Genho v. Riverdale Hot Springs, LLC

CourtIdaho Supreme Court
DecidedDecember 10, 2024
Docket50294
StatusPublished

This text of Genho v. Riverdale Hot Springs, LLC (Genho v. Riverdale Hot Springs, LLC) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Genho v. Riverdale Hot Springs, LLC, (Idaho 2024).

Opinion

IN THE SUPREME COURT OF THE STATE OF IDAHO Docket No. 50294

DANIEL PHILLIP GENHO, an ) individual, d/b/a GENHO ) CONSTRUCTION, ) ) Plaintiff-Respondent, ) ) v. ) ) RIVERDALE HOT SPRINGS, LLC, an ) Idaho Limited Liability Company, d/b/a ) Boise, August 2024 Term RIVERDALE RESORT; RIVERDALE ) RESORT AND SPA, LLC, an Idaho ) Filed: December 10, 2024 Limited Liability Company, d/b/a ) RIVERDALE RESORT, ) Melanie Gagnepain, Clerk ) Defendants-Appellants, ) ) TIPPETTS, INC., an Idaho Corporation ) and NORTHERN TITLE COMPANY, ) INC., a Utah Corporation, ) ) Defendants. ) ____________________________________)

Appeal from the District Court of the Sixth Judicial District of the State of Idaho, Franklin County. Mitchell W. Brown, District Judge.

The decision of the district court is affirmed in part and reversed in part, with the judgment for attorney fees vacated and remanded.

Silvey Law Office LTD, Boise, attorneys for Appellants. Greg Silvey argued.

May, Rammell & Wells, Pocatello, attorneys for Respondent. Peter M. Wells argued. _________________________________

BEVAN, Chief Justice. This appeal asks the Court to determine whether the Idaho Contractor Registration Act (ICRA or “the Act”) permits equitable remedies for contractors who become registered under the Act midway through a construction project. See I.C. §§ 54-5201 to -5219. The case arises from a

1 dispute between Daniel Genho and Riverdale Hot Springs, LLC (“Riverdale” or “Resort”) over remodel work Genho performed at the Resort. Towards the end of the construction project, the parties had a payment dispute. Riverdale refused to pay Genho and prevented him from retrieving his tools and the materials he had purchased from Riverdale’s property. Genho filed a Mechanic’s and Materialmen’s Lien pursuant to Idaho Code section 45-507 against the real property of Riverdale Resort. Genho sued for breach of contract, unjust enrichment, quantum meruit, conversion, and to foreclose on the mechanic’s lien. The case proceeded to jury trial. During trial, the district court granted Riverdale’s motion for directed verdict on the breach of contract claim but denied it on Genho’s other claims. Riverdale argues that the district court erred by granting a directed verdict only on Genho’s breach of contract claim, arguing that Genho’s claims for unjust enrichment, quantum meruit, conversion, and to foreclose the lien are also barred under ICRA because Genho was not a registered Idaho contractor at all times while acting as a contractor for Riverdale. Accordingly, Riverdale asks this Court to vacate the district court’s judgment on all counts entered in favor of Genho. We affirm in part and reverse in part. I. BACKGROUND A. Factual Background Riverdale Resort is a motel and camping destination located north of Preston, Idaho, along the Bear River. Together with the motel, the Resort includes several RV sites, cabins, a condominium (“condo”), and two water slides, which include locker rooms. Riverdale Resort consists of two companies: (1) Riverdale Hot Springs, LLC, which owns the real property associated with the Resort, and (2) Riverdale Resort and Spa, LLC, which runs and operates the business located at the Resort. Jonathan Taft Steele (“Steele”) is the sole member of both LLCs (limited liability companies). Steele’s sister, Rachel Steele-Babneau (“Steele- Babneau”) manages the Resort and its workers. At some point in 2017, the women’s locker room flooded from ruptured pipes and fire damage. Steele decided that along with repairing that damage, he would remodel parts of the Resort, which included updating the lobby, motel rooms, and the condo. According to Riverdale, Steele met Genho while Genho was living in Steele’s parents’ basement. According to Genho, the two met at Steele’s home, after which Steele invited Genho to the Resort to observe the locker room damage. Genho testified that Steele walked him through the

2 property asking if Genho could repair various issues and asked for Genho’s advice on remodeling the lobby and motel rooms and building a commercial kitchen. After the walkthrough, Genho emailed Steele Google SketchUp drawings with his ideas for remodeling the kitchen, lobby, and condo. Genho testified that in response to Steele’s request, he included a quote of $89,375 for materials in one of these emails. According to Genho, Steele did not immediately respond to these emails. Instead, Genho claimed that Steele-Babneau asked Genho to start on the construction projects. Genho immediately began demolition work on those projects. Genho testified that Steele-Babneau was his primary contact at the Resort during the demolition phase. Steele described the agreement between him and Genho as a time and materials contract: Our agreement was that I would pay him [$]27.40 an hour, and I would cover any of the costs, materials, other workers, anything else that was necessary. I would cover the costs at cost, and he . . . would keep track of his hours, and I would pay him [$]27.50 an hour. And that was it. Steele claimed that the initial scope of the remodel portion of the project included updating the lobby, motel rooms, and the condo, but that the duration and other work was “open-ended” because there were several projects that needed to be done and that “we would figure those things out as we went along.” Genho acknowledged that he agreed to do the preliminary demolition work for $27.50 per hour and that the original timeline for the work was loose, with Steele telling him “when you have time, let’s just do some things.” Genho did construction work at the Resort between January and March 2018. The work included demolishing the lobby and installing a new ceiling, performing demolition work in all eight motel rooms and the condo, and installing new flooring and remodeling the motel room bathrooms. Genho testified that in February 2018 Riverdale accelerated the project timeline to try to open for the summer season. Genho testified that when Riverdale moved up the completion date, he told Steele-Babneau that he could not meet the earlier timeline on the existing time and materials contract. To meet the new timeline for the remodel project, Genho testified that he spoke with Steele- Babneau in person (Steele was not present or part of this discussion) and Steele-Babneau suggested that he hire a crew, register as a contractor, and submit a bid to Riverdale. If Riverdale accepted the bid, Genho would complete the remodel project in time for the summer season, and if Riverdale declined the bid, it was “free to go find someone else.” Genho began the process of applying for an Idaho contractor’s registration on or about February 28, 2018, and received it on March 19, 2018.

3 Genho stated that he spoke with Steele-Babneau by phone on March 14, 2018, and then texted her the quote for the remodel project. The quote was based on the work Steele-Babneau told Genho that Steele wanted done. Genho claimed that the remodel project quote was a fixed-price contract (where labor was included in the quote) and that the bid was contingent on Genho obtaining his contractor’s registration. Genho testified that even though Steele-Babneau said the bid looked good, Steele never signed the bid: [Steele-Babneau] . . . said the bid looks good. I’ll have [Steele] sign it. And then they never signed it and brought it to me. And I said: Hey, you guys never signed that. And they said: Don’t worry. We’ll pay it. We’re good. The day after this conversation, on March 15, 2018, Steele-Babneau gave him a check to buy materials to start the project the following week. Genho bought the materials the same day and immediately began work on the remodel project. Genho received his contractor’s registration four days later, on March 19, 2018. Genho testified that throughout the project, Riverdale added materials and work to the project that were not part of the original quote or bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stonebrook Constraction, LLC v. Chase Home Finance, LLC
277 P.3d 374 (Idaho Supreme Court, 2012)
Carrillo v. BOISE TIRE CO., INC.
274 P.3d 1256 (Idaho Supreme Court, 2012)
Farrell v. Whiteman
268 P.3d 458 (Idaho Supreme Court, 2012)
Taylor v. McNichols
243 P.3d 642 (Idaho Supreme Court, 2010)
Joseph Bolognese v. Paul Forte
292 P.3d 248 (Idaho Supreme Court, 2012)
Gaylen Clayson v. Don Zebe
280 P.3d 731 (Idaho Supreme Court, 2012)
AED, Inc. v. KDC Investments, LLC
307 P.3d 176 (Idaho Supreme Court, 2013)
Day v. West Coast Holdings, Inc.
699 P.2d 1067 (Nevada Supreme Court, 1985)
Highland Enterprises, Inc. v. Barker
986 P.2d 996 (Idaho Supreme Court, 1999)
Quick v. Crane
727 P.2d 1187 (Idaho Supreme Court, 1986)
Christensen v. Stuchlik
427 P.2d 278 (Idaho Supreme Court, 1967)
Smith v. Sharp
375 P.2d 184 (Idaho Supreme Court, 1962)
Nelson v. Armstrong
582 P.2d 1100 (Idaho Supreme Court, 1978)
Brower v. EI DuPont De Nemours and Co.
792 P.2d 345 (Idaho Supreme Court, 1990)
Brooks v. Gigray Ranches, Inc.
910 P.2d 744 (Idaho Supreme Court, 1996)
Vanderford Co., Inc. v. Knudson
165 P.3d 261 (Idaho Supreme Court, 2007)
Fox v. Mountain West Electric, Inc.
52 P.3d 848 (Idaho Supreme Court, 2002)
Rockefeller v. Grabow
39 P.3d 577 (Idaho Supreme Court, 2001)
Opportunity, L.L.C. v. Ossewarde
38 P.3d 1258 (Idaho Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Genho v. Riverdale Hot Springs, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/genho-v-riverdale-hot-springs-llc-idaho-2024.