Western Asphalt Co. v. Valle

171 P.2d 159, 25 Wash. 2d 428, 1946 Wash. LEXIS 407
CourtWashington Supreme Court
DecidedJuly 18, 1946
DocketNo. 29789.
StatusPublished
Cited by13 cases

This text of 171 P.2d 159 (Western Asphalt Co. v. Valle) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Asphalt Co. v. Valle, 171 P.2d 159, 25 Wash. 2d 428, 1946 Wash. LEXIS 407 (Wash. 1946).

Opinion

Beals, C. J.

Western Asphalt Company, a Washington corporation, instituted this action against Henrik Valle and his wife, Ellen Stray Valle, alleging in its complaint its corporate existence, and that the defendants were husband and wife engaged in a general construction business under the name of Henrik Valle Company; that, during the month of July, 1944, the defendants were preparing to submit a bid for a general construction job involving the building of a naval advance base depot at Tacoma, Washington, in accordance with general plans and specifications, which included asphalt pavement and soil stabilization; that, at the request of defendants, plaintiff furnished them with its engineering services in computing costs relating to the asphalt pavement and soil stabilization portions of the general contract; that plaintiff’s services, computations, and costs were, by plaintiff, furnished to defendants and were used by them in submitting their bid; that the computations and estimates furnished defendants by plaintiff aggregated $294,539.51, and that, aided by the facilities and computations furnished by plaintiff, defendants bid upon the contract and were the low bidder for the general contract for the entire construction, including the asphalt pavement and the soil stabilization; that defendants were awarded the general contract for approximately $1,996,000; that the reasonable value of the services performed by plaintiff for defendants was the sum of $43,000, for which amount plaintiff prayed for judgment.

Defendants admitted that they were husband and wife and engaged in business as alleged by plaintiff, and denied each and every other allegation contained in plaintiff’s complaint, praying that the action be dismissed.

*430 The cause was tried to a jury, which returned a verdict in favor of the defendants, whereupon plaintiff moved for judgment in its favor notwithstanding the verdict or, in the alternative, for a new trial, basing its motion for a new trial upon six of the statutory grounds.

The trial court denied plaintiff’s motion for judgment in its favor notwithstanding the verdict, but granted plaintiff’s motion for a new trial upon two grounds mentioned in the order as follows:

“1. Error of the Court in giving instruction No. 11 which was excepted to at the time by the plaintiff. 2. That the verdict is contrary to the evidence adduced at the trial and substantial justice has not been done.”

From this order, the defendants have appealed to this court. We shall refer to appellant Henrik Valle as though he were the sole appellant. •

Appellant assigns error upon the refusal of the trial court to grant his motion to dismiss the action, which motion was interposed at the close of respondent’s case and renewed at the close of all the evidence;, upon the order of the court granting respondent’s motion for a new trial, and upon the refusal of the trial court to enter judgment in appellant’s favor upon the verdict of the jury.

As appellant did not stand upon his motion to dismiss interposed at the close of respondent’s case, but proceeded to introduce evidence on his own behalf, appellant’s motion for judgment in his favor as matter of law made at the close of all the evidence is the only motion which may be considered on appeal.

The somewhat complicated facts may be stated as follows:

Respondent is engaged in the business of laying asphalt paving and similar work. While respondent occasionally directly contracted for the laying of asphalt, it more frequently entered into subcontracts with general construction contractors.

When respondent’s officers learned that a contract in which it might be interested was about to be let, preparations would be made for bidding upon any desirable sub *431 contract, and plans and specifications would be obtained to enable respondent to prepare necessary estimates. Information concerning these estimates would often be made available to any reputable general contractor who asked for them, the estimates being made so available to the general contractors because of respondent’s desire to obtain from the successful bidder a subcontract for the installation of so much of the work as fell within the scope of respondent’s activities. It does not appear that respondent ever made a charge for this service of furnishing estimates of prices, but apparently respondent had always received the subcontracts for the installation of asphalt paving when the general contractor to whom it had furnished data had been awarded the contract for the entire job.

About July 20, 1944, respondent learned that the United States government would open bids for the construction of the naval base advance depot at eleven a. m., July 28th, following. The construction included a substantial amount of asphaltic pavement, and July 22nd respondent’s officers procured the plans and specifications from a general contractor who was expecting to file a bid. The specifications were introduced in evidence, and comprised thirty-two sections. Section 9, shown on six pages, provided for soil stabilization, and section 10, of three pages, covered the laying of asphaltic concrete. It was these two sections which interested respondent, whose plant was just across the street from the land upon which the naval base was to be built.

This was the largest contract with which respondent had ever been concerned, and its officers were anxious to obtain a subcontract for that portion of the work in which respondent was engaged. At the request of an officer of respondent, two competent persons computed the yardage required for the soil stabilization and for the asphaltic concrete. For this, respondent paid seventy-five dollars. Three of respondent’s officers independently estimated the amount of asphaltic work to be done and the total price at which respondent would do the work. July 27th, the day before *432 the bids were to be opened, the three agreed upon a common figure as respondent’s estimate. This estimate was typed upon respondent’s letterhead, and without the name of any addressee reads as follows:

“Gentlemen:
“We are pleased to quote the following prices for furnishing all labor, equipment, supplies and materials necessary for completing asphalt pavement and soil stabilization at the Naval Advance Base Depot, Tacoma, Washington, in accordance with Sections 9 and 10 of plans and specifications and addenda thereto. Basic Bid Section 9 — 17^ per square yard; Section 10 — 82<¿ per square yard.”

The estimate continued with certain statements concerning other portions of the contract, prices being included.

Page 1 includes the following:

“The foregoing quotations are unit prices. We based our figures upon the approximate areas shown on the attached sheet, but cannot guarantee those quantities. However, no change of unit price will be involved because of reasonable variation in quantities.”

Upon an attached sheet is found the following:

“For your information and checking, our estimator obtained the figures listed below before issuance of addendum covering G-l and G-2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paffhausen v. Balano
1998 ME 47 (Supreme Judicial Court of Maine, 1998)
Kintz v. Read
626 P.2d 52 (Court of Appeals of Washington, 1981)
Kilthau v. Covelli
563 P.2d 1305 (Court of Appeals of Washington, 1977)
Jacobs v. Brock
406 P.2d 17 (Washington Supreme Court, 1965)
Orin Osborn v. Boeing Airplane Company
309 F.2d 99 (Ninth Circuit, 1962)
Shurrum v. Watts
324 P.2d 380 (Idaho Supreme Court, 1958)
Milone & Tucci, Inc. v. Bona Fide Builders, Inc.
301 P.2d 759 (Washington Supreme Court, 1956)
Felton v. Finley
209 P.2d 899 (Idaho Supreme Court, 1949)
State v. Brent
191 P.2d 682 (Washington Supreme Court, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
171 P.2d 159, 25 Wash. 2d 428, 1946 Wash. LEXIS 407, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-asphalt-co-v-valle-wash-1946.