Cuddy Mountain Concrete, Inc. v. Citadel Construction, Inc.

824 P.2d 151, 121 Idaho 220, 1992 Ida. App. LEXIS 6
CourtIdaho Court of Appeals
DecidedJanuary 2, 1992
Docket18701
StatusPublished
Cited by13 cases

This text of 824 P.2d 151 (Cuddy Mountain Concrete, Inc. v. Citadel Construction, Inc.) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cuddy Mountain Concrete, Inc. v. Citadel Construction, Inc., 824 P.2d 151, 121 Idaho 220, 1992 Ida. App. LEXIS 6 (Idaho Ct. App. 1992).

Opinions

SILAK, Judge.

Citadel Construction was the general contractor for the construction of a Shopko store in Lewiston, Idaho. Cuddy Mountain Concrete, the concrete subcontractor, brought a breach of contract action against Citadel after Citadel terminated its subcontract. Following a trial, the jury awarded Cuddy Mountain $74,000 on its breach of contract claim, which included lost profits and punitive damages. The trial court denied Citadel’s motion for a new trial and its motion for a judgment notwithstanding the verdict. Citadel has appealed this decision. For the reasons stated below, we affirm the judgment of the district court.

I. FACTS AND PROCEDURAL BACKGROUND

On March 23, 1987, Cuddy Mountain and Citadel entered into a written contract titled “Subcontract Agreement.” Cuddy Mountain agreed to provide labor and all incidental materials to build the concrete footings, pads, foundation walls, and all concrete flatwork for the construction of a Shopko store in Lewiston. Citadel agreed to pay Cuddy Mountain $92,209 for its work. The Subcontract Agreement incorporated the terms of the contract between Citadel and Shopko. One of the terms of the Citadel-Shopko contract requires seven days’ written notice before the contractor or a subcontractor can be terminated for cause.

Cuddy Mountain began work on the project in April, 1987. The parties presented conflicting testimony on the issue whether a work schedule existed and whether the schedule was modified at daily and weekly meetings. Rainy weather affected the ability of both parties to complete their work.

The most divisive problems occurred in the middle of May. On May 12, Larry Bratcher, owner of Cuddy Mountain, stopped work because of rain. Larry Hueter, project manager for Citadel, became angry and told Bratcher to keep pouring concrete even though the rain could affect the quality of the work; nevertheless, Bratcher refused to continue working. [223]*223Hueter summoned Bratcher to the job shack later that day for a meeting to discuss how Cuddy Mountain was going to finish the project. During the meeting, Hueter told Bratcher that Shopko was dissatisfied with Bratcher’s work. Hueter mentioned three specific complaints: there were too many concrete workers at the job site; the quality of the work was poor; and Cuddy Mountain failed to provide a “pour” schedule. Hueter told Bratcher that Cuddy Mountain needed to improve its performance or he would seek another concrete subcontractor. A heated, acrimonious exchange ensued. From this point on, communications between Citadel and Cuddy Mountain deteriorated rapidly.

On May 15, more time was lost because of bad weather. Bratcher cancelled his crew. This displeased Rick Walther, the construction manager for Citadel, because he felt that other work could have been done. Walther asked Cuddy Mountain to work the following Saturday to make up for the time lost due to rain. Cuddy Mountain declined because it already had other commitments.

There was conflicting testimony regarding the effect of Cuddy Mountain’s allegedly slow progress. Hueter testified that, on a project of this nature, the concrete subcontractor should only require minimum supervision from the general contractor, but that he had had to heavily assist Cuddy Mountain with its work. Bratcher testified that he was never behind schedule. Hueter disagreed and testified that Cuddy Mountain was not performing its work in a manner consistent with the flow of the project.

On May 18, Hueter faxed a termination letter to Cuddy Mountain without having given Cuddy Mountain the required seven-day written notice. Hueter was frustrated with Cuddy Mountain’s poor production and lack of commitment to the job. Prior to the termination, Hueter met with a replacement contractor, Kirby Prendiville, who was able to begin working the day after Cuddy Mountain was fired. Prendiville and Citadel completed the concrete work eight days behind the original schedule. After being terminated by Citadel, Cuddy Mountain obtained a contract for a small construction project at the Culdesac Granary.

After Cuddy Mountain was terminated, Hueter asked Walther to supplement the daily reports for the period prior to the termination with comments regarding Cuddy Mountain’s performance. Hueter told Walther that he wanted a more specific record of Cuddy Mountain’s work in case something happened after the termination. Walther had written the original reports on a daily basis as the work progressed. The new comments were written on the original reports. There is no indication on the face of the records that they were written at a later time. Walther testified that he did not falsify the records in any way and that he did not intend to create the impression that the additional comments were written contemporaneously with the original daily reports. Tom Rogers, Shopko’s on-site representative, also drafted a report regarding Cuddy Mountain’s substandard performance. Rogers dated this report May 19 but actually did not write the report until July. The report emphasized the inexperience of Cuddy Mountain’s crew and lack of supervision as the cause of the slow progress on the Shopko project.

The breach of contract theory was tried on the basis that Cuddy’s performance was adequate, that the termination without seven days’ notice violated the contract, and that Citadel’s conduct was egregious in terms of the manner of communication, and in terms of the falsification of documents later. Cuddy Mountain claimed several different components of contract damages. Cuddy Mountain’s total bid for the Shopko project was $92,209. As of May 18, 1987, the date of its termination, Cuddy Mountain had performed $1,164 worth of extra work, bringing the total contract value of the work to $93,373. Citadel paid Cuddy Mountain $34,620.30 for the work it had performed prior to termination. At trial, Cuddy Mountain claimed it was entitled to an additional $24,340 for the work completed prior to termination. This amount does not include $5,965 in liens which were satisfied by Citadel. The jury awarded Cuddy [224]*224Mountain $24,341 as additional payment for the work it completed prior to termination. The jury further awarded $25,000 in punitive damages, $9,300 in lost profits, and $14,700 for interest on an operating loan which had not been repaid.

Citadel filed a motion for judgment notwithstanding the verdict pursuant to I.R.C.P. 50(b), a motion to alter or amend the judgment pursuant to I.R.C.P. 59(e), and a motion for a new trial pursuant to I.R.C.P. 59(a)(5) (excessive damages), I.R.C.P. 59(a)(6) (insufficiency of the evidence), and I.R.C.P. 59(a)(7) (error of law). The trial court issued an opinion and order denying Citadel’s motions, with the exception that the court granted Citadel’s post-trial motion for judgment notwithstanding the verdict with regard to the award of interest on the operating loan. The court found that Cuddy Mountain had not proved that this was a natural and ordinary consequence of Citadel’s breach of contract and could not have been “reasonably expected by the parties to the contract at the time the contract was made.” No appeal was taken from this ruling.

After the trial court denied Citadel’s motions, Cuddy Mountain filed a motion for pre-judgment interest; the court granted $8,850.76 in pre-judgment interest on the award of the value of work completed, and $3,209.94 in pre-judgment interest on the award for lost profit. The court also awarded costs and attorney fees. Citadel has not appealed from the district court’s orders awarding pre-judgment interest, costs and attorney fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thurston and T3 v. Safeguard
Idaho Supreme Court, 2019
Thurston Enters., Inc. v. Safeguard Bus. Sys., Inc.
435 P.3d 489 (Idaho Supreme Court, 2019)
Hansen-Rice, Inc. v. Celotex Corp.
414 F. Supp. 2d 970 (D. Idaho, 2006)
General Auto Parts Co. v. Genuine Parts Co.
979 P.2d 1207 (Idaho Supreme Court, 1999)
State v. Gile
985 P.2d 199 (Court of Appeals of Oregon, 1999)
Bouchard v. Boyer, No. 543089 (May 17, 1999)
1999 Conn. Super. Ct. 6067 (Connecticut Superior Court, 1999)
Magic Valley Truck Brokers, Inc. v. Meyer
982 P.2d 945 (Idaho Court of Appeals, 1999)
Walston v. Monumental Life Insurance
923 P.2d 456 (Idaho Supreme Court, 1996)
Badell v. Badell
835 P.2d 677 (Idaho Court of Appeals, 1992)
Cuddy Mountain Concrete, Inc. v. Citadel Construction, Inc.
824 P.2d 151 (Idaho Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
824 P.2d 151, 121 Idaho 220, 1992 Ida. App. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cuddy-mountain-concrete-inc-v-citadel-construction-inc-idahoctapp-1992.