Idaho Power Co. v. Cogeneration, Inc.

9 P.3d 1204, 134 Idaho 738, 2000 Ida. LEXIS 66
CourtIdaho Supreme Court
DecidedJuly 13, 2000
Docket24865
StatusPublished
Cited by62 cases

This text of 9 P.3d 1204 (Idaho Power Co. v. Cogeneration, Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaho Power Co. v. Cogeneration, Inc., 9 P.3d 1204, 134 Idaho 738, 2000 Ida. LEXIS 66 (Idaho 2000).

Opinion

SILAK, Justice.

This is an appeal by Cogeneration, Inc. (Cogeneration) from a district court judgment in favor of Idaho Power Company (Idaho Power) in a breach of contract action. We affirm.

I.

FACTUAL AND PROCEDURAL BACKGROUND

A. Factual Background

Cogeneration held a Federal Energy Regulatory Commission (FERC) license to construct a hydroelectric facility at Auger Falls on the Snake River. Under federal law, Idaho Power was obligated to enter into an agreement with Cogeneration for the purchase of power from the Auger Falls plant after its completion.

In January 1992, Idaho Power and Cogeneration entered into a “firm energy sales agreement” (the Agreement) that required Cogeneration to have the power plant constructed and on line by January 1, 1996 with operations to begin by February 1,1996, and to post a liquid security deposit (the security) to assure full and timely performance of its obligations. The security was to be paid in two installments: the first, on or before June 1, 1992 in the amount of $250,000, and the second, on or before January 1, 1994 in the amount of $1,874,800.

*741 The Agreement contained an additional clause, which excused any affected performance if an event of force majeure occurred. As defined in relevant part by the Agreement:

[F]orce majeure or an event of force majeure means any cause beyond the control of the Seller or of Idaho Power which, despite the exercise of due diligence, such Party is unable to prevent or overcome, including but not limited to an act of God, fire, flood, explosion, strike, sabotage, an act of the public enemy, civil or military authority, court orders, laws or regulations, insurrection or riot, an act of the elements or lack of precipitation resulting in reduced water flows for power production purposes. If either party is rendered wholly or in part unable to perform its obligations under this Agreement because of an event of force majeure, both parties shall be excused from whatever performance is affected by the event of force majeure, provided that:
(1) The non-performing Party shall, as soon as is reasonably possible after the occurrence of the event of force majeure, give the other Party written notice describing the particulars of the occurrence.
(2) The suspension of performance shall be of no greater scope and of no longer in duration than is required by the event of force majeure.
(3) No obligations of either Party which arose before the occurrence causing the suspension of performance and which could and should have been fully performed before such occurrence shall be excused as a result of such occurrence.

(emphasis added).

Cogeneration obtained a letter of credit from its financing partner, Calpine, Inc. (Cal-pine) and made the first installment of the security by June 1, 1992 as required by the Agreement.

As part of the process for building a hydroelectric power facility on the Snake River, Cogeneration was required to obtain permits from various federal and state agencies. A “401 Certificate” from the Idaho Department of Environmental Quality (DEQ) was required to ensure that all relevant environmental considerations had been met. In addition, a “404 Certificate” from the Army Corps of Engineers (Corps) was required before any construction could be undertaken in the streambed of the Snake River. A 401 certificate is a prerequisite to the issuance of a 404 certificate by the Corps.

In the early 1980’s, Cogeneration had obtained a 401 certificate from the DEQ and received a reconfirmation of the certificate in January, 1992. However, in February, 1992, the DEQ revoked the existing 401 certificate and established an extensive set of new criteria for Cogeneration to meet in order to obtain a new one. Cogeneration did not appeal the revocation or otherwise challenge the DEQ’s action. Instead, Cogeneration entered into negotiations with the DEQ regarding requirements for the issuance of a new certificate. In October, 1992, Cogeneration and the DEQ negotiated a consent order and issuance of a new 401 certificate, subject to, a list of conditions to be met by Cogeneration.

Cogeneration was unable to meet the conditions of the new 401 certificate to the satisfaction of the DEQ and in December, 1993, the DEQ notified the Corps that the newly issued 401 certificate was being revoked due to non-conformance with conditions imposed by the consent order. This notification urged the Corps to suspend further consideration of Cogeneration’s pending 404 certificate.

Cogeneration did not make the second security payment to Idaho Power on January 1, 1994. On January 3, Idaho Power issued notice to Cogeneration that it was in default of the Agreement, giving Cogeneration sixty days to cure. Cogeneration responded by invoking the Agreement’s force majeure provision asserting that the DEQ unilaterally and arbitrarily revoked the project’s 401 certificate, which in turn prevented Cogeneration from securing the financing necessary to post the security. On January 7, 1994, a meeting was held among Idaho Power, Co-generation and Calpine. Cogeneration and Calpine indicated that the security would be *742 paid if Idaho Power acknowledged that the certification problems constituted events of force majeure. Idaho Power replied that the security would have to be paid first, and then it would evaluate the issue of force majeure. Calpine was not willing to advance funds toward the venture on Cogeneration’s behalf without assurance that Idaho Power would acknowledge the certification problems to be an event of force majeure. Cogeneration itself, did not have the financial resources to satisfy the security. No payment of the security was made.

B. Procedural Background

In December 1994, Idaho Power petitioned the Idaho Public Utilities Commission (IPUC) and sued Cogeneration in district court seeking a declaration in each case that Cogeneration had defaulted on the Agreement because of delinquency in posting the security.

Idaho Power first pursued proceedings before the IPUC where Cogeneration requested a declaration that an event of force majeure had occurred. The IPUC ordered Cogeneration to post the second installment of the security by May 1, 1995. Both parties sought reconsideration. The IPUC declined to reconsider its earlier order, and declined to exercise jurisdiction to interpret and declare the parties’ contractual obligations. Instead, it suggested that a state district court would be a more appropriate forum for the issues. Neither party appealed either IPUC order. Cogeneration did not deposit the second security installment.

The parties proceeded with suit in district court. Idaho Power asserted that Cogeneration’s failure to comply with the IPUC’s order put Cogeneration in default of the Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Somes v. Starnes
Idaho Court of Appeals, 2025
Radford v. Van Orden
Idaho Supreme Court, 2025
IDHW v. Jane Doe
Idaho Court of Appeals, 2023
Dorr v. IDOL
Idaho Supreme Court, 2022
State v. Smith
516 P.3d 1071 (Idaho Supreme Court, 2022)
Allen v. Campbell
492 P.3d 1084 (Idaho Supreme Court, 2021)
Gordon v. U.S. Bank
Idaho Supreme Court, 2019
State v. Sims (Supreme Court)
Supreme Court of Kansas, 2019
Brand Makers v. Archibald
Idaho Court of Appeals, 2018
Taylor v. Taylor
Idaho Supreme Court, 2018
Burns Concrete, Inc. v. Teton County
384 P.3d 364 (Idaho Supreme Court, 2016)
Rice v. Sallaz
357 P.3d 1256 (Idaho Supreme Court, 2015)
Deutsche Bank v. Breinholt
Idaho Court of Appeals, 2014
Melaleuca, Inc. v. Foeller
318 P.3d 910 (Idaho Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
9 P.3d 1204, 134 Idaho 738, 2000 Ida. LEXIS 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/idaho-power-co-v-cogeneration-inc-idaho-2000.