the unfinished demolition . . . .”

The plaintiff discovered asbestos paint on a load bearing wall in late August, 1996. According to the court’s memorandum of decision, “Clearheart admits that the asbestos painted wall required special handling that was not part of [United’s] contract” and that Clearheart’s responsibility was “only to permit use of its dumpster for the disposal of the wall debris.” The court stated that the plaintiff had claimed that it could not remove [510]*510the wall until the paint was first removed. The plaintiff refused to permit its dumpster to be used, claiming that the use would violate various environmental protection regulations and that the plaintiff was not licensed by the state to remove asbestos.5

The court found that if the plaintiff had completed its contract, it would be due $88,900, the contract price, plus change orders of $5100 for a total of $94,000.6 The court determined that 75 percent of the contract work had been completed by the plaintiff so that it was due $70,500 for that work. The defendant had not paid the plaintiff anything toward the contract price and, therefore, no credit was given to the defendant for a payment. The court deducted the costs of the defendant to complete the work and rendered judgment for the plaintiff in the amount of $41,125.

The defendant claims that because the court found that there was a written contract and that the plaintiff had not substantially completed its work by the contractual completion date, there could be no recovery under either quantum meruit or unjust enrichment. The defendant also claims that if any damages were due, they were found improperly because there was no evidence to support the dollar amounts of the value of the work performed by the plaintiff and the cost to the defendant to complete the work.

“[T]he determinations of whether a particular failure to pay was unjust and whether the defendant was benefited are essentially factual findings . . . that are subject only to a limited scope of review on appeal. . . . Those findings must stand, therefore, unless they are [511]*511clearly erroneous or involve an abuse of discretion.” (Internal quotation marks omitted.) Gardner v. Pilato, 68 Conn. App. 448, 453, 791 A.2d 707, cert. denied, 260 Conn. 908, 795 A.2d 544 (2002), citing Hartford, Whalers Hockey Club v. Uniroyal Goodrich Tire Co., 231 Conn. 276, 283, 649 A.2d 518 (1994). We must determine, therefore, whether there was sufficient evidence to find that the plaintiff was entitled to restitution and, if so, the proper amount due.

Counts two and three of the complaint, which seek damages for unjust enrichment and quantum meruit, are meant to provide an alternative basis for recovery in the event of a failure to prove the breach of contract claim in count one. See Bolmer v. Kocet, 6 Conn. App. 595, 612, 507 A.2d 129 (1986). Thus, the defendant cannot prevail on its claim that the plaintiff is precluded from recovering in quantum meruit because it did not complete its contractual obligation. See id.

In this case, the plaintiff alleged in count one that it “performed the entire contract under the terms of [the] written agreement as best as could be complied with in accordance with the laws of the State of Connecticut” (emphasis added) and that the defendant had failed to pay the plaintiff any sums under the terms of the contract or for additional approved work. The court found against the plaintiff on that count.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peter Martin v. Google LLC
D. Connecticut, 2026
Kloth-Zanard v. Weebly, Inc.
D. Connecticut, 2025
Piccolo v. American Auto Sales, LLC
195 Conn. App. 486 (Connecticut Appellate Court, 2020)
Crosskey Architects, LLC v. POKO Partners, LLC
Connecticut Appellate Court, 2019
Autery v. Pope
260 So. 3d 846 (Court of Civil Appeals of Alabama, 2018)
Pollansky v. Pollansky
Connecticut Appellate Court, 2016
300 State, LLC v. Hanafin
59 A.3d 287 (Connecticut Appellate Court, 2013)
BHP Land Services, LLC v. Seymour
47 A.3d 950 (Connecticut Appellate Court, 2012)
Imaginative Research Associates, Inc. v. Ramirez
718 F. Supp. 2d 236 (D. Connecticut, 2010)
Data-Flow Technologies, LLC v. Harte Nissan, Inc.
958 A.2d 195 (Connecticut Appellate Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
802 A.2d 901, 71 Conn. App. 506, 2002 Conn. App. LEXIS 419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-coastal-industries-inc-v-clearheart-construction-co-connappct-2002.