Mitchell v. Siqueiros

582 P.2d 1074, 99 Idaho 396, 1978 Ida. LEXIS 431
CourtIdaho Supreme Court
DecidedJuly 5, 1978
Docket12407
StatusPublished
Cited by76 cases

This text of 582 P.2d 1074 (Mitchell v. Siqueiros) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitchell v. Siqueiros, 582 P.2d 1074, 99 Idaho 396, 1978 Ida. LEXIS 431 (Idaho 1978).

Opinions

McFADDEN, Justice.

This appeal is a sequel to Neilsen & Co. v. Cassia & Twin Falls County oint Class A School District 151, 96 Idaho 763, 536 P.2d 1113 (1975) (hereinafter Neilsen), involving a public works contract for the construction of the Burley Junior High School. The controversy concerns a specialty subcontract bid to perform a portion of the general contract construction project. The district court granted summary judgment for the specialty subcontractor, defendant-respondent John Siqueiros, doing business as J & R Plumbing and Heating Company. The general contractor, plaintiff-appellant Leslie L. Mitchell, doing business as Mitchell Construction Company, appeals and argues that: (1) determining whether a subcontract existed is a question of fact precluding summary judgment; (2) summary judgment was improper because appellant alleged a claim based on fraudulent misrepresentation; and (3) the district court erred in granting summary judgment because appellant’s complaint supports a claim based on promissory estoppel. It is the conclusion of the court that no genuine issue of material fact exists concerning appellant’s subcontract cláim; however, unresolved issues of fact concerning appellant’s fraudulent misrepresentation claim preclude summary judgment. The judgment of the district court is therefore affirmed in part and reversed in part. Because of the court’s disposition of the case, appellant’s third contention is not addressed.

On February 14,1974, respondent filed an application for a Class AAA public works contractor’s license with the Idaho Public Works Contractors State License Board. Respondent then held a Class AA license authorizing public works contracts not in excess of $250,000.00; a Class AAA license would authorize performing public works contracts in excess of $250,000.00. At the March 3, 1974, meeting of the state licensing board respondent’s Class AAA license application was approved but issuance de[398]*398ferred because of the board’s thirty day filing requirement.1

On March 28, 1974, respondent submitted a subcontract bid through the Idaho Subcontractors Bid Service to appellant. The $465,331.00 subcontract bid was for the plumbing and mechanical portion of the Burley Junior High School construction project. This bid noted that respondent then held a public works contractor’s license number 4071-AA. The numerals 4071 indicate the work type or specialty respondent could perform (specialty — plumbing and mechanical); the letters A A signify the volume in dollar amounts that respondent was licensed to perform (costs not exceeding $250,000.00). Respondent’s bid also noted “Our firm has been cleared by state office for AAA license.”

At the April 3, 1974, bid opening appellant submitted the lowest prime bid for the construction project. Appellant named respondent as the plumbing and mechanical subcontractor in the contract bid,2 and appellant was awarded the construction contract for the project. Appellant then tendered to respondent a written contract for the plumbing and mechanical portions of the construction project, conditioned upon respondent obtaining a Class AAA license. However, at the April 8, 1974, meeting of the state licensing board respondent’s application for a Class AAA license was again deferred because respondent had submitted to appellant a subcontract bid in excess of $250,000 without first obtaining a Class AAA license. Because of this deferral, appellant did not accept respondent’s subcontract offer and appellant executed a written contract for the plumbing and mechanical subcontract with another subcontractor who performed the work at an increased cost.

Appellant’s complaint sought to recover these added costs based on breach of contract and tortious misrepresentation. On August 4, 1976, respondent’s motion for summary judgment was granted. This appeal is from that judgment.

We note initially that in ruling on an appeal from summary judgment this court will only determine: “1. Whether there is a genuine issue as to any material fact; and 2. Whether the moving party is entitled to judgment as a matter of law.” Stewart v. Hood Corporation, 95 Idaho 198, 200, 506 P.2d 95, 97 (1973). This determination is to be based on the “pleadings, depositions, and admissions on file, together with the affidavits, if any . . . .” I.R.C.P. 56(c). However, courts should liberally construe the facts in favor of the party opposing the motion, together with all reasonable inferences from the evidence. Farmer’s Insurance Company of Idaho v. Brown, 97 Idaho 380, 544 P.2d 1150 (1976).

I

Appellant maintains that when a subcontractor is named, pursuant to I.C. § 67-[399]*3992310, to perform the mechanical subcontract portion of a public works project, a contract exists if the general contractor is awarded the prime contract. Appellant argues that the subcontract bid is an offer, which is conditionally accepted by naming the subcontractor, upon the express condition that the general contractor be awarded the prime contract by the awarding authority. We find nothing in common law contract principles, in I.C. § 67-2310 or in Neilsen, supra, to support this position.

It is a settled common law contract principle that utilizing a subcontractor’s bid in submitting the prime or general contract bid does not, without more, constitute an acceptance of the subcontractor’s offer conditioned upon being awarded the general contract by the awarding authority. C. H. Leavell and Co. v. Grafe and Associates, Inc., 90 Idaho 502, 414 P.2d 873 (1966). Accord, Universal Const. Co. v. Arizona Consolidated Masonry & Plastering Contractors Ass’n, 93 Ariz. 4, 377 P.2d 1017 (1963); Corbin-Dykes Electric Co. v. Burr, 18 Ariz.App. 101, 500 P.2d 632 (1972); Southern Cal. Acoustics Co., Inc. v. C. V. Holder, Inc., 71 Cal.2d 719, 79 Cal.Rptr. 319, 456 P.2d 975 (1969); Klose v. Sequoia Union High School Dist., 118 Cal.App.2d 636, 258 P.2d 515 (1953); K. L. House Constr. Co., Inc. v. Watson, 84 N.M. 783, 508 P.2d 592 (1973); R. J. Daum Constr. Co. v. Child, 122 Utah 194, 247 P.2d 817 (1952); Plumbing Shop, Inc. v. Pitts, 67 Wash.2d 514, 408 P.2d 382 (1965); Milone and Tucci, Inc. v. Bona Fide Builders, 49 Wash.2d 363, 301 P.2d 759 (1956). Unless the facts otherwise disclose, utilizing respondent’s bid was not by itself an acceptance of the subcontract bid offer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wandering Trails, LLC v. Big Bite Excavation, Inc.
329 P.3d 368 (Idaho Supreme Court, 2014)
Syringa Networks, LLC v. Idaho Department of Administration
305 P.3d 499 (Idaho Supreme Court, 2013)
Sines v. Blaser
592 P.2d 1367 (Idaho Supreme Court, 2012)
West Construction, Inc. v. Florida Blacktop, Inc.
88 So. 3d 301 (District Court of Appeal of Florida, 2012)
Gray v. Tri-Way Construction Services, Inc.
210 P.3d 63 (Idaho Supreme Court, 2009)
McColm-Traska v. Valley View, Inc.
65 P.3d 519 (Idaho Supreme Court, 2003)
Staff of the Idaho Real Estate Commission v. Nordling
22 P.3d 105 (Idaho Supreme Court, 2001)
Martin v. Spalding
988 P.2d 695 (Idaho Court of Appeals, 1998)
Lopez v. State
919 P.2d 355 (Idaho Court of Appeals, 1996)
Brooks v. Logan
903 P.2d 73 (Idaho Supreme Court, 1995)
Jones v. State
870 P.2d 1 (Idaho Court of Appeals, 1994)
Hoffman v. State
868 P.2d 516 (Idaho Court of Appeals, 1994)
Hawkeye-Security Insurance v. Gilbert
866 P.2d 976 (Idaho Court of Appeals, 1994)
Suitts v. First SEC. Bank of Idaho, NA
867 P.2d 260 (Idaho Court of Appeals, 1993)
Lawrence v. Jones
864 P.2d 194 (Idaho Court of Appeals, 1993)
Williams Bros. Construction, Inc. v. Public Building Commission
612 N.E.2d 890 (Appellate Court of Illinois, 1993)
Thompson v. Pike
838 P.2d 293 (Idaho Supreme Court, 1992)
Kelley Bean Co. v. Victor
834 P.2d 912 (Idaho Court of Appeals, 1992)
Nellsch v. State
835 P.2d 661 (Idaho Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
582 P.2d 1074, 99 Idaho 396, 1978 Ida. LEXIS 431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchell-v-siqueiros-idaho-1978.