M. J. Daly & Sons, Inc. v. New Haven Hotel Co.

99 A. 853, 91 Conn. 280, 1917 Conn. LEXIS 7
CourtSupreme Court of Connecticut
DecidedJanuary 25, 1917
StatusPublished
Cited by41 cases

This text of 99 A. 853 (M. J. Daly & Sons, Inc. v. New Haven Hotel Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. J. Daly & Sons, Inc. v. New Haven Hotel Co., 99 A. 853, 91 Conn. 280, 1917 Conn. LEXIS 7 (Colo. 1917).

Opinions

Prentice, C. J.

The complaint in this case seeks a foreclosure of a mechanic’s lien filed by the plaintiff against real estate of the defendant Hotel Company, hereinafter, for convenience sake, referred to as the defendant, to secure the sum of $18,573.72 claimed to be due the plaintiff for labor performed and materials furnished in the construction of a building thereon, under and by virtue of a contract with the owner. No objection was made below, or is made here, to the validity of the lien or the right of the plaintiff to have a foreclosure judgment, except such as is addressed to the existence of an indebtedness for the labor performed and materials furnished upon the building. The plaintiff alleges that the sum named is due: the defendant that nothing is due. If anything is shown by the evidence to be due, the lien is good for that amount and may be foreclosed for that amount. Nichols v. Culver, 51 Conn. 178, 180; Marston v. Kenyon, 44 Conn. 349, 356. The fundamental question of the case, therefore, relates to the existence of such indebtedness and its amount. Its answer is to be determined by recourse to the ordinary rules of law.

As to the $4,957.14, alleged by the plaintiff to be due under an award of arbitrators made in conformity with a provision of the contract, no objection is made to the plaintiff’s right to charge that sum against the defendant. Its right to charge any portion of the balance of the claimed indebtedness is stoutly denied, and many of the alleged errors of the trial court gather around its conclusion that the sum of $12,690 was properly charge *286 able as a balance due for labor and materials performed and furnished in the execution of the contract.

The trial court found that the plaintiff substantially-performed its contract, that its defaults were not wilful, and that an expenditure of $500 would have-accomplished full performance. It accordingly held that there was due to the plaintiff, secured by the lien, the unpaid balance of the contract price less $500, to wit, $12,690, and rendered its judgment of foreclosure for that sum. Assuming the facts to be as found, the court’s action was that which, the counterclaim aside, the law sanctions. Pinches v. Swedish Evangelical Lutheran Church, 55 Conn. 183, 187, 10 Atl. 264; Jones v. Marlborough, 70 Conn. 583, 589, 40 Atl. 460; Jones & Hotchkiss Co. v. Davenport, 74 Conn. 418, 420, 50 Atl. 1028; Morehouse v. Bradley, 80 Conn. 611, 613, 69 Atl. 937; O’Loughlin v. Poli, 82 Conn. 427, 429, 74 Atl. 763. The allegations of the complaint do not place limitations upon the plaintiff’s right to a foreclosure of its lien for whatever sum is rightfully due to it on account of the construction of the building. They are sufficient to support a judgment of foreclosure upon whatever theory or basis the amount of that indebtedness is to be arrived at, whether it be that the plaintiff performed its contract, or substantially performed it, or was wrongfully prevented by the defendant from performing it.

Doubtless counsel for the defendant are right in saying that the complaint gives evidence that the plaintiff was not looking to a recovery upon the basis of performance, since the averment that the work was done under a contract providing for payment after completion, is unaccompanied by one of completion. But it does not follow from that fact that the amount for which foreclosure may be had is to be determined upon direct proof of the reasonable worth of the labor *287 performed and materials furnished, and not with reference to the contract price presumably embodying an element of profit. On the contrary, the well-established rule, in this and other jurisdictions, is that the reasonable value for which recovery may be had in cases of substantial performance of building contracts, is to be ascertained with reference to the contract price and by deducting from that price such sum as ought to be allowed for the omissions and variations. Pinches v. Swedish Evangelical Lutheran Church, 55 Conn. 183, 187, 10 Atl. 264; Jones & Hotchkiss Co. v. Davenport, 74 Conn. 418, 420, 50 Atl. 1028; Valente v. Weinberg, 80 Conn. 134, 138, 67 Atl. 369; Morehouse v. Bradley, 80 Conn. 611, 614, 69 Atl. 937; O’Loughlin v. Poli, 82 Conn. 427, 429, 74 Atl. 763; Bowen v. Kimball, 203 Mass. 364, 369, 89 N. E. 542; Danforth v. Freeman, 69 N. H. 466, 469, 43 Atl. 621; Phillip v. Gallant, 62 N. Y. 256, 265; 24 L. R. A. (N. S.) 351 note; 6 R. C. L. p. 967, § 343.

If it were so that the complaint contained averments which, either expressly or by reasonable implication, alleged completion, the plaintiff would not for that reason be deprived of the right to have a judgment of foreclosure for an amount ascertained upon the basis of substantial performance. Healy v. Fallon, 69 Conn. 228, 234, 37 Atl. 495.

The rule stated as applicable to building contracts is an exception to that governing contracts generally. It had its origin in considerations of equity and justice, and its recognition is due to the fact that substantial justice in such cases can be done in no other way. There is no reason why one who has substantially performed such a contract, but unintentionally failed of strict performance in the matter of minor details, should have imposed upon him as a condition of recovery for that of which the other party has received *288 the benefit, the burden of showing by direct evidence its reasonable value, or why he should be deprived of all benefit of the contract which he has substantially .performed. The doctrine of substantial performance has had the approval of the courts for the very purpose of avoiding the hardships arising from the operation of the general rule, and the principles governing its application were designed to work to the fullest attainable extent approximate justice to all concerned.

In the determination of the amount of deduction which ought to be made in the application to specific cases of the rule stated, regard must be had to the circumstances which each presents. A different method, for instance, is required to accomplish the ends of justice where the shortcomings are such as may be remedied and completion according to the contract had without substantial interference with the structure of the building, than where the remedy and completion involves substantial structural changes. In the first case—and that, upon the finding, is ■ this case—the approved method under ordinary conditions is to deduct from the contract price such sum as it would cost to make the work comply with the contract. In the latter case, the amount of deduction might be measured by the diminished value of the building to the owner by reason of the defects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Absolute Plumbing & Heating, LLC v. Edelman
77 A.3d 889 (Connecticut Appellate Court, 2013)
E & M Custom Homes, LLC v. Negron
59 A.3d 262 (Connecticut Appellate Court, 2013)
Intercity Development, LLC v. Andrade
901 A.2d 731 (Connecticut Appellate Court, 2006)
Ambrogio v. Beaver Road Associates
836 A.2d 1183 (Supreme Court of Connecticut, 2003)
Carmel Homes, Inc. v. Bednar, No. Cv 99-0079393 S (Mar. 26, 2001)
2001 Conn. Super. Ct. 4317 (Connecticut Superior Court, 2001)
State v. Fisher
748 A.2d 377 (Connecticut Appellate Court, 2000)
Kelly v. Thompson, No. Cv95 0049283s (Jun. 14, 1998)
1998 Conn. Super. Ct. 7303 (Connecticut Superior Court, 1998)
Sullivan v. Buckland Meadow Associates, No. Cv92 51236 S (Aug. 12, 1996)
1996 Conn. Super. Ct. 5252-PPP (Connecticut Superior Court, 1996)
Amundsen v. Phoenix Home Life Mut. Ins., No. Cv 94 0049137 S (Dec. 7, 1995)
1995 Conn. Super. Ct. 13515 (Connecticut Superior Court, 1995)
A. Prete Son Cons. v. Town, Madison, No. Cv 91-03103073-S (Oct. 4, 1994)
1994 Conn. Super. Ct. 10068-D (Connecticut Superior Court, 1994)
C J Home Improvements v. Sabbatucci, No. Cv91 0321090 (Nov. 23, 1993)
1993 Conn. Super. Ct. 10180 (Connecticut Superior Court, 1993)
Pds Engineering Const. v. Double Rs, No. Cv90-0378684 (Dec. 19, 1991)
1991 Conn. Super. Ct. 10306 (Connecticut Superior Court, 1991)
John T. Brady & Co. v. City of Stamford
599 A.2d 370 (Supreme Court of Connecticut, 1991)
Habetz v. Condon, No. Cv90 03 32 36s (Sep. 27, 1991)
1991 Conn. Super. Ct. 7772 (Connecticut Superior Court, 1991)
Edens v. Kole Construction Co.
450 A.2d 1161 (Supreme Court of Connecticut, 1982)
Vincenzi v. Cerro
442 A.2d 1352 (Supreme Court of Connecticut, 1982)
Burns v. Gould
374 A.2d 193 (Supreme Court of Connecticut, 1977)
Levesque v. D & M BUILDERS, INC.
365 A.2d 1216 (Supreme Court of Connecticut, 1976)
Gulash v. Stylarama, Inc.
364 A.2d 1221 (Connecticut Superior Court, 1975)
Gulash v. Stylarama, Inc.
33 Conn. Supp. 108 (Pennsylvania Court of Common Pleas, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
99 A. 853, 91 Conn. 280, 1917 Conn. LEXIS 7, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-j-daly-sons-inc-v-new-haven-hotel-co-conn-1917.