Strimiska v. Yates

257 A.2d 814, 158 Conn. 179, 1969 Conn. LEXIS 591
CourtSupreme Court of Connecticut
DecidedApril 15, 1969
StatusPublished
Cited by56 cases

This text of 257 A.2d 814 (Strimiska v. Yates) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Strimiska v. Yates, 257 A.2d 814, 158 Conn. 179, 1969 Conn. LEXIS 591 (Colo. 1969).

Opinion

Thim, J.

The defendant has appealed from a judgment which was rendered by a state referee and which awarded the plaintiff the entire unpaid balance of the contract price. Although the judgment was rendered against two defendants, only one de *181 fendant has taken this appeal. He claims that a material variance exists between the pleadings and the finding, that the finding fails to reveal the occurrence of a claimed condition precedent and, finally, that the plaintiff was not entitled to recover as damages the entire unpaid balance of the contract price.

The defendant has failed to pursue in his brief a number of assignments of error including certain attacks on the finding. These assignments of error are treated as abandoned. Martin v. Kavanewsky, 157 Conn. 514, 516, 255 A.2d 619; Katz v. Brandon, 156 Conn. 521, 524, 245 A.2d 579; State v. Kohlfuss, 152 Conn. 625, 635, 211 A.2d 143.

On June 10, 1955, the plaintiff and the defendants entered into a written agreement which provided that the plaintiff would furnish the labor, materials and equipment necessary to construct all roads and drains in a certain residential development owned by the defendants and situated in the town of New Canaan. In the agreement, the plaintiff promised to perform all of his work in a substantial, workmanlike manner and to comply with the requirements and specifications of the planning commission and the town engineer, so that the roads would be accepted by the town of New Canaan as public streets. The plaintiff promised to commence work immediately and to complete the job, including all extras, on or before September 15, 1955. He agreed to pay $25 a day as liquidated damages for so long as the work remained unfinished after September 15, 1955. In consideration for the plaintiff’s promises, the defendants promised to pay the plaintiff $15,400.

The plaintiff commenced work in the late spring of 1955, and, during the remainder of that year, he cleared and excavated the road sites and filled them with gravel in accordance with the standards pre *182 vailing in the locality. On April 26,1956, the parties executed a second written agreement, which provided, among other things, that the completion date of the first agreement would be deferred until June 1, 1956. This second agreement did not contain a provision for liquidated damages.

During the spring of 1956, the defendants had two water mains installed underneath the roads which were being developed by the plaintiff. Lateral lines, for conducting water from the main lines to each of the house lots, were also installed. Following the installation of the water mains and the lateral lines, the plaintiff returned to the job, and, after discovering that some of his work had been destroyed, he repaired the damage as an extra. Thereafter, the plaintiff completed the hardtop surfacing and remedied some deficiencies in his work which had been noted by the town engineer.

At about this time, the parties orally modified their original contract, agreeing that, with respect to two building lots, the plaintiff would instal approximately one-half of the drainage pipe which had previously been agreed upon. The lesser length of drainage pipe which would be installed, however, was to be laid in a more expensive and desirable manner than had been required by the original agreement.

The defendants offered evidence to establish that they had hired another contractor to work on their property; nevertheless, they failed to prove that this contractor did any work which should have been performed by the plaintiff. The referee concluded that the plaintiff had performed all of the work required by the agreement as altered and that the defendants failed to prove that they incurred any expense to complete or remedy the plaintiff’s *183 performance. The referee, therefore, awarded the plaintiff the sum of $5600, which was the entire unpaid balance of the contract price.

The defendant’s principal claim on this appeal is that a material variance exists between the facts as found by the referee and those alleged in the complaint. The defendant, therefore, urges that the judgment should be reversed because the plaintiff did not prove the material facts as he alleged them in his complaint. We do not agree with this claim for reasons hereinafter stated.

In his complaint, the plaintiff alleged that he completed performance of the written contract of June 10, 1955. At the hearing, however, the plaintiff testified that the written contract of June 10, 1955, had been orally modified with respect to the length and quality of drainage pipe for two building lots. There was no mention in the complaint of this oral modification of the contract, and the plaintiff did not attempt to amend his complaint so that it would conform with his proof. Despite the plaintiff’s failure to amend his complaint, the referee found that he had performed all of the work required by the agreement as altered.

A variance is a departure of the proof from the facts as alleged. Not every variance, however, is a fatal one since immaterial variances are disregarded under our practice. Practice Book § 134; Schaller v. Roadside Inn, Inc., 154 Conn. 61, 64, 221 A.2d 263; Bridgeport Hardware Mfg. Corporation v. Bouniol, 89 Conn. 254, 258, 93 A. 674; see also Practice Book § 150. Only material variances, those which disclose a departure from the allegations in some matter essential to the charge or claim, warrant the reversal of a judgment. Reciprocal Exchange v. Altherm, Inc., 142 Conn. 545, 552, 115 A.2d 460; Bridgeport *184 Hardware Mfg. Corporation v. Bouniol, supra; Maguire v. Kiesel, 86 Conn. 453, 457, 85 A. 689.

An immaterial variance is one in -which, the difference between the allegations and the proof is so slight and unimportant that the adverse party is not misled as to the charge he is required to meet or prejudiced in maintaining his defense on the merits of the case. Schaller v. Roadside Inn, Inc., supra, 65; Buol Machine Co. v. Buckens, 146 Conn. 639, 643, 153 A.2d 826; Antonofsky v. Goldberg, 144 Conn. 594, 599, 136 A.2d 338; Reciprocal Exchange v. Altherm, Inc., supra, 552; Rose v. Van Bosch, 119 Conn. 514, 519, 177 A. 565.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zhuleku v. Naugatuck Valley Radiology Associates
232 Conn. App. 143 (Connecticut Appellate Court, 2025)
Interbank of New York v. Foster, No. Cv01-0276819 (Jul. 16, 2002)
2002 Conn. Super. Ct. 9810-ar (Connecticut Superior Court, 2002)
Daley v. Wesleyan University
772 A.2d 725 (Connecticut Appellate Court, 2001)
Dean v. Ridgefield Water Supply Co., No. Cv-97-8040 (Jan. 8, 1998)
1998 Conn. Super. Ct. 1168 (Connecticut Superior Court, 1998)
Covey v. Comen
698 A.2d 343 (Connecticut Appellate Court, 1997)
Mucha v. Brown, No. Cv 91 48796 S (Jul. 10, 1997)
1997 Conn. Super. Ct. 7245 (Connecticut Superior Court, 1997)
Dimartino v. Voight, No. Cvnh 7907 (Apr. 29, 1997)
1997 Conn. Super. Ct. 2300 (Connecticut Superior Court, 1997)
City of Groton v. Board of Labor Rel., No. Cv 94 010 47 42 (Mar. 12, 1997)
1997 Conn. Super. Ct. 3420 (Connecticut Superior Court, 1997)
Marchetti v. Ramirez
673 A.2d 567 (Connecticut Appellate Court, 1996)
Moore v. Sergi
664 A.2d 795 (Connecticut Appellate Court, 1995)
Commissioner of Motor Vehicles v. DeMilo
659 A.2d 148 (Supreme Court of Connecticut, 1995)
Lebow v. American Chemical Refining Co., No. 0112554 (Nov. 7, 1994)
1994 Conn. Super. Ct. 11309 (Connecticut Superior Court, 1994)
Town of Southbury v. Smarrelli, No. 104659 (Oct. 17, 1994)
1994 Conn. Super. Ct. 10530 (Connecticut Superior Court, 1994)
M & L Building Corp. v. Housing Authority
646 A.2d 244 (Connecticut Appellate Court, 1994)
A. V. Giordano Co. v. American Diamond Exchange, Inc.
623 A.2d 1048 (Connecticut Appellate Court, 1993)
Grogan v. Zoning Board of Appeals, No. Cv910098506s (May 21, 1992)
1992 Conn. Super. Ct. 4894 (Connecticut Superior Court, 1992)
Kelley v. Bonney
606 A.2d 693 (Supreme Court of Connecticut, 1992)
John T. Brady & Co. v. City of Stamford
599 A.2d 370 (Supreme Court of Connecticut, 1991)
Ayotte v. Ayotte, No. 085916 (Nov. 7, 1991)
1991 Conn. Super. Ct. 9984 (Connecticut Superior Court, 1991)
Bell Atl.-Tricon v. 255 Main St. Assoc., No. Cv87 241451s (Mar. 11, 1991)
1991 Conn. Super. Ct. 2331 (Connecticut Superior Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
257 A.2d 814, 158 Conn. 179, 1969 Conn. LEXIS 591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/strimiska-v-yates-conn-1969.