Bouchard v. Boyer, No. 543089 (May 17, 1999)

1999 Conn. Super. Ct. 6067
CourtConnecticut Superior Court
DecidedMay 17, 1999
DocketNo. 543089
StatusUnpublished

This text of 1999 Conn. Super. Ct. 6067 (Bouchard v. Boyer, No. 543089 (May 17, 1999)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bouchard v. Boyer, No. 543089 (May 17, 1999), 1999 Conn. Super. Ct. 6067 (Colo. Ct. App. 1999).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

POST-TRIAL MEMORANDUM OF DECISION CT Page 6068
I. PROCEDURAL BACKGROUND
On July 29, 1997, the plaintiff, Gerard J. Bouchard, d/b/a Bouchard Builders Company (hereinafter the "plaintiff"), filed a three-count complaint against the defendant, Kenneth G. Boyer, d/b/a New England Investors (hereinafter the "defendant"), for breach of contract, quantum meruit/unjust enrichment and for violations of the Connecticut Unfair Trade Practices Act. On November 3, 1997, the defendant filed a five-count counterclaim sounding in breach of contract, breach of implied warranty, negligence, unfair trade practices and breach of implied covenant of good faith and fair dealing. Both parties seek money damages, punitive damages, costs, interest and attorney's fees.

Following a non-jury trial before this court, the parties filed post-trial memoranda on February 11, 1999. The court now makes the following findings of fact and conclusions of law.

II. FINDINGS OF FACT AND CONCLUSIONS OF LAW
The plaintiff is an experienced contractor and the defendant is a real estate investor. The parties entered into a contract on April 12, 1996, whereby the plaintiff agreed to construct a single-family dwelling on land owned by the defendant. The contract is a standard owner-contractor agreement form, as drafted by the American Institute of Architects (AIA), Document A101 (hereinafter the "Contract"). Article 1 of the contract expressly incorporates by reference "General Conditions of the Contract" as set forth in AIA Document A201 (hereinafter "General Conditions"). See Defendant's Exhibit 14.

A. The Contract
The project is specified as a single-family house on lot number three at 6 Somerset Lane, Old Lyme, Connecticut. Article 2 sets forth eleven specifications to constitute the work required of the plaintiff. Specifically, the plaintiff was obligated to: "construct a single family house per plans; no kitchen and or bath cabinets/countertops furnished or installed; no appliances; no wallpaper and or wall coverings; no fill material supplied or installed; no water or rock removal; no removal of contaminated materials; no stump removal from site, only burial on site; wood CT Page 6069 beams in place of steel; fireplace flue to be 12" x 12", furnace flue to be 8" x 8"; no wood ceiling in master bedroom." See Contract, Article 2, Nos. 1 through 11. Article 3 establishes April 9, 1996, as the date of commencement, and September 14, 1996, as the date at which the plaintiff was required to achieve substantial completion of the entire project. Article 4 states that the total contract price is $220,000, and also sets forth a "lite fixtures allowance" for $2000, and a "tree clearing allowance" for $1500. Changes to the contract and the contract price are permissible and accomplished by execution of a written Change Order signed by all parties. See General Conditions, §§ 7.1, 7.2.

B. Undisputed Modifications: The Change Orders
On April 23, 1996, the parties signed and agreed to Change Order Number MC1, which changed the contract as follows: "Truck and place sanitary fill as required by site plan [$1,700]; Add footing drains per site plan [$370]; Add infiltrators per site plan [$1,784]." The contract price was agreed to be increased from $220,000 to $223,854.

On May 29, 1996, the parties signed and agreed to Change Order Number MC2, which changed the contract as follows: "Blast ledge in foundation area to obtain foundation depth [$1,600]; Excavator to move blasting mats and remove rock [$1,200]." The contract price was thereby increased from $223,854 to $226,654, and the date of substantial completion was extended from September 14, 1996 to September 18, 1996.

On July 3, 1996, the parties signed and agreed to Change Order Number MILEC-02, which, through various changes and credits, decreased the total contract price by $14,860. Thus, as of July 3, 1996, the total contract price owed by the defendant was $211,794.

The parties further agree that two verbal change orders increased the contract price by $750 for stump removal, and $9,007 for kitchen cabinets. Therefore, after adding these items, the total contract price was at $221,551. The parties also agree that the contract price was further reduced by $1,100 (granite top credit), $600 (two cabinets credit), $4,115 (direct payment to Kitchen Beautiful by defendant), and $1,000 (direct payment to Ray's Sheetmetal by defendant). The contract price was therefore reduced by $6,815, so as to bring the total contract price to CT Page 6070$214,736.

C. Disputed Additions Subtractions
The plaintiff asserts that the contract price was increased by $3,854 (septic system), $1,200 (Jacuzzi), $1,700 (septic fill), $1,400 (excavator blasting), and $5,000 (site fill), for a total amount of $13,154. Thus, according to the plaintiff, the total contract price should be $227,890. The defendant disputes these additions.

The plaintiff also adds $3,591 as the balance to complete the contract, thus increasing the contract price to $231,481. However, the plaintiff subtracts $800 (light fixture allowance), $100 (tub surround) and $1000 (floor finish) to decrease the contract price to $229,581.

D. Balance Due
The parties agree that the defendant, as of November 13, 1996, made payments to the plaintiff totaling $218,480.12. Thus, according to the total contract price as asserted by the defendant ($214,736), the defendant overpaid by $3,744.12. According to the contract price asserted by the plaintiff ($229,581), however, the defendant owes $11,100.88.

E. Other Amounts Claimed
The plaintiff, in addition to claiming that he is due $11,100.88 pursuant to the contract, also claims he is owed interest at 1.5% for thirteen months, $8,209.40 in attorney's fees and costs, and $16,418.80 in double attorney's fees under CUTPA. According to the plaintiff, therefore, the total amount owed to him by the defendant is $38,088.75.

The defendant, on the other hand, claims that he paid an additional $17,324.76 to complete the construction of the house, plus $13,375 for the cost of missing items that the plaintiff allegedly failed to install. The defendant also claims $20,636.99 in attorney's fees, plus $21,703.26 in interest on his construction loan after the contract date of completion, and $25,550.24 as the balance of 15% lost profit from projected sale price of home. Thus, including the $3,744.12 that the defendant claims he overpaid, the defendant claims that the plaintiff owes him a total of $102,334.37. CT Page 6071

F. The Plaintiff's Case
1. Breach of Contract
In his breach of contract claim, the plaintiff alleges that the defendant: (1) failed to make a progress payment and payment in full for the substantially completed work; and (2) wrongfully terminated the plaintiff without giving the contractually-required seven-day written notice.

(a) Substantial Performance
The court must first determine whether the plaintiff substantially performed his contractual obligations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cuddy Mountain Concrete, Inc. v. Citadel Construction, Inc.
824 P.2d 151 (Idaho Court of Appeals, 1992)
Ravitch v. Stollman Poultry Farms, Inc.
328 A.2d 711 (Supreme Court of Connecticut, 1973)
Bertozzi v. McCarthy
323 A.2d 553 (Supreme Court of Connecticut, 1973)
Edens v. Kole Construction Co.
450 A.2d 1161 (Supreme Court of Connecticut, 1982)
Hartford Electric Applicators of Thermalux, Inc. v. Alden
363 A.2d 135 (Supreme Court of Connecticut, 1975)
Silliman Co. v. S. Ippolito & Sons, Inc.
467 A.2d 1249 (Connecticut Appellate Court, 1983)
Chinigo v. Ehrenberg
152 A. 305 (Supreme Court of Connecticut, 1930)
Walter Kidde Constructors, Inc. v. State
434 A.2d 962 (Connecticut Superior Court, 1981)
Providence Washington Insurance v. Beck
255 N.E.2d 600 (Massachusetts Supreme Judicial Court, 1970)
Multi-Service Contractors, Inc. v. Town of Vernon
477 A.2d 653 (Supreme Court of Connecticut, 1984)
Nor'easter Group, Inc. v. Colossale Concrete, Inc.
542 A.2d 692 (Supreme Court of Connecticut, 1988)
Warner v. Konover
553 A.2d 1138 (Supreme Court of Connecticut, 1989)
Argentinis v. Gould
592 A.2d 378 (Supreme Court of Connecticut, 1991)
Habetz v. Condon
618 A.2d 501 (Supreme Court of Connecticut, 1992)
Hartford Whalers Hockey Club v. Uniroyal Goodrich Tire Co.
649 A.2d 518 (Supreme Court of Connecticut, 1994)
Weisman v. Kaspar
661 A.2d 530 (Supreme Court of Connecticut, 1995)
Saturn Construction Co. v. Premier Roofing Co.
680 A.2d 1274 (Supreme Court of Connecticut, 1996)
Burns v. Koellmer
527 A.2d 1210 (Connecticut Appellate Court, 1987)
Rokalor, Inc. v. Connecticut Eating Enterprises, Inc.
558 A.2d 265 (Connecticut Appellate Court, 1989)
Argentinis v. Gould
579 A.2d 1078 (Connecticut Appellate Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Conn. Super. Ct. 6067, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bouchard-v-boyer-no-543089-may-17-1999-connsuperct-1999.