Habetz v. Condon, No. Cv90 03 32 36s (Sep. 27, 1991)

1991 Conn. Super. Ct. 7772
CourtConnecticut Superior Court
DecidedSeptember 27, 1991
DocketNo. CV90 03 32 36S
StatusUnpublished

This text of 1991 Conn. Super. Ct. 7772 (Habetz v. Condon, No. Cv90 03 32 36s (Sep. 27, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Habetz v. Condon, No. Cv90 03 32 36s (Sep. 27, 1991), 1991 Conn. Super. Ct. 7772 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION This case raises the question to what extent a technical violation of the Home Improvement Act excuses payment to a builder for a substantially complete addition to a residence and allows a claim for damages by the homeowners.

The plaintiffs are owners of property on Arrowhead Drive in Orange. In early 1989 the plaintiff Peter Habetz contacted the defendant, Ken Condon, by telephone about constructing an addition on the plaintiffs' residence. Meetings and discussions followed, CT Page 7773 and when Habetz refused to hire an architect to design the addition, Condon prepared preliminary plans with his consent. Condon also prepared a five page contract which outlined the work to be performed for a contract price of $103,000, a time schedule for payments based on designated stages of construction of the addition. The written agreement was signed by Condon and Habetz on April 20, 1989.

As the work progressed Habetz made minor changes in the addition and requested additional work from Condon and some of the subcontractors. The extra work agreed to between Condon and Habetz was itemized on a two page written proposal (Ex. 3) which Condon asked Habetz to sign numerous times. Despite these requests Habetz failed to sign the list of extras, although he pressed for the additional work to be done. By August 10, 1989 most of the work under the original contract was completed, and the plaintiffs had paid the defendant $93,000 of the $103,000 contract price. When Condon requested the $10,000 balance on the contract, Habetz made some excuses for nonpayment and indicated he wanted more extra work performed. Subsequently he made complaints about some of the work. Condon substantially completed the extra work on the written proposal which Habetz had agreed to but did not sign. The cost of that work, itemized on Exhibit 3, is $6,244.

The first count of the complaint claims that some of the work was done in a negligent and unworkmanlike manner and that some of the work under the contract was incomplete. The defects claimed in paragraph 3 of the amended complaint are as follows:

(a) Anderson window missing to second floor addition;

(b) tile splashboard missing;

(c) cracked floor tiles in kitchen;

(d) replaced siding does not match existing siding;

(e) Townsend paneling missing;

(f) insulation damaged the trim molding;

(g) tarpaper not laid under shingles on roof in violation of Connecticut State Building Code R-803.2;

(h) damaged antenna system caused by roof construction;

(i) bathroom tile floor and grouting of shower, floor and toilet unfinished;

(j) insulation throughout addition incomplete; CT Page 7774

(k) ceiling, wall and floor water damage;

(l) central vacuum system incomplete;

(m) chimney cracked;

(n) outside deck and support columns not to code and unsafe;

(o) fiberglass hot tub cracked caused by shifting deck.

The plaintiffs have not proven by a fair preponderance of the evidence some of these claims of defective or incomplete work, including the following subsections of paragraph 3 of the complaint: (a), (b), (e), (h), (l), (n) and (o). These claims of damages were not proven for one or more of the following reasons: (1) insufficient evidence; (2) adequate substitute work; (3) the work requested is beyond the requirements of the contract; (4) the damage was caused by someone other than the defendant; or (5) the condition or work was consented to by the plaintiffs. The defendant installed all of the Townsend panelling that the plaintiffs were entitled to under the contract and more. The television antenna was not damaged by the roof construction done by the defendant's subcontractors, and it was replaced on the roof exactly where the plaintiffs requested. The problems with the deck were caused by the plaintiffs' own conduct in moving a fiberglass hot tub onto the deck, which was not designed to support it when filled with water. Building the deck to carry the fiberglass hot tub was not part of the plans or contract. The deck and support columns were adequate for normal use. While the plans called for four Anderson windows, they were replaced by three larger windows and a medicine cabinet worth at least the same value, and with the consent of the plaintiffs.

While some of the cracked floor tiles in the kitchen were replaced, $212 is allowed to replace other broken tiles. The siding did not conform to the contract and $1,317.50 is allowed for the siding. An allowance of $275 is adequate to replace the damaged trim molding, and $275 is also allowed to complete the bathroom.

The major problem is a leaky roof due to defective construction, aggravated by failure to use tarpaper in accordance with customary building practice and the requirements of the Connecticut Building Code. The original plans originally called for tarpaper as an underlayment. The existing house did not have tarpaper under the shingles. Condon and Habetz discussed whether tarpaper should be used, and Habetz consented to completing the roof on the addition without it in return for a credit for not installing it. The plaintiffs spent $3,365 to repair ceiling, wall CT Page 7775 and floor water damages from the leaky roof, and an additional $400 is allowed for unrepaired damage.

The entire roof on the addition has to be replaced which requires removing the existing roof, putting down tarpaper and reshingling the roof. The evidence was conflicting as to the cost of the required work, but the reasonable value of labor and materials for roof repairs and to dispose of existing roof materials is $8,420. An additional $2,078 is allowed to complete the inadequate insulation, and $200 is required to repair the cracked chimney.

The plaintiffs contend in the second count of the complaint that the construction work performed by the defendant was subject to the Home Improvement Act and that the written agreement of April 20, 1989 violated 20-429 (a) of the General Statutes. The complaint does not state how the plaintiffs were injured or sustained any financial loss because of noncompliance with the statute, which provides as follows:

"No home improvement contract shall be valid or enforceable against an owner unless it: (1) is in writing, (2) is signed by the owner and contractor, (3) contains the entire agreement between the owner and the contractor, (4) contains the date of the transaction, (5) contains the name and address of the contractor, (6) contains a notice of the owner's cancellation rights in accordance with the provisions of chapter 740, (7) contains a starting date and completion date, and (8) is entered into by a registered salesman or registered contractor. Each change in the terms and conditions of a contract shall be in writing and shall be signed by the owner and contractor."

This version of the statute was effective October 1, 1988. The contract between the parties here was made on April 20, 1989. The defendant was a contractor subject to the Home Improvement Act (HIA) and the contract and written list of extras were a home improvement contract. The contract complied with the version of20-429 (a) which existed prior to October 1, 1988, since it was in writing and contained the entire agreement between the parties. The original contract for $103,000 meets all of the requirements of the amended statute except subsection (6). Page 5 of the contract contains what amounts to starting and completion dates. Section20-429

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conaway v. Prestia
464 A.2d 847 (Supreme Court of Connecticut, 1983)
Bruni v. Behnke
128 A.2d 543 (Supreme Court of Connecticut, 1956)
M. J. Daly & Sons, Inc. v. New Haven Hotel Co.
99 A. 853 (Supreme Court of Connecticut, 1917)
Emlee Equipment Leasing Corp. v. Waterbury Transmission, Inc.
595 A.2d 951 (Connecticut Superior Court, 1991)
Kulak v. Landers, Frary Clark
2 Conn. Super. Ct. 69 (Connecticut Superior Court, 1935)
Hinchliffe v. American Motors Corp.
440 A.2d 810 (Supreme Court of Connecticut, 1981)
Caulkins v. Petrillo
513 A.2d 43 (Supreme Court of Connecticut, 1986)
Lamb v. Burns
520 A.2d 190 (Supreme Court of Connecticut, 1987)
Atlantic Richfield Co. v. Canaan Oil Co.
520 A.2d 1008 (Supreme Court of Connecticut, 1987)
Paulsen v. Manson
525 A.2d 1315 (Supreme Court of Connecticut, 1987)
Gargano v. Heyman
525 A.2d 1343 (Supreme Court of Connecticut, 1987)
Barrett Builders v. Miller
576 A.2d 455 (Supreme Court of Connecticut, 1990)
A. Secondino & Son, Inc. v. LoRicco
576 A.2d 464 (Supreme Court of Connecticut, 1990)
Liljedahl Bros. v. Grigsby
576 A.2d 149 (Supreme Court of Connecticut, 1990)
Sidney v. DeVries
575 A.2d 228 (Supreme Court of Connecticut, 1990)
A-G Foods, Inc. v. Pepperidge Farm, Inc.
579 A.2d 69 (Supreme Court of Connecticut, 1990)
Argentinis v. Gould
592 A.2d 378 (Supreme Court of Connecticut, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 7772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/habetz-v-condon-no-cv90-03-32-36s-sep-27-1991-connsuperct-1991.