Gaylen Clayson v. Don Zebe

280 P.3d 731, 153 Idaho 228, 2012 WL 2529226, 2012 Ida. LEXIS 168
CourtIdaho Supreme Court
DecidedJuly 2, 2012
Docket38471
StatusPublished
Cited by27 cases

This text of 280 P.3d 731 (Gaylen Clayson v. Don Zebe) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gaylen Clayson v. Don Zebe, 280 P.3d 731, 153 Idaho 228, 2012 WL 2529226, 2012 Ida. LEXIS 168 (Idaho 2012).

Opinion

*231 HORTON, Justice.

This appeal arises from Gaylen Clayson’s attempt to purchase a restaurant and cheese factory in Thayne, Wyoming. Prior to making a formal offer on the property, Clayson was granted access to the property in order to begin operating the restaurant and refurbishing the factory. Clayson’s effort to purchase the subject property ultimately failed, and Don Zebe (Don) and Rick Lawson (referred to individually as Don or Rick, collectively as Zebe) subsequently purchased the property. Clayson then filed a breach of contract action against Zebe, alleging the existence of both express and implied contracts entitling Clayson to compensation for the pre-purchase work Clayson had performed on the property. The district court partially granted Zebe’s motion for summary judgment, holding that there was no express contract between the parties. After a bench trial, the district court determined that the parties’ conduct created both implied-in-fact and implied-in-law contracts, which required Zebe to reimburse Clayson $97,310.94 for costs he incurred while working on the subject property.

Zebe appeals, arguing that the district court erred because Zebe neither requested Clayson’s performance nor received any benefit as a result of Clayson’s work on the property. Zebe asks this Court to vacate the judgment of the district court and remand the matter for entry of judgment in their favor. We affirm.

I. FACTUAL AND PROCEDURAL BACKGROUND

In 2007, Clayson entered into discussions to purchase the Star Valley Cheese Plant (Plant) in Thayne, Wyoming, from Morris Farinella. Prior to entering into any contract, Farinella gave Clayson permission to take over operation of the restaurant attached to the Plant. On July 1, 2008, Clay-son began living at the Plant to manage the restaurant and supervise the cleaning and refurbishing of the cheese factory. According to Clayson, he worked ten to twelve hours per day, six days per week from July 1, 2008, until October 8, 2008. He hired and supervised workers that performed refurbishing tasks at the Plant, which included cleaning, plaster repair, painting, floor resurfacing, and removing unnecessary equipment. Around the end of July 2008, Clayson hired Dairy Systems Company, Inc., (Dairy Systems) to upgrade the electrical system at the Plant, for which Clayson paid Dairy Systems $50,000. Overall, Clayson claims he incurred approximately $150,000 in expenses to refurbish the Plant.

A mutual friend introduced Clayson to Don and Rick sometime in the summer of 2008. Don, a real estate agent, initially became involved in the transaction to help Clayson prepare a business plan to assist in obtaining financing. Rick is an accountant who performed the financial analysis included in the business plan. At some point, Don and Rick became interested in participating in owning and operating the Plant with Clayson.

On October 2, 2008, Clayson, Don, and Rick formed a Wyoming limited liability company known as SVC, LLC (SVC), with the expectation that the three would jointly own and operate the Plant. On October 8, 2008, Clayson called Rick and requested assistance meeting the restaurant payroll. The parties dispute the exact content of that conversation, but Clayson contends that Rick agreed to reimburse Clayson for the refurbishment expenses he incurred if Clayson would withdraw from the plan to own and operate the Plant. The same day, Clayson stopped working on the Plant and left the premises. After the conversation with Clayson, Rick had the SVC articles of incorporation amended to remove Clayson’s name. Clayson testified that shortly after the phone call between himself and Rick, both Don and Rick confirmed that they would pay Clayson’s proved refurbishment expenses once they obtained financing for the purchase.

Clayson entered into a purchase and sale agreement (Agreement) on October 17, 2008, in which he agreed to purchase the Plant for $800,000. Neither Don nor Rick was a party to the Agreement, but Clayson assigned his interest in the Agreement to SVC on November 4, 2008. The assignment was made by way of an addendum to the Agreement and is silent as to consideration.

*232 After Clayson assigned the Agreement to SVC, Don made several statements about his intention to pay Clayson, including the following: On January 14, 2009, Don emailed the real estate agent handling the transaction for the Plant and stated he and Rick planned to “absorb” the cost of Clayson’s refurbishments, including electrical work. In order to obtain their own financing, Don and Rick also submitted a business plan to their lender, which falsely represented that SVC had already paid Dairy Systems for its work. Additionally, Don sent three emails to Dairy Systems in which he indicated that he intended to pay Dairy Systems for the work it had done at Clayson’s request. SVC eventually did purchase the Plant, closing the transaction on February 24,2009.

Clayson filed his initial complaint on June 9, 2009, alleging breach of contract and, alternatively, unjust enrichment, along with several unrelated claims. The district court granted partial summary judgment in favor of Zebe, dismissing all of Clayson’s claims except the claim for reimbursement under either an implied-in-fact or implied-in-law contract. The district court dismissed Clay-son’s claim of breach of an express contract, finding that there was no evidence that the parties had achieved a meeting of the minds as to all terms of the contract. After a court trial, the district court found that both implied-in-law and implied-in-fact contracts existed and awarded Clayson damages totaling $97,310.24. Zebe timely appealed.

II. STANDARD OF REVIEW

Both quantum meruit (implied-in-fact contracts) and unjust enrichment (implied-in-law contracts) are “measures of equitable recovery.” Farrell v. Whiteman (Farrell I), 146 Idaho 604, 612, 200 P.3d 1153, 1161 (2009) (citing Great Plains Equip., Inc. v. Nw. Pipeline Corp., 132 Idaho 754, 767, 979 P.2d 627, 640 (1999)). “The application of equitable remedies is a question of fact because it requires a balancing of the parties’ equities.” Farrell v. Whiteman (Farrell II), 152 Idaho 190, 194, 268 P.3d 458, 462 (2012) (citing O’Connor v. Harger Const., Inc., 145 Idaho 904, 909, 188 P.3d 846, 851 (2008)). “In all actions tried upon the facts without a jury ..., the court shall find the facts specially and state separately its conclusions of law thereon____” I.R.C.P. 52(a). When reviewing a district court’s decision after a trial without a jury, this Court’s review of the decision:

[I]s limited to ascertaining whether the evidence supports the findings of fact, and whether the findings of fact support the conclusions of law. A district court’s findings of fact in a bench trial will be liberally construed on appeal in favor of the judgment entered, in view of the district court’s role as trier of fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Freeland v. Agricultural Services, Inc.
Idaho Court of Appeals, 2025
R.C. Worst & Company, Inc. v. Williams
Idaho Court of Appeals, 2025
Genho v. Riverdale Hot Springs, LLC
560 P.3d 1041 (Idaho Supreme Court, 2024)
Abell v. Abell
534 P.3d 957 (Idaho Supreme Court, 2023)
Bagby v. Davis
Idaho Supreme Court, 2023
Cook v. Van Orden
507 P.3d 119 (Idaho Supreme Court, 2022)
Turcott v. Estate of Bates
443 P.3d 197 (Idaho Supreme Court, 2019)
Valiant Idaho, LLC v. N. Idaho Resorts, LLC
428 P.3d 800 (Idaho Supreme Court, 2018)
Medical Recovery Svc v. Neumeier
Idaho Supreme Court, 2018
Med. Recovery Servs., LLC v. Neumeier
415 P.3d 372 (Idaho Supreme Court, 2018)
Bret and Marti Kunz v. Nield, Inc.
398 P.3d 165 (Idaho Supreme Court, 2017)
John B. Kugler v. Ron Nelson
374 P.3d 571 (Idaho Supreme Court, 2016)
American Bank v. BRN Dev. & Taylor Eng.
358 P.3d 762 (Idaho Supreme Court, 2015)
Usha Pandey Sharma v. Niraj Sharma
Idaho Court of Appeals, 2015
Pocatello Hospital, LLC v. Quail Ridge Medical Investor, LLC
330 P.3d 1067 (Idaho Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
280 P.3d 731, 153 Idaho 228, 2012 WL 2529226, 2012 Ida. LEXIS 168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gaylen-clayson-v-don-zebe-idaho-2012.