Electro-Lab of Aiken, Inc. v. Sharp Construction Co. of Sumter, Inc.

593 S.E.2d 170, 357 S.C. 363, 2004 S.C. App. LEXIS 17
CourtCourt of Appeals of South Carolina
DecidedFebruary 2, 2004
Docket3731
StatusPublished
Cited by32 cases

This text of 593 S.E.2d 170 (Electro-Lab of Aiken, Inc. v. Sharp Construction Co. of Sumter, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electro-Lab of Aiken, Inc. v. Sharp Construction Co. of Sumter, Inc., 593 S.E.2d 170, 357 S.C. 363, 2004 S.C. App. LEXIS 17 (S.C. Ct. App. 2004).

Opinion

HEARN, C.J.:

Electro-Lab of Aiken asserts that Sharp Construction Company breached the parties’ contract by replacing Electro-Lab with a different subcontractor. The parties became contractually bound, Electro-Lab argues, by virtue of Sharp’s use of Electro-Lab’s subcontracting bid in its general contracting bid and by certain acts following the use of the bid. The trial court disagreed, concluding that no contract existed between the parties. We affirm.

FACTS

On April 24, 1997, bidding closed for all general contractors on two projects to build schools in York County, South Car *366 olina. Before the bid deadline, Sharp Construction Co., a general contractor, received an oral bid by telephone from Electro-Lab pertaining to one of the school projects’ electrical work. Electro-Lab’s bid amount was $1,150,000. Sharp listed Electro-Lab in its overall general contractor’s bid submitted to the project’s owner. Sharp alleges this inclusion was actually a mistake because it had inadvertently overlooked a lower bid from another electrical subcontractor, Ind-Com Electric Company, Inc. for $1,140,000. However, this oversight was not discovered until after Sharp submitted its general contractor’s bid. At the time Sharp submitted its general contractor’s bid, the only information it had about Electro-Lab’s bid was the dollar amount.

Sharp, as the low bidder for the project, was awarded the general contract and was required to provide payment and performance bonds. When Electro-Lab contacted Sharp to inquire about the project, Sharp notified Electro-Lab that its bid was the lowest and that it was listed as the electrical subcontractor in Sharp’s successful bid. Sharp’s project manager testified that during this telephone conversation, he told Electro-Lab that he would like to know what its bond rate was and asked Electro-Lab to fax its bid in writing. Shortly thereafter, Sharp discovered that Electro-Lab’s subcontract bid was not the lowest bid received, and asked Electro-Lab if it could perform the work for $1,140,000. Electro-Lab agreed, and Sharp submitted the following confirmatory fax:

Dear Michael:
This letter is to confirm that we will be issuing a subcontract for the electrical work on the above referenced project for $1,140,000.00.
Please proceed immediately with having shop drawing completed and performance and payment bonds issued. A subcontract is forthcoming. We look forward to working with you.
Sincerely,
SHARP CONSTRUCTION CO. OF SUMTER, INC. HAL TURNER

Following receipt of this letter, Electro-Lab attended a pre-construction conference at Sharp’s request and began gather *367 ing submittals for the project from suppliers. Approximately six weeks after bidding closed on the project, Electro-Lab informed Sharp that it had been unable to obtain the required bonds. According to Sharp, during this telephone conversation Electro-Lab requested that its name be withdrawn from further consideration as the electrical subcontractor for the project. Electro-Lab disputes this, maintaining that it never requested to be withdrawn from consideration.

After Electro-Lab informed Sharp that it could not obtain the bonds, Sharp entered into a subcontract for the same dollar amount with Ind Com, which provided payment and performance bonds as required. By letter, Sharp confirmed that it would be switching to a different electrical subcontractor because of Electro-Lab’s inability to obtain bonding.

Electro-Lab did not protest the change until nine months later when it initiated the instant lawsuit, alleging that Sharp breached their contract by switching the subcontract for the project’s electrical work to Ind-Com. After a full trial on the merits, the trial judge ruled in favor of Sharp, determining that no contract existed between the parties and that Electro-Lab’s proof of damages was legally insufficient.

STANDARD OF REVIEW

An action for breach of contract is an action at law. Auto Owners Ins. Co. v. Langford, 330 S.C. 578, 581, 500 S.E.2d 496, 497 (Ct.App.1998) (citation omitted). In an action at law, on appeal of a case tried without a jury, the appellate court’s standard of review extends only to the correction of errors of law. Okatie River, L.L.C. v. Southeastern Site Prep, L.L.C., 353 S.C. 327, 334, 577 S.E.2d 468, 472 (Ct.App.2003) (citation omitted). The trial judge’s findings of fact will not be disturbed upon appeal unless found to be without evidence which reasonably supports the judge’s findings. King v. PYA/Monarch, Inc., 317 S.C. 385, 388, 453 S.E.2d 885, 888 (1995) (citation omitted).

ISSUES

1. Did the trial court err when it found no contract existed between the parties?

2. Did the trial court err when it found that Electro-Lab’s proof of damages was legally insufficient?

*368 LAW/ANALYSIS

Electro-Lab argues a contract existed between the parties by virtue of the use of Electro-Lab’s bid in Sharp’s successful general contracting bid, the parties’ subsequent communications, and Electro-Lab’s attendance at a pre-construction meeting and its gathering of submittals from suppliers. We disagree.

“A contract is an obligation which arises from actual agreement of the parties manifested by words, oral or written, or by conduct.” Regions Bank v. Schmauch, 354 S.C. 648, 660, 582 S.E.2d 432, 439 (Ct.App.2003) (citations omitted). The necessary elements of a contract are offer, acceptance, and valuable consideration. Carolina Amusement Co. v. Connecticut Nat’l Life Ins. Co., 313 S.C. 215, 220, 437 S.E.2d 122, 125 (Ct.App.1993). In this case, there was a valid oral offer to perform electrical subcontract work for $1,150,000 based on the telephone bid received by Sharp before Sharp furnished its general contractor’s bid to the project owner. See id. (quoting Restatement (Second) of Contracts § 24 (1981)) (“ ‘An offer is the manifestation of willingness to enter into a bargain, so made as to justify another person in understanding that his assent to that bargain is invited and will conclude it.’ ”). See also Klose v. Sequoia Union High Sch. Dist., 118 Cal.App.2d 636, 258 P.2d 515, 517 (1953) (“A subcontractor bidder merely makes an offer that is converted into a contract by a regularly communicated acceptance conveyed to him by the general contractor.”). As a result, the issue in this case turns on whether Sharp’s conduct following Electro-Lab’s bid amounted to acceptance of Electro-Lab’s offer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daniel E. Schall v. Lori M. Sealy
Court of Appeals of South Carolina, 2026
Casey Putman v. Jamie Marie McAdams
Court of Appeals of South Carolina, 2026
The State, Inc. v. Hampton County
Court of Appeals of South Carolina, 2025
Lisa Summer Rice v. Newberry Lions Club
Court of Appeals of South Carolina, 2025
Nicole Lampo v. Amedisys Holding, LLC
Supreme Court of South Carolina, 2025
Jimmy Helms v. Debbie Willing
Court of Appeals of South Carolina, 2024
Shem Creek v. Town of Mount Pleasant
Court of Appeals of South Carolina, 2024
Portrait Homes v. Pennsylvania National Mutual
Court of Appeals of South Carolina, 2023
J & W Corporation v. Broad Creek Marina
Court of Appeals of South Carolina, 2023
Tony T. Good v. Tomekia Means
Court of Appeals of South Carolina, 2023
Nicole Lampo v. Amedisys Holding, LLC
Court of Appeals of South Carolina, 2022
Wendy Reed v. County of Dorchester
Court of Appeals of South Carolina, 2022
Baker v. The Boeing Company Inc
D. South Carolina, 2021
Burton Fire District v. City of Beaufort
Court of Appeals of South Carolina, 2020
Mac Papers, Inc. v. Genesis Press, Inc.
826 S.E.2d 874 (Court of Appeals of South Carolina, 2019)
Riley v. Outlaw
Court of Appeals of South Carolina, 2019
Jenkins v. Refuge Temple Church of God in Christ, Inc.
818 S.E.2d 13 (Court of Appeals of South Carolina, 2018)
Dealer Services Corporation v. Total, Inc.
Court of Appeals of South Carolina, 2017
Spanish Wells v. Luckenbill
Court of Appeals of South Carolina, 2017

Cite This Page — Counsel Stack

Bluebook (online)
593 S.E.2d 170, 357 S.C. 363, 2004 S.C. App. LEXIS 17, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electro-lab-of-aiken-inc-v-sharp-construction-co-of-sumter-inc-scctapp-2004.