Miller Const. v. STRESSTEK, DIV, LR YEGGE

697 P.2d 1201, 108 Idaho 187, 1985 Ida. App. LEXIS 586
CourtIdaho Court of Appeals
DecidedMarch 22, 1985
Docket14541
StatusPublished
Cited by7 cases

This text of 697 P.2d 1201 (Miller Const. v. STRESSTEK, DIV, LR YEGGE) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller Const. v. STRESSTEK, DIV, LR YEGGE, 697 P.2d 1201, 108 Idaho 187, 1985 Ida. App. LEXIS 586 (Idaho Ct. App. 1985).

Opinion

SWANSTROM, Judge.

Miller Construction Company brought suit for breach of contract against Stresstek. Miller sought to recover the difference between the amount it paid a subcon *188 tractor for work done on a highway overpass and the amount bid for the same work by Stresstek. Miller alleged that the parties had an oral contract for the work, while Stresstek maintained that it was not bound because it had not signed a written contract. The district court held that a written contract, although contemplated by the parties, was a mere formality and that Stresstek was bound by an oral contract to do the work. Stresstek appealed. We affirm and award Miller attorney fees on appeal.

Stresstek raises three issues: (1) whether the district court erred in finding that a written contract was only a formality and that a contract, came into existence by oral agreement; (2) whether the court erred by considering parol evidence to determine whether Miller had accepted Stresstek's bid; and (3) whether the court erred in refusing to grant Stresstek an involuntary dismissal at the close of Miller’s case.

In 1973, Miller submitted a bid to the general contractor covering the construction of a portion of U.S. Highway 80 near Bliss, Idaho. Before making its bid, Miller had solicited bids for “post-tensioning” concrete girders for a highway overpass it was to construct. It is disputed who contacted whom first — Miller claims Stresstek telephoned to submit a bid; Stresstek claims it was telephoned by Miller and was requested to submit a bid. In any event, Stresstek was the low bidder and Miller used its figure in making a bid to the general contractor. Miller was awarded the subcontract in January 1974 and contends it immediately informed Stresstek that Stresstek was to do the post-tensioning work. Stresstek denies being informed its bid was accepted, but acknowledges that various conversations between the two companies occurred over the next few months.

It is undisputed both parties contemplated that a written agreement would be executed. In fact, such an agreement was required by the state. The parties differ, however, as to the legal effect of the proposed written agreement — Miller argues it was only a formality, while Stresstek insists it was a condition precedent to the formation of the contract. In June 1974, a written sub-subcontract was sent to Stresstek for signatures. Stresstek refused to sign, stating several reasons: (l) the steel for the project would not be available until mid-1975; (2) the bid was effective for only thirty days after its submission and the written contract was submitted far too late; and (3) the price of steel had risen one hundred percent since the time the bid was submitted. A fourth reason, that the written contract did not include seven “conditions” imposed by Stresstek, as part of its bid, apparently was not raised until after the action had been brought. 1 As a result of Stresstek’s failure to sign the contract, Miller was forced to hire another company, at a substantially higher cost, to do the work.

I

The first issue we will discuss is whether a contract arose without the necessity of a writing.

In order for a contract to exist, a distinct understanding common to both parties is necessary____ Whether a contract exists when contracting parties agree to reduce their agreement to writing, is a question of the parties’ intent---Where it is clear that one party has agreed that an oral agreement must be reduced to writing before it shall be binding, there is no contract until a formal document is executed____

Mitchell v. Siqueiros, 99 Idaho 396, 400, 582 P.2d 1074, 1078 (1978) (citations omitted). Stresstek contends that it did not intend to be bound prior to reduction of the agreement to writing. The district court, however, found that Stresstek’s bid was *189 accepted by Miller on January 22 or 23, 1974, and that Miller had agreed to the seven conditions Stresstek placed on its bid. The court further found that the parties had not intended, when the oral agreement was reached, to be bound only if the agreement were reduced to writing. The written contract was a formality, necessary to comply with state regulations, but unnecessary to the parties’ intent to be bound by their offer and acceptance. The district court’s findings will not be set aside unless they are clearly erroneous. I.R.C.P. 52(a).

In determining the parties’ intent several factors have been suggested as helpful. They are:

whether the contract is one usually put in writing; whether there are few or many details; whether the amount involved is large or small; whether it requires a formal writing for a full expression of the covenants and promises; and whether the negotiations themselves indicate that a written draft is contemplated as the final conclusion of the negotiations. It is said, moreover, that the burden of proof is on the party claiming that the contract was completed before the written draft was signed. However, if the parties act under the preliminary agreement or receive benefits thereunder, they will be held to be bound notwithstanding the fact that a formal contract has never been executed.

Elliott v. Pope, 42 Idaho 505, 511, 247 P. 796, 797 (1926) (quoting 6 RULING CASE LAW 618). See also RESTATEMENT (SECOND) OF CONTRACTS § 27 comment c (1981) (hereinafter referred to as Restatement). Naturally, the task of weighing these factors and thus determining intent is in the first instance the responsibility of the trier of fact. After analyzing the evidence in light of Elliott, we hold that the district court’s findings were not clearly erroneous.

Employing the Elliott criteria, we note, first that a subcontractor’s contract, such as the one here, is usually one put in writing. This is borne out, at least in this case, by the fact that the written contract sent to Stresstek was a form contract which, according to Dickerson, Miller’s construction superintendent, was “sent [to] all of our subcontractors to sign.” Second, we also recognize that a subcontractor’s contract is often very detailed. Dickerson testified, however, that a large number of these details are standard provisions common to all such contracts. A written document which consists only of these standard provisions is more likely, in our view, to be a mere formality than a necessity. No writing would be required to inform the parties of their rights and responsibilities, and to assure them there was a meeting of the minds because there could be no dispute regarding these standard provisions. More important to a determination of intent are those additional provisions peculiar to the specific contract in question. A contract containing a large number of nonstandard provisions might require a writing for the protection of all parties concerned. In this case, the dispute centers around the seven conditions imposed by Stresstek. Stresstek maintains that the omission of these conditions from the written document signified that the parties had failed to reach agreement on these conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barry v. Pacific West Construction, Inc.
103 P.3d 440 (Idaho Supreme Court, 2004)
Idaho Power Co. v. Cogeneration, Inc.
9 P.3d 1204 (Idaho Supreme Court, 2000)
Rowley v. Fuhrman
982 P.2d 940 (Idaho Supreme Court, 1999)
Durrant v. Quality First Marketing, Inc.
903 P.2d 147 (Idaho Court of Appeals, 1995)
Hibbler v. Fisher
712 P.2d 708 (Idaho Court of Appeals, 1985)
Price v. Aztec Limited, Inc.
701 P.2d 294 (Idaho Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
697 P.2d 1201, 108 Idaho 187, 1985 Ida. App. LEXIS 586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-const-v-stresstek-div-lr-yegge-idahoctapp-1985.