West Construction, Inc. v. Florida Blacktop, Inc.

88 So. 3d 301, 2012 WL 1414304, 2012 Fla. App. LEXIS 6485
CourtDistrict Court of Appeal of Florida
DecidedApril 25, 2012
DocketNo. 4D11-408
StatusPublished
Cited by10 cases

This text of 88 So. 3d 301 (West Construction, Inc. v. Florida Blacktop, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Construction, Inc. v. Florida Blacktop, Inc., 88 So. 3d 301, 2012 WL 1414304, 2012 Fla. App. LEXIS 6485 (Fla. Ct. App. 2012).

Opinion

GROSS, J.

In this case between a subcontractor and a general contractor, we reverse a final judgment for the subcontractor because the parties’ dealings did not give rise to an enforceable contract.

Florida Blacktop, Inc., an asphalt paving subcontractor, sued West Construction, Inc., a general contractor. The essence of Blacktop’s complaint was that, even though West used its bid to secure a project contract with the Village of Royal Palm Beach, West contracted with another to perform the work.

Florida Blacktop’s complaint asserted three causes of action: breach of oral contract, promissory estoppel, and unjust enrichment, which is also called a contract implied in law. See Commerce P’ship 8098 Ltd. P’ship v. Equity Contracting Co., [303]*303Inc., 695 So.2d 383, 386 (Fla. 4th DCA 1997). The case went to a jury trial. An issue of fact to be decided by the jury was whether there was a contract between the parties. In a blended jury instruction, the jury was told about an express oral contract, where an agreement is arrived at by words. See id. at 385. Also, without objection, the jury was instructed about a contract implied in fact, where an agreement “is not put into promissory words with sufficient clarity, so a fact finder must examine and interpret the parties’ conduct to give definition to their unspoken agreement.” See id. By answering an interrogatory verdict, the jury found that Blacktop and West “enter[ed] into an oral agreement” that West would use Blacktop “as its asphalt paving contractor if’ West “was awarded the Project” by Royal Palm Beach.1 The jury also found that West breached that “oral contract” and awarded damages. Thus, given the way the jury was instructed and the structure of the verdict form, the jury’s finding of an “oral contract” could have been based on an express oral contract, a contract implied in fact, or both.

On appeal, West argues that, when “reviewing the evidence in a light most favorable to [Blacktop], there [was] no competent evidence creating an oral agreement,” so that the trial court should have granted its motion for directed verdict. Because of the way the case was submitted to the jury, our inquiry must focus on whether either an enforceable oral contract or contract implied in fact was formed between the parties.

Evidence at Trial2

The Village of Royal Palm Beach initiated a public competitive bidding process, inviting contractors to submit bids in connection with the construction of a building. West decided to compete for the project and invited subcontractors to submit bids for parking lot and asphalt work. Blacktop submitted a “Proposal/Contract” offering to do the paving for a unit price of $14.10, but reserving the right to alter its price due to changes in material costs.

Page four of the proposal contained this preprinted, small print clause:

Florida Blacktop, Inc. has devoted time, money and resources toward the preparation of this bid and as consideration therefore itf’Js submitting this bid to “buyer" with the express understanding and agreement of the parties that in the event the “buyer" in any way uses Florida Blacktop, Inc.’s bid such as figures contained therein for purposes of shopping the bid with third parties and/or divulging information contained in the bid to third parties similarly competing with Florida Blacktop, Inc. for the work at issue and/or incorporating any portion of Florida Blacktop, Inc.’s bid in correspondence with third parties competing or in any way involved with the construction work on the project at issue such action(s) shall in all instances constitute acceptance of Florida Blacktop, Inc.’s bid and shall create a binding contract between the parties consistent with the bid documents.

(Emphasis added). Without explanation or elaboration, the president of Blacktop vaguely testified that this clause was the [304]*304“industry standard,” meaning he understood the clause to mean that, if West used Blacktop’s bid and got the job, “a contractual agreement” arose. Although Blacktop’s “Proposal/Contract” had places for signatures for both Blacktop and West, neither party signed the document. There was no evidence that West orally agreed to the pre-printed paragraph of the proposal quoted above. There was no evidence that West, either orally or in writing, accepted Blacktop’s proposal. The parties never entered into a written contract.

Thereafter, West submitted its bid to the Village and was notified that it was the lowest bidder. West then furnished the Village with a list of proposed subcontractors and suppliers, indicating that $165,259.93 was attributable to asphalt paving work, which would be performed by Blacktop. Even though Blacktop sent a letter to West thanking it for the work, West never discussed the project with Blacktop, taking the position that Blacktop had been listed as a subcontractor by accident. West hired a different company to do the paving work.

The trial court denied West’s motions for directed verdict and submitted the case to the jury on the blended contract theory described above.

Discussion

For there to be an enforceable contract, “there must be an offer, an acceptance, consideration, and sufficient specification of terms so that the obligations involved can be ascertained.” Savoca Masonry Co., v. Homes & Son Constr. Co., 112 Ariz. 392, 542 P.2d 817, 819 (1975). A subcontractor’s bid is “nothing more than an offer to perform the subcontract under specified terms.” Corbin-Dykes Elec. Co. v. Burr, 18 Ariz.App. 101, 500 P.2d 632, 633 (1972). The bid does not evolve into a contract until it is accepted by the general contractor; “no contract is formed when a bid is made pursuant to an invitation to bid.” Hoon v. Pate Constr. Co., 607 So.2d 423, 426 (Fla. 4th DCA 1992). Acceptance of an offer may be by the words used or by “other manifestations of intent having reference to the contract.” Corbin-Dykes, 500 P.2d at 634.

Here, there was no express oral or written acceptance of Blacktop’s bid. If there was an acceptance by West, it must be found in a contract implied in fact by evaluating the circumstances under an objective standard. See Holman Erection Co. v. Orville E. Madsen & Sons, Inc., 330 N.W.2d 693, 695 (Minn.1983). “It is a settled common law contract principle that utilizing a subcontractor’s bid in submitting the prime or general contract bid does not, without more, constitute an acceptance of the subcontractor’s offer conditioned upon being awarded the general contract by the awarding authority.” Id. at 696 (quoting Mitchell v. Siqueiros, 99 Idaho 396, 582 P.2d 1074, 1077 (1978)); see also Merritt-Chapman & Scott Corp. v. Gunderson Bros. Eng’g Corp., 305 F.2d 659, 662-63 (9th Cir.1962) (“At the outset, it is clear that in Washington [state] use of a bid by a prime contractor is not the legal equivalent of acceptance.” (citation omitted)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Eleftherio
S.D. Florida, 2025
Sanders v. Kerwin
M.D. Florida, 2024
P.D.K., INC. v. MADELINE MCCONNELL
District Court of Appeal of Florida, 2020
EDIOL TOPALLI v. EDDIE FELICIANO
267 So. 3d 513 (District Court of Appeal of Florida, 2019)
Jericho All-Weather Opportunity Fund, LP v. Pier Seventeen Marina & Yacht Club, LLC
207 So. 3d 938 (District Court of Appeal of Florida, 2016)
Land Company of Osceola County, LLC v. Genesis Concepts, Inc.
169 So. 3d 243 (District Court of Appeal of Florida, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
88 So. 3d 301, 2012 WL 1414304, 2012 Fla. App. LEXIS 6485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-construction-inc-v-florida-blacktop-inc-fladistctapp-2012.