Barry v. Pacific West Construction, Inc.

103 P.3d 440, 140 Idaho 827, 2004 Ida. LEXIS 201
CourtIdaho Supreme Court
DecidedDecember 1, 2004
Docket30105
StatusPublished
Cited by50 cases

This text of 103 P.3d 440 (Barry v. Pacific West Construction, Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barry v. Pacific West Construction, Inc., 103 P.3d 440, 140 Idaho 827, 2004 Ida. LEXIS 201 (Idaho 2004).

Opinion

SCHROEDER, Chief Justice.

William “Bill” Barry, d/b/a/ Quality Interiors (Quality), sued Pacific West Construction, Inc. (Pae-West) for payment for construction services rendered by Quality to Pac-West. Following trial the district court entered a *830 judgment in favor of Quality for $52,410.97, plus accrued interest, costs and attorney fees. Pac-West appeals.

I.

FACTUAL AND PROCEDURAL BACKGROUND

On December 3, 2001, the Intermountain Contractors publication advertised for bids for work on a number of projects, including a 15-bed mental health addition to the Bannock Regional Medical Center (“BRMC”). Some projects listed on the same page as the BRMC project were specifically identified as “Public Works License” jobs, meaning that bidders on those projects must hold a public works license issued pursuant to Idaho’s Public Works Contractors License Act (“PWCLA”). I.C. § 54-1901 et seq. The BRMC project was not identified as a “Public Works License” job on that page. However, the BRMC project was “public works construction” as defined by the PWCLA. In addition, the “Supplementary Instructions to Bidders” indicated that all bidders on all projects listed in the advertisement must “hold current licenses as public works contractors in the State of Idaho.”

Bill Barry, on behalf of Quality, submitted an identical bid to all general contractors listed in the advertisement on two specifications, Section 09260 and Section 09511. The total amount of the bid was $93,565.

Pac-West was hired as the general contractor for the project. Alex Jack, the BRMC Project Manager for Pac-West, contacted Quality and offered it the job. PacWest maintains that it believed an additional section, Section 09111, was part of Quality’s bid. Accordingly, Pac-West claims it was hiring Quality to perform the work for Sections 09260, 09511, and 09111.

Pac-West sent a Proposed Subcontract to Quality. The contract identified Sections 09260, 09511, and 09111 as the work to be performed by Quality. Barry left for vacation and his partner, Robert Figueroa, and a crew commenced work on February 1, 2001. When Barry returned, he signed the Proposed Subcontract but never delivered it to Pac-West. Barry contacted Jack and informed him that the subcontract contained a section that Quality did not bid. Barry offered to do the Section 09111 work for cost plus 10%, but Jack persisted in his belief that this section was included in Quality’s original bid price.

On March 8, Jack asked Barry if Quality had a public works license. Barry acknowledged that it did not. Jack stated that Quality would have to continue its work as PacWest employees. Barry agreed and advised his employees of the arrangement. Quality continued its work under the umbrella of Pac-West’s public works license.

Barry testified that the following week Jack had a conversation with him about making Quality’s lack of a public works license problem “go away” if Quality would perform the Section 09111 work as part of its original bid price. When Quality refused to do the work, Pac-West turned its men away from the job site. Pac-West claims it was only attempting to get Quality to perform the work that Pac-West believed was included in its bid price. At the time Quality was turned away it would have taken about two more weeks to complete the work on Sections 09260 and 09511.

Quality filed suit on June 7, 2002, claiming breach of contract and unjust enrichment. Quality also filed a claim against Jack individually for civil extortion. The civil extortion claim was dismissed on summary judgment. After the trial on the contract claims, the district court held that a contract had been formed between the parties for work on Sections 09260 and 09511, the job “[Quality] had bid.” The district court determined that Quality breached the contract because it did not have a public works license but found that Pac-West was estopped from asserting its breach of contract claim because it attempted to use Quality’s lack of a license as “leverage” to get Quality to perform the Section 09111 work at no additional cost. The district court held that Pac-West breached the contract by turning away Quality’s crew from the worksite.

Quality’s damages figure was arrived at by taking the total amount of the bid ($93,-565.00) and subtracting the estimated price *831 for the work remaining after Quality was turned away from the worksite ($28,088.00), and subtracting amounts for credits, additional work requested and interest. The district court awarded Quality the amount it requested, $52,410.97, plus interest, costs and attorney fees. With respect to the civil extortion claim against Jack, the district court determined that Alex Jack was the “prevailing party” on the civil extortion claim and entitled to his costs. However, Jack presented evidence of only one cost, $36.50 for mileage to Pocatello. The court held that it could not award Jack this cost because “[t]here is no reference to the date of the mileage claim or for whom it is claimed.” In regards to Jack’s attorney fees, the court held that because the claim against him was a tort there was no basis for awarding him fees.

This appeal followed. Pac-West maintains that the district court erred in concluding the parties formed a contract when there was no meeting of the minds as to the scope of the work and in finding that Pac-West awarded Quality the “work it had bid.” Pac-West also claims that the district court erred in allowing Quality to recover even though it found that Quality had breached the contract and erred in allowing Quality the benefit of the bargain, including lost profits, of an unenforceable contract. Further, Pac-West maintains that the district court erred in refusing to consider Pac-West’s damages and in awarding Quality attorney fees. In addition, Alex Jack appeals the district court’s denial of his costs and attorney fees incurred in defending the civil extortion claim.

II.

STANDARD OF REVIEW

The district court’s findings of fact are reviewed to determine whether the evidence supports the findings of fact, and whether the findings of fact support the conclusions of law. Electrical Wholesale Supply Co., Inc. v. Nielson, 136 Idaho 814, 820, 41 P.3d 242, 248 (2001). In a court-tried case, the findings of fact are liberally construed on appeal in favor of upholding the judgment entered. Id. If the findings of fact are based on substantial evidence, even where that evidence is conflicting, they will not be overturned on appeal. Id. This court exercises free review over the lower court’s conclusions of law. Mutual of Enumclaw v. Box, 127 Idaho 851, 852, 908 P.2d 153, 154 (1995).

III.

EVIDENCE SUPPORTS THE DISTRICT COURT’S FINDING THAT A CONTRACT WAS FORMED BETWEEN QUALITY AND PAC-WEST FOR QUALITY TO PERFORM THE WORK ON SECTIONS 09260 AND 09511

The district court determined that the parties entered into a preliminary agreement for Quality to perform the work on Sections 09260 and 09511. There are facts in the record that support this finding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

York v. Kemper Northwest, Inc.
Idaho Supreme Court, 2026
Stunja v. High Corral
Idaho Court of Appeals, 2026
Genho v. Riverdale Hot Springs, LLC
560 P.3d 1041 (Idaho Supreme Court, 2024)
Pickering v. Sanchez
544 P.3d 135 (Idaho Supreme Court, 2024)
Litster Frost v. Idaho Injury Law Group
518 P.3d 1 (Idaho Supreme Court, 2022)
Van Orden v. Van Orden
515 P.3d 233 (Idaho Supreme Court, 2022)
Asher v. McMillan
503 P.3d 172 (Idaho Supreme Court, 2021)
Hawes v. Western Pacific Timber LLC
477 P.3d 950 (Idaho Supreme Court, 2020)
Wadsworth Reese v. Siddoway & Co
Idaho Supreme Court, 2019

Cite This Page — Counsel Stack

Bluebook (online)
103 P.3d 440, 140 Idaho 827, 2004 Ida. LEXIS 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barry-v-pacific-west-construction-inc-idaho-2004.