The Roost Project, LLC v. Andersen Construction Company

CourtDistrict Court, D. Idaho
DecidedFebruary 4, 2020
Docket1:18-cv-00238
StatusUnknown

This text of The Roost Project, LLC v. Andersen Construction Company (The Roost Project, LLC v. Andersen Construction Company) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Roost Project, LLC v. Andersen Construction Company, (D. Idaho 2020).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF IDAHO

THE ROOST PROJECT, LLC, a California limited liability company, Case No. 1:18-cv-00238-CWD Plaintiff/Counterdefendant, MEMORANDUM DECISION vs. AND ORDER

ANDERSEN CONSTRUCTION COMPANY, an Oregon corporation,

Defendant/Counterclaimant.

INTRODUCTION This case involves a dispute regarding the respective rights, obligations, and liabilities of the parties arising out of and relating to construction of The Fowler building in downtown Boise, Idaho. The Roost Project, LLC (Roost) and Andersen Construction Company (ACCO) entered into a contract (the Construction Agreement) to build The Fowler in December 2015. The project was delayed for a host of different reasons resulting in The Fowler being finished eight months after the initial contract completion date. As a result, Roost initiated this action against ACCO raising contract and tort claims. ACCO denies those claims and has filed counterclaims against Roost. Presently before the Court are the parties cross motions for partial summary judgment, Roost’s motion to amend the complaint to add punitive damages, and ACCO’s motion to strike. The motions are fully briefed. The Court conducted a hearing on December 12, 2019. After careful consideration of the record, the parties’ briefing and supporting materials, and oral argument, the Court finds there are several genuine issues

of material fact in this case which preclude summary judgment. The Court will therefore deny both summary judgment motions. The Court will also deny the motion to add punitive damages. The motion to strike will be granted in part and denied in part. FACTS 1 1. The Construction Agreement

On December 11, 2015, Roost and ACCO entered into the Construction Agreement to build The Fowler, a mixed-use building predominately developed as a residential apartment complex. (Dkt. 10-1.) The substantial completion date for the project was in June 2017. (Dkt. 10-2, Ex. B.) The project broke ground on February 5, 2016, and was substantially completed on February 21, 2018, eight months after the contract completion date. The parties disagree over which party breached and which party performed under the

Construction Agreement and whether either party is otherwise liable for or entitled to damages outside of the contract. Roost contends ACCO breached several terms of the Construction Agreement and is not entitled to any relief. Generally, Roost argues ACCO failed to deliver the project on time and failed to provide the project schedule updates, reports, and notices required by the

Construction Agreement. Further, Roost argues ACCO mismanaged the project,

1 The parties each submitted a statement of facts with their respective summary judgment motions. (Dkt. 36, 40.) When discussing the facts, the parties’ arguments, and the record herein, the Court will cite to the portion of the applicable statement of facts wherein the supporting documents are cited or will cite directly to the record or document itself. misrepresented the project’s status, and concealed information about the project from Roost. ACCO disputes Roost’s claims, countering that it performed under the terms of the

Construction Agreement, did not misrepresent or conceal information, properly managed the project, and that Roost failed to act in good faith by refusing to approve changes and equitable adjustments to the project schedule. Several provisions of the Construction Agreement are implicated by the parties’ positions in this case. The following are particularly relevant.

A. Contractor’s General Representations and Warranties Section 5.9 states, in relevant part: Contractor makes the following express representations and warranties to Owner, which are continuing during the term of this Agreement:

5.9.2 Contractor has thoroughly and carefully examined the Contract Documents (as a contractor, not a licensed design professional), and has found them to be complete, coordinated and suitable for Contractor’s performance of the Work in accordance with this Agreement.

5.9.3 Contractor has thoroughly and carefully examined the Project Schedule and has found it to be complete and to provide suitable time for Contractor’s performance of the Work in accordance with this Agreement.

5.9.6 Contractor is familiar with the local and other conditions which may be material to Contractor’s performance of its obligations under the Contract Documents (including, but not limited to transportation, seasons and climates, access, the handling and storage of materials and fuel and availability and quality of labor and materials). Contractor has thoroughly and carefully examined the market conditions related to the Work, including the availability and pricing of materials, labor, supplies and all other things necessary for the performance of the Work and found them to be adequate for Contractor to perform the Work as provided in the Contract Documents.

(Dkt. 10-1 at § 5.9.) B. Project Schedule Notifications, Delays, and Changes The Construction Agreement states that ACCO will keep Roost “fully informed of

Contractor’s performance of the Work so Owner can have timely and meaningful opportunities to review and input” and “Contractor will promptly notify Owner of any actions or decisions required of Owner for Contractor to timely and properly perform the Work, and any deadlines pertaining thereto to prevent delays in the Work.” (Dkt. 10-1 at § 5.2.1 and § 5.2.2.) Article 8.1 addresses the project schedule, stating:

Contractor will commence performance of the Work upon Owner’s notice to proceed and will diligently and expeditiously continue its performance until all Work has been fully completed. The dates in the Project Schedule are of the essence and will not be exceeded by Contractor without Owner’s prior consent or as permitted in Section 8.3.2. If and when Contractor has reason to believe that any date in the Project Schedule may not be met, Contractor will make appropriate recommendations to Owner to keep the Work on schedule, bring the Work back on schedule and/or mitigate potential impacts of a delayed performance. Contractor represents and warrants to Owner that the Substantial Completion Deadline provides a reasonable time for completing the entire Work, including the time specified for the review of Contractor Submittals by Owner and Governmental Authorities.

Delays and extensions of time to the project schedule are covered by Article 8.3 which requires the Contractor to diligently avoid delays in timely performance and to immediately notify the Owner of any matter wholly or partially preventing or delaying timely performance and provide regular reports concerning the same. (Dkt. 10-1 at § 8.3.1.) Section 8.3.2, in particular, sets for the process for the Contractor to make a claim for an equitable adjustment to the project schedule where “the critical path of the Contractor’s performance is wholly or partially prevented or delayed due to” certain listed circumstances. (Dkt. 10-1 at § 8.3.2.) Changes in the work by the Owner are addressed in Article 10 of the Construction Agreement which sets forth the procedures for change orders and change directives. (Dkt.

10-1 at § 10.2, § 10.3.) Article 17 covers resolution of claims, setting forth the process for the Contractor to make a claim and setting forth the parties’ rights and responsibilities in resolving a claim. 2. Construction of The Fowler Between groundbreaking in February 2016 and July 2016, ACCO’s superintendent, Tom Hayes, provided project schedule updates to Roost on February 16, March 28, April

22, and June 27. Hayes provided a master schedule update on July 20, 2016 which reported a new substantial completion date of June 16, 2017, a delay of a few days from the original contract completion date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Thomas
249 P.3d 829 (Idaho Supreme Court, 2011)
Employers Mutual Casualty Co. v. Donnelly
300 P.3d 31 (Idaho Supreme Court, 2013)
DBSI/TRI v. v. Bender
948 P.2d 151 (Idaho Supreme Court, 1997)
Manning v. Twin Falls Clinic & Hospital, Inc.
830 P.2d 1185 (Idaho Supreme Court, 1992)
Magic Lantern Productions, Inc. v. Dolsot
892 P.2d 480 (Idaho Supreme Court, 1995)
Wolford v. Tankersley
695 P.2d 1201 (Idaho Supreme Court, 1985)
Peavey v. Pellandini
551 P.2d 610 (Idaho Supreme Court, 1976)
General Auto Parts Co. v. Genuine Parts Co.
979 P.2d 1207 (Idaho Supreme Court, 1999)
Cuddy Mountain Concrete, Inc. v. Citadel Construction, Inc.
824 P.2d 151 (Idaho Court of Appeals, 1992)
State Ex Rel. Kidwell v. Master Distributors
615 P.2d 116 (Idaho Supreme Court, 1980)
In Re Western Acceptance Corp., Inc.
788 P.2d 214 (Idaho Supreme Court, 1990)
Jones v. Panhandle Distributors, Inc.
792 P.2d 315 (Idaho Supreme Court, 1990)
Strong v. Unumprovident Corp.
393 F. Supp. 2d 1012 (D. Idaho, 2005)
Seiniger Law Office, P.A. v. North Pacific Insurance
178 P.3d 606 (Idaho Supreme Court, 2008)
Myers v. Workmen's Auto Insurance
95 P.3d 977 (Idaho Supreme Court, 2004)
Idaho Power Co. v. Cogeneration, Inc.
9 P.3d 1204 (Idaho Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
The Roost Project, LLC v. Andersen Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-roost-project-llc-v-andersen-construction-company-idd-2020.