John T. Brady & Co. v. City of Stamford

599 A.2d 370, 220 Conn. 432, 1991 Conn. LEXIS 486
CourtSupreme Court of Connecticut
DecidedNovember 19, 1991
Docket14284
StatusPublished
Cited by38 cases

This text of 599 A.2d 370 (John T. Brady & Co. v. City of Stamford) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John T. Brady & Co. v. City of Stamford, 599 A.2d 370, 220 Conn. 432, 1991 Conn. LEXIS 486 (Colo. 1991).

Opinion

Peters, C. J.

In this action for breach of a commercial construction contract, the principal issue is whether [435]*435the trial court, in its evidentiary rulings and its instructions to the jury, assigned proper weight to the terms of three contracts consecutively negotiated by the parties. The appeal arises out of two lawsuits that were consolidated for trial. The first was an action brought by the plaintiffs, John T. Brady and Company (contractor), and its surety and assignee, Federal Insurance Company (surety), to recover the unpaid portion of the contract price and the price of certain alleged contract extras from the defendant, the Connecticut Urban Redevelopment Commission of the city of Stamford (owner).1 The second was an action brought by the owner and Rich-Taubman Associates (redeveloper) to recover damages from the contractor and the surety because of the contractor’s alleged failure to comply with contract specifications in timely fashion. The jury found in favor of the contractor and the surety in both actions, awarding them jointly $2,612,098.84 plus interest in the amount of $1,456,520.49. Following the trial court’s denial of motions by the owner and the redeveloper to set aside the verdict and for judgment notwithstanding the verdict, the owner and the redeveloper appealed to the Appellate Court and the surety and the contractor cross appealed. We transferred the appeals to this court in accordance with Practice Book § 4023 and now reverse.

The litigation arises out of a contract between the owner and the contractor, John T. Brady and Company, for the construction of a regional shopping center and garage known as the Stamford Town Center (the project). The contractor undertook to build a nine story parking garage and the shell of an adjacent enclosed shopping mall that the redeveloper was to complete and operate. The named surety and four reinsurance com[436]*436panies issued a performance bond underwriting the performance of the contract. The owner and the contractor agreed on a contract price, as amended, of $36,014,993, of which the contractor has been paid $33,028,201.

Three interrelated contracts memorialized the agreement between the owner and the contractor. These contracts consisted of: the underlying construction contract, executed on December 19, 1978, prior to the commencement of construction; the settlement agreement, executed on September 28,1981, when the project was 94 percent complete; and the completion agreement, executed on June 1,1982, when the project was 99 percent complete.

The construction contract incorporated relevant drawings and specifications for the project, for which the owner agreed to pay the designated contract price. The contract stipulated that time was of the essence, set January 20,1981, as the date for completion of the project, and contained a clause liquidating damages in the amount of $3000 each day for any delay after the completion date.2 The contract defined substantial completion of the project as including the issuance of a final certificate of occupancy.3 Further, the contract indicated that the contractor would not be entitled to final payment until all of its work had been accepted by the owner.4

[437]*437In order to resolve substantial disagreements about delay in the performance of the contract and responsibility for extra work, the parties negotiated a settlement agreement on September 28,1981, eight months after the completion date contained in the construction contract. The settlement agreement provided, inter alia, that: (1) the owner would pay the contractor $2,250,000; (2) the contractor immediately released the owner from all claims arising prior to that time; (3) the owner immediately waived any claim for liquidated damages until after January 20, 1982; (4) the owner agreed to waive its claim for actual damages due to delay, stipulated by the parties to amount to $800,000, if the contractor substantially completed the project by January 20, 1982; and (5) the parties agreed that the completion date could be extended under specified circumstances.

The project was not completed by the revised completion date of January 20,1982. Relying on the extension provision in the settlement agreement, the contractor maintained that this delay resulted from the absence of timely instructions and the issuance of belated change orders. Because the owner disagreed with the validity of these claims, it paid the contractor only $1,375,000 of the additional $2,250,000 promised in the settlement agreement, and refused to waive the $800,000 in actual delay damages stipulated in that agreement. The resultant financial difficulties led the [438]*438contractor, in March of that year, to assign its contract rights to the surety, which thereupon began funding further work on the project.

On June 1, 1982, the owner, the contractor and the surety entered into the completion agreement. By the terms of that contract: (1) the surety agreed to finance the resumption of work on the project so that it could be completed by July 9,1982; (2) the owner agreed to waive any claim for delay damages sustained between the new completion date and the prior revised completion date of January 20,1982; (3) the owner agreed to pay $1,000,000 upon substantial completion of the project by the new completion date; (4) the surety agreed to obtain releases of mechanic’s liens; and (5) the owner agreed to make monthly progress payments. Like the settlement agreement, the completion agreement provided that the new completion date could be extended for reasons enumerated in the agreement.

The project was not completed on July 9,1982. Alleging that certain important work remained undone or unaccepted, and that mechanic’s liens had not been released, the owner withheld further payments. On August 19, 1982, the contractor sued to recover the unpaid contract price and an additional amount representing the cost of alleged extra work. The complaint also contained a count for prejudgment interest. This cause of action, with the surety replacing the contractor as the real party in interest, is the first of the lawsuits before us on this appeal.

Despite the lawsuit, work continued on the project, resulting in the issuance of a temporary certificate of occupancy on October 22,1982. Maintaining that it had completed its work on the project, the contractor left the work site on January 5,1983. The owner continued to insist that there were uncorrected defects in the contractor’s performance. When the surety refused a [439]*439request for further corrective work, the owner engaged another contractor to complete the project. This aspect of the controversy between the parties was the basis for the second cause of action before us, a suit by the owner and the redeveloper to recover liquidated and actual damages because of the contractor’s delay in completing the project, and actual damages because of the contractor’s allegedly unsatisfactory performance of the contract, in the total amount of $3,225,907.14 above and beyond the remaining balance on the contract price. Like that of the contractor and the surety in the first case, the complaint of the owner and the redeveloper included a claim for prejudgment interest.

The trial of these consolidated causes of action began with jury selection in April, 1989. The trial itself began on July 5, 1989, and continued until April 24, 1990, when the jury returned its verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Lombardo Bros. Mason Contractors, Inc.
980 A.2d 983 (Connecticut Superior Court, 2009)
Billy & Leo, LLC v. Michaelidis
867 A.2d 119 (Connecticut Appellate Court, 2005)
PSE Consulting, Inc. v. Mercede
838 A.2d 135 (Supreme Court of Connecticut, 2004)
Hubbard v. State Farm Indemnity Co.
584 S.E.2d 176 (West Virginia Supreme Court, 2003)
United Coastal Industries, Inc. v. Clearheart Construction Co.
802 A.2d 901 (Connecticut Appellate Court, 2002)
Treglia v. Zanesky
788 A.2d 1263 (Connecticut Appellate Court, 2001)
Vitone Admx v. Waterbury Hospital, No. Cv97-0139262s (Dec. 7, 2001)
2001 Conn. Super. Ct. 16195 (Connecticut Superior Court, 2001)
Mouta v. T S Investments, No. Cv 01-0807151 (Aug. 22, 2001)
2001 Conn. Super. Ct. 11478 (Connecticut Superior Court, 2001)
Stillman v. Allstate Insurance Company, No. Cv 97 0073062s (Jun. 20, 2001)
2001 Conn. Super. Ct. 8022 (Connecticut Superior Court, 2001)
Organized N. East. v. Capital City E.D.A., No. Cv 01-0806228 (Jun. 7, 2001)
2001 Conn. Super. Ct. 7458 (Connecticut Superior Court, 2001)
Biller Associates v. Peterken
751 A.2d 836 (Connecticut Appellate Court, 2000)
Regional School Dist. v. Wayne Const., No. Cv99 033 78 80 S (May 18, 2000)
2000 Conn. Super. Ct. 5775 (Connecticut Superior Court, 2000)
Levine v. Darrow, No. X01 Cv 89 0146670 (Apr. 18, 2000)
2000 Conn. Super. Ct. 4591 (Connecticut Superior Court, 2000)
Medcalf v. Washington Heights Condominium Ass'n
747 A.2d 532 (Connecticut Appellate Court, 2000)
Carlin Cont. v. Blakeslee Arpaia Chapman, No. Cv 99-00551690 (Feb. 22, 2000)
2000 Conn. Super. Ct. 2393 (Connecticut Superior Court, 2000)
Black, Inc. v. Cotton, No. Cv 93 05 22710s (Sep. 2, 1998)
1998 Conn. Super. Ct. 10883 (Connecticut Superior Court, 1998)
Empire Paving, Inc. v. City of Milford, No. Cv-94-0362457s (Mar. 3, 1998)
1998 Conn. Super. Ct. 2687 (Connecticut Superior Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
599 A.2d 370, 220 Conn. 432, 1991 Conn. LEXIS 486, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-t-brady-co-v-city-of-stamford-conn-1991.