Milone & Tucci, Inc. v. Bona Fide Builders, Inc.

301 P.2d 759, 49 Wash. 2d 363, 1956 Wash. LEXIS 280
CourtWashington Supreme Court
DecidedSeptember 27, 1956
Docket33512
StatusPublished
Cited by50 cases

This text of 301 P.2d 759 (Milone & Tucci, Inc. v. Bona Fide Builders, Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milone & Tucci, Inc. v. Bona Fide Builders, Inc., 301 P.2d 759, 49 Wash. 2d 363, 1956 Wash. LEXIS 280 (Wash. 1956).

Opinion

Weaver, J.

The sole question in this action for breach of an alleged contract is whether a contract exists between the parties.

Plaintiff and defendant are corporations engaged in the contracting business. Plaintiff specializes in the construction and installation of underground utilities; defendant specializes in the construction of commercial and industrial buildings.

The United States government advertised for bids for the cconstruction of four buildings. Under the specifications, the labor to be performed and the materials to be furnished were separated into thirty-eight separate items. Items numbered 15 through 37 of the specifications were designated “utilities” and, for the most part, covered water and sewer installations. The government required that bidders on the prime contract bid upon every item listed in the plans and specifications.

General and subcontractors interested in bidding for the job secured the plans and specifications. Several days prior to bid opening time, plaintiff telephoned a number of general contractors, including defendant, to inquire whether they desired to be furnished with plaintiff’s bid on the subcontract covering items 15 through 37. Plaintiff prepared its bid of $20,774.85 on these items and furnished it to a number of the general contractors, including defendant. At the time of furnishing the bid, plaintiff did not expect to be reimbursed for the actual costs ($210) of preparing the bid, *365 which it furnished to a number of prime contractors, except as it might be compensated by receiving a subcontract to perform the work.

In compiling its bid on the prime contract, defendant used the figures contained in plaintiff’s bid on items 15 through 37. A witness for defendant testified that plaintiff’s figures had been used, with the mistaken belief that plaintiff’s bid was the lowest one submitted to it up to bid-opening time. It appears, from an abstract of the bids submitted to the government, that the bids of six prime contractors on items 15 through 37 were lower than defendant’s bid (based on plaintiff’s figures) on these items. Hence, it would appear, since defendant was awarded the prime contract with a low bid of $224,929.54, that defendant’s bid on items other than items 15 through 37 was the controlling factor.

Defendant awarded the entire “mechanical” subcontract to Ray N. Erickson, Inc., for $63,803.12. This subcontract included other contract items, in addition to items 15 through 37, except it did not include items 33 and 34. It refused to award the subcontract for contract items 15 through 37 to plaintiff.

It is plaintiff’s (respondent’s) contention, as stated in its brief,

“. . . that appellant [defendant], by using the bid figures from respondent [plaintiff] on a portion of the work required to be performed, was obligated to award the subcontract to respondent at its bid figure, rather than to another bidder whose bid may have been lower ...” (Italics ours.)

The trial court entered judgment for plaintiff in the sum of $4,154.97, the amount the court found to be the “reasonable profit” plaintiff would have made had the subcontract been awarded to it.

The trial court advanced two theories in support of its judgment. First, that the decision of this court in Western Asphalt Co. v. Valle, 25 Wn. (2d) 428, 171 P. (2d) 159 (1946)', is authority for the proposition that the use of estimates furnished by a subcontractor to a prime contractor* *366 who thereafter receives the general contract for the entire job, gives rise to an implied contract between the prime contractor and the subcontractor.

The trial court’s second theory is found in finding of fact No. XI.

“The Court finds that there is, and at all of the times referred to herein there existed a general custom in the said industry for such, general contractors, prior, to bid opening time, to solicit bids, or to accept unsolicited bids, from contractors in such specialized fields for the performance of such specialized work, and which bids were furnished to the general contractors, not only as a valuable aid to such contractors in preparing their bids, but as an offer to perform the work, specified in such subbid, for the price bid therein, and if the figures presented in it were accepted by it and used by the general contractor, in compiling-his or its bid, and such general contractor is awarded the contract by the Government, that, by the acceptance and use of the figures compiled by said subcontract bidder on the various items included therein, there was created and there arose an implied contract to enter into a subcontract with such bidder whose bid the general contractor so accepted and used for such purpose, irrespective of whether or not such bid was the lowest bid submitted to such general contractor, prior to the opening of the bids by the Government.” (Italics ours.) - ■ .

In Western Asphalt Co., supra, the quotation of the subcontractor was secured by the prime contractor under circumstances materially different from those of the case before us. There was evidence, if believed, from which the jury could conclude, that there was a contract between the parties. This court affirmed an order granting a. new trial, saying: “The evidence on this phase of the case presents a question to be’determined by the trier of the facts.”

A careful reading of the opinion does not disclose that this court held that the use of a bid furnished by a subcontractor to a prime contractor gives rise to an implied contract between the prime contractor and the subcontractor, if the prime contractor is awarded the general contract.

Usage and custom are admissible in evidence to explain the terms of an express or implied contract once the *367 contract is established. The fallacy of the trial court’s second theory is that an implied contract cannot arise from proof of usage and custom. The effect of custom or usage upon contractual obligations is dependent upon the existence of an actual contract between the parties. Where there is no contract, proof of usage and custom will not make one. Pearce v. Dulien Steel Products, 14 Wn. (2d) 132, 135, 127 P. (2d) 271 (1942), and cases cited.

Thus, as we analyze the records, we are back to the question suggested in the opening sentence of this opinion: Does a contract exist between the parties?

The claimed agreement, upon which plaintiff bases its right to recover, is not an express contract. As this court pointed out in Chandler v. Washington Toll Bridge Authority, 17 Wn. (2d) 591, 600, 137 P. (2d) 97 (1943), the law recognizes two classes of implied contracts: those implied in fact, and those implied in law. The contracts falling within the- latter classification are generally termed quasi contracts and arise from an implied

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Converse v. Vizio, Inc.
W.D. Washington, 2020
Schultz v. United Airlines, Inc.
797 F. Supp. 2d 1103 (W.D. Washington, 2011)
Krottner v. Starbucks Corp.
628 F.3d 1139 (Ninth Circuit, 2010)
Hoving v. Lawyers Title Insurance
256 F.R.D. 555 (E.D. Michigan, 2009)
Davenport v. Washington Education Ass'n
147 Wash. App. 704 (Court of Appeals of Washington, 2008)
Davenport v. Washington Educ. Ass'n
197 P.3d 686 (Court of Appeals of Washington, 2008)
McClung v. City of Sumner
548 F.3d 1219 (Ninth Circuit, 2008)
Bybee Farms, LLC v. Snake River Sugar Co.
563 F. Supp. 2d 1184 (E.D. Washington, 2008)
Dragt v. Dragt/DeTray, LLC
139 Wash. App. 560 (Court of Appeals of Washington, 2007)
Lake Limerick Country Club v. Hunt Mfg. Homes, Inc.
84 P.3d 295 (Court of Appeals of Washington, 2004)
Lake Limerick Country Club v. Hunt Manufactured Homes, Inc.
120 Wash. App. 246 (Court of Appeals of Washington, 2004)
Electro-Lab of Aiken, Inc. v. Sharp Construction Co. of Sumter, Inc.
593 S.E.2d 170 (Court of Appeals of South Carolina, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
301 P.2d 759, 49 Wash. 2d 363, 1956 Wash. LEXIS 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milone-tucci-inc-v-bona-fide-builders-inc-wash-1956.