The Roost Project, LLC v. Andersen Construction Company

District Court, D. Idaho·Decided October 26, 2020·No. 1:18-cv-00238·Unknown

Opinion

UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF IDAHO

THE ROOST PROJECT, LLC, a California limited liability company, Case No. 1:18-cv-00238-CWD Plaintiff/Counterdefendant, MEMORANDUM DECISION vs. AND ORDER

ANDERSEN CONSTRUCTION COMPANY, an Oregon corporation,

Defendant/Counterclaimant.

INTRODUCTION Before the Court is Plaintiff’s motion for sanctions due to spoliation of evidence. (Dkt. 84.)1 The motion is fully briefed and at issue. On October 5, 2020, the Court heard oral argument on the motion. After careful consideration of the record, the parties’ briefing and supporting materials, and oral argument, the Court will deny the motion for the reasons explained below. FACTUAL AND PROCEDURAL BACKGROUND This case arises out of a dispute regarding the rights, obligations, and liabilities of the parties relating to construction of The Fowler building in downtown Boise, Idaho.

1 There are other pending motions before the Court that will be addressed in separate orders. The Roost Project, LLC (Roost) and Andersen Construction Company (ACCO) entered into a contract (the Construction Agreement) to build The Fowler in December 2015. The

project was delayed for a host of different reasons resulting in The Fowler being finished eight months after the initial contract completion date. The parties disagree over the respective faults and liabilities for the project delays and resulting damages. As a result, Roost initiated this action raising several claims against ACCO: breach of the Construction Agreement; breach of the implied covenant of good faith and fair dealing; fraud; violation of the Idaho Consumer Protection Act; and breach of the

implied warranty of workmanship. (Dkt. 1, 10.) ACCO denies those claims and, on August 21, 2018, filed counterclaims for 1) breach of contract and the covenant of good faith and fair dealing; and 2) unjust enrichment and quantum meruit. (Dkt. 22.) A jury trial is scheduled to commence on November 2, 2020. In the motion presently before the Court, Roost argues ACCO failed to preserve

electronically stored information (ESI), the loss of which is prejudicial to Roost. Roost requests imposition of certain sanctions relating to the presentation of evidence at trial pursuant to Federal Rule of Civil Procedure 37(e)(1). LEGAL STANDARD “Spoliation is the destruction or significant alteration of evidence, or the failure to

preserve [evidence,] ... in pending or reasonably foreseeable litigation.” Compass Bank v. Morris Cerullo World Evangelism, 104 F.Supp.3d 1040, 1051-52 (S.D. Cal. 2015) (citing United States v. Kitsap Physicians Serv., 314 F.3d 995, 1001 (9th Cir. 2002)). Spoliation of ESI evidence is governed by Federal Rule of Civil Procedure 37(e) which states: If electronically stored information that should have been preserved in the anticipation or conduct of litigation is lost because a party failed to take reasonable steps to preserve it, and it cannot be restored or replaced through additional discovery, the court:

(1) upon finding prejudice to another party from loss of the information, may order measures no greater than necessary to cure the prejudice; or

(2) only upon finding that the party acted with the intent to deprive another party of the information's use in the litigation may:

(A) presume that the lost information was unfavorable to the party;

(B) instruct the jury that it may or must presume the information was unfavorable to the party; or

(C) dismiss the action or enter a default judgment. Fed. R. Civ. P. 37(e).2 Under Rule 37(e), the Court assesses four factors: 1) whether the information qualifies as ESI; 2) whether the ESI is “lost” and “cannot be restored or replaced through additional discovery;” 3) whether the ESI “should have been preserved in the anticipation or conduct of litigation;” and 4) whether the responding party failed to take reasonable steps to preserve the ESI. Colonies Partners, L.P. v. County of San Bernardino, No. 5:18-cv-00420-JGB (SHK), 2020 WL 1496444, at * 3 (C.D. Cal. Feb. 27, 2020); Fed. R. Civ. P. 37(e). If these factors are satisfied, and the Court finds there is “prejudice to another party from [the] loss of the [ESI],” the Court may “order measures no greater than

2 Courts formerly imposed spoliation sanctions based on both their inherent authority and Rule 37. Following the 2015 Amendments to the Federal Rules, Rule 37(e) is the exclusive remedy for the loss of ESI. See Fed. R. Civ. P. 37(e), Adv. Comm. Notes to 2015 Amendment; Stevens v. Brigham Young Univ.-Idaho, No. 4:16-CV-530-BLW, 2019 WL 6499098, at *3 (D. Idaho Dec. 3, 2019). Accordingly, the Court considers the motion only under Rule 37(e). necessary to cure the prejudice.” Fed. R. Civ. P. 37(e)(1). If the party that was required to preserve the ESI “acted with the intent to deprive another party of the information’s use

in the litigation,” Rule 37(e)(2) authorizes the following sanctions: 1) a presumption that the lost information was unfavorable to the non-moving party; 2) instructing the jury that it may or must presume the information was unfavorable to the non-moving party; or 3) dismiss the action or enter a default judgment. “‘The applicable standard of proof for spoliation in the Ninth Circuit appears to be by a preponderance of the evidence.’” Compass Bank, 104 F.Supp.3d at 1052-53. The

party moving for spoliation sanctions under Rule 37 bears the burden of establishing spoliation by demonstrating that the non-moving party destroyed information or data and had some notice that the information or data was potentially relevant to the litigation before it was destroyed. Ryan v. Editions Ltd. West, Inc., 786 F.3d 754, 766 (9th Cir. 2015); see also Kitsap Physicians Serv., 314 F.3d at 1001.

ANALYSIS The evidence at issue on this motion relates to electronic schedule updates for The Fowler sent by ACCO to Roost between June 7, 2016, and January 5, 2018. (Dkt. 84-1.) During this period of time, Roost received schedule updates from ACCO only in a portable document format (“.pdf”). Prior to June 7, 2016, the schedule updates were sent

to Roost in a Microsoft Project format (“.mpp”). Roost argues the .mpp files contain important schedule logic information and data that is not included in the .pdf versions of the schedule updates. Namely, information describing when revisions were made to the schedule or when delays were first identified. That scheduling data was lost after June 7, 2016, Roost contends, because ACCO wrote over the .mpp files when making schedule updates without saving the native .mpp files of

the prior schedule. (Dkt. 84.) ACCO disputes that the .mpp files were lost or destroyed and maintains Roost has not established that ACCO had a duty to preserve the native .mpp files or shown that spoliation sanctions are appropriate. (Dkt. 88.) 1. The Information Qualifies as ESI. The information Roost seeks and argues has been lost is the “schedule logic” contained in the native versions of the .mpp files and information correlating the .mpp

Free access — add to your briefcase to read the full text and ask questions with AI

The Roost Project, LLC v. Andersen Construction Company, (D. Idaho 2020).

The Roost Project, LLC v. Andersen Construction Company (The Roost Project, LLC v. Andersen Construction Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Napster, Inc. Copyright Litigation
462 F. Supp. 2d 1060 (N.D. California, 2006)
Victoria Ryan v. Editions Limited West, Inc.
786 F.3d 754 (Ninth Circuit, 2015)
Glover v. Bic Corp.
6 F.3d 1318 (Ninth Circuit, 1993)
United States v. Kitsap Physicians Service
314 F.3d 995 (Ninth Circuit, 2002)
Compass Bank v. Morris Cerullo World Evangelism
104 F. Supp. 3d 1040 (S.D. California, 2015)
Akiona v. United States
938 F.2d 158 (Ninth Circuit, 1991)