Edens v. Kole Construction Co.

450 A.2d 1161, 188 Conn. 489, 1982 Conn. LEXIS 608
CourtSupreme Court of Connecticut
DecidedSeptember 28, 1982
StatusPublished
Cited by29 cases

This text of 450 A.2d 1161 (Edens v. Kole Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edens v. Kole Construction Co., 450 A.2d 1161, 188 Conn. 489, 1982 Conn. LEXIS 608 (Colo. 1982).

Opinion

*490 Arthur H. Healey, J.

This is an action for breach of a construction contract to build a single family residence. On March 9, 1973, the plaintiffs-purchasers entered into a contract with the defendant building contractor for the construction of a house on Perkins Road in Greenwich. The total contract price was $128,000 and the parties have stipulated that $103,000 was actually paid to the defendant. Although the house was contracted to be completed in August, 1973, it had not been completed by September 28, 1973, at which time the plaintiffs determined that the defendant’s work was defective and notified the defendant that they were terminating the contract. In fact, no certificate of occupancy was issued until April, 1974.

The plaintiffs moved into the house in September, 1973, before final completion but with the knowledge of the defendant. Two or three weeks after the plaintiffs had moved in, there was a heavy rainstorm which was part of a tornado in the area. The roof on the plaintiffs’ house leaked in- many places during this storm. The plaintiffs called the defendant who allegedly repaired the leaks and placed a plastic cover on the entire roof. The plaintiffs also found that there were leaks into the basement of the house from the roof and that the gutter pipes were improperly hooked onto the drainpipes. The plaintiffs also claimed that there were many other defective or incomplete items in the house 1 besides the leaky roof and improperly installed drainpipes.

*491 The plaintiffs filed suit seeking $100,000 in damages for the defective construction of the house and an injunction ordering the immediate release of a mechanic’s lien which the defendant filed on the plaintiffs’ property. The defendant counterclaimed alleging that it had completed its obligations under the contract and that the plaintiffs still owed approximately $52,430.93 for the remainder of the contract price and extras. The defendant also counterclaimed for foreclosure of the above-mentioned mechanic’s lien. 2

The trial court filed two memoranda of decision and a special finding of facts. 3 It found for the plaintiffs on the complaint but also found that the evidence justified an award of only $17,152.65 plus interest to the plaintiffs for the defective roof and the improperly installed drainpipes. In addition, the trial court specifically found for the plaintiffs on the defendant’s counterclaim. It held that there was sufficient justification for the plaintiffs’ action in terminating the contract in light of the evidence that the roof had been poorly installed and the evidence of the large number of items which were unfinished a month after the house was scheduled to be completed. The court also found, in response to the defendant’s motion to reopen, that the defendant was not entitled to the $25,000 balance of the con *492 tract price because it had not completed the contract. The court stated that only $103,000 was due and that the plaintiffs had already paid that amount. Finally, the court found that the defendant’s evidence 4 in support of its contention that it had completed 97 percent of the construction was “unconvincing” because the estimate was based on “what sounded like a cursory inspection . . .

The defendant has raised four claims of error in this appeal. Specifically, it claims that the trial court erred by failing to subtract the plaintiffs’ $17,152.65 damage award from the $25,000 balance due the defendant on the contract; by improperly finding that the defendant was entitled to no part of the $25,000 balance on the contract; by inconsistently holding that the plaintiffs’ evidence was insufficient to warrant a monetary award but also that the plaintiffs were entitled to an award of $17,152.65 plus no obligation to pay the remaining $25,000 balance on the contract; and by totally rejecting the $21,831.63 counterclaim for “extras” performed.

The defendant’s first two claims of error address the same issue. That issue is basically whether the court erred by failing to net the plaintiffs’ $17,152.65 damage award against the $25,000 balance allegedly due the defendant under the contract. The defendant alleges that it substantially performed the contract by completing 97 percent of the construction and, therefore, is entitled to 97 *493 percent of the contract price offset by the amount already paid by the plaintiffs plus the additional damage award of the court. 5

At the outset, we note that the defendant has not challenged the award of $17,152.65 in damages to the plaintiff for the defective roof and drainpipes. We understand its claim of error to refer only to the trial court’s refusal to find that it was entitled to the $25,000 balance allegedly due on the contract and in the court’s failure to deduct the damage award from this balance.

We must determine if the defendant sufficiently proved his claim that he was entitled to the balance due on the contract by virtue of his alleged 97 percent completion of the contract. The contract between the parties provided as follows: “In the event the BUILDER shall breach this contract, or shall neglect to prosecute the work hereunder diligently and properly or in the event the BUILDER is adjudged a bankrupt or shall make an assignment for the benefit of creditors, or if the assets of the BUILDER are placed in the hands of a receiver, then this contract shall terminate at the option of the OWNER upon ten (10) days’ written notice given to the BUILDER, and the OWNER shall not be further obligated to make any additional payments hereunder (except those to which the BUILDER shall be entitled for work already performed), fully reserving to himself any and all rights and remedies which he may have at law or in equity against the BUILDER.” (Emphasis added.) *494 “ ‘There is no reason why one who has substantially performed ... a [building] contract, but unintentionally failed of strict performance in the matter of minor details, should have imposed upon him as a condition of recovery for that of which the other party has received the benefit, the burden of showing by direct evidence its reasonable value, or why he should be deprived of all benefit of the contract which he has substantially performed.’ Daly & Sons v. New Haven Hotel Co., 91 Conn. 280, 287-88, 99 A. 853 (1917).” Vincenzi v. Cerro, 186 Conn. 612, 615, 442 A.2d 1352 (1982).

Substantial performance of a building contract, however, is ordinarily a question of fact for the trier to determine. Randolph Construction Co. v. Kings East Corporation, 165 Conn. 269, 274, 334 A.2d 464 (1973); Chinigo v. Ehrenberg, 112 Conn. 381, 384, 152 A. 305 (1930); Daly & Sons v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pettit v. HAMPTON AND BEECH, INC.
922 A.2d 300 (Connecticut Appellate Court, 2007)
Carmel Homes v. Bednar, No. Cv 99-0079393 S (Oct. 1, 2001)
2001 Conn. Super. Ct. 13475 (Connecticut Superior Court, 2001)
Pisani Construction, Inc. v. Kruger, No. Cv-97-0328803-S (Sep. 15, 2000)
2000 Conn. Super. Ct. 11218 (Connecticut Superior Court, 2000)
Bouchard v. Boyer, No. 543089 (May 17, 1999)
1999 Conn. Super. Ct. 6067 (Connecticut Superior Court, 1999)
Shay v. Gallagher, No. Cv 93-0302341 (Jan. 23, 1995)
1995 Conn. Super. Ct. 430-F (Connecticut Superior Court, 1995)
Normand Josef Enterprises, Inc. v. Connecticut National Bank
646 A.2d 1289 (Supreme Court of Connecticut, 1994)
State v. Cavell
641 A.2d 426 (Connecticut Appellate Court, 1994)
Gould v. Valus, No. Cv88 0247598 S (Sep. 25, 1991)
1991 Conn. Super. Ct. 7811 (Connecticut Superior Court, 1991)
Argentinis v. Gould
592 A.2d 378 (Supreme Court of Connecticut, 1991)
Hines v. Westfield Inc., No. Cv-88-0251120 S (Apr. 29, 1991)
1991 Conn. Super. Ct. 3735 (Connecticut Superior Court, 1991)
Dinehart v. Berube, No. 29 01 48 (Apr. 25, 1991)
1991 Conn. Super. Ct. 3404 (Connecticut Superior Court, 1991)
Cianci Constr. Co. v. Griffin Constr. Co., No. 27 77 93 (Feb. 4, 1991)
1991 Conn. Super. Ct. 1461 (Connecticut Superior Court, 1991)
Argentinis v. Gould
579 A.2d 1078 (Connecticut Appellate Court, 1990)
Ozkan v. Ozkan
556 A.2d 628 (Connecticut Appellate Court, 1989)
Nor'easter Group, Inc. v. Colossale Concrete, Inc.
542 A.2d 692 (Supreme Court of Connecticut, 1988)
Sunbury v. Sunbury
538 A.2d 1082 (Connecticut Appellate Court, 1988)
State v. Navikaukas
533 A.2d 1214 (Connecticut Appellate Court, 1987)
Howie's Painting Service, Inc. v. Ferreria
532 A.2d 1318 (Connecticut Appellate Court, 1987)
Goold v. Goold
527 A.2d 696 (Connecticut Appellate Court, 1987)
Boland v. Catalano
521 A.2d 142 (Supreme Court of Connecticut, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
450 A.2d 1161, 188 Conn. 489, 1982 Conn. LEXIS 608, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edens-v-kole-construction-co-conn-1982.