Ivanov v. Fitness Elite Training Center, Inc.

CourtDistrict Court, D. Idaho
DecidedMarch 3, 2025
Docket1:20-cv-00380
StatusUnknown

This text of Ivanov v. Fitness Elite Training Center, Inc. (Ivanov v. Fitness Elite Training Center, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ivanov v. Fitness Elite Training Center, Inc., (D. Idaho 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF IDAHO

IVAN DELCHEV IVANOV, Case No. 1:20-cv-00380-CWD Plaintiff, v. MEMORANDUM DECISION AND ORDER ON REMAND FITNESS ELITE TRAINING CENTER, INC., an Idaho corporation, DAN MAUGER, and BROOKE MAUGER

Defendants.

INTRODUCTION This matter is before the Court following a decision on appeal remanding the case in part for further proceedings. (Dkt. 166, 167.) At the Court’s direction, the parties conferred and submitted briefing on the two issues identified for remand. (Dkt. 168, 171, 172, 174, 175, 176, 177.) The facts and legal arguments are adequately presented in the briefs and record. Accordingly, in the interest of avoiding delay, and because the Court conclusively finds that the decisional process would not be aided by oral argument, the issues on remand will be decided on the present record. Dist. Idaho L. Civ. R. 7.1(d). The Court finds as follows. BACKGROUND1 This diversity case arises from Plaintiff’s claim that Defendants breached the Head Coach Employment Agreement (Agreement) by terminating Plaintiff’s employment as

the Head Wrestling Coach for Fitness Elite Training Center without cause. The Complaint raised five causes of action: 1) breach of contract; 2) a claim for unpaid wages under the Idaho Wage Claim Act (“IWCA”), Idaho Code Section 45-615; 3) breach of the implied covenant of good faith and fair dealing; 4) piercing the corporate veil; and 5) quasi-estoppel. (Dkt. 1.)

A five-day jury trial was held, and after deliberations on July 28, 2023, the jury returned a verdict in favor of Plaintiff on his claims for breach of contract and breach of the implied covenant of good faith and fair dealing. (Dkt. 93.) The jury found Plaintiff’s employment was terminated without cause and awarded Plaintiff $660,000.00 on the breach of contract claim, and $456.52 on the breach of the implied covenant claim. The

equitable claims were submitted to the jury for an advisory verdict. (Dkt. 81, 93.) Post- trial motions were filed and, on October 6, 2023, the Court entered its Findings of Fact and Conclusions of Law, issued decisions on the post-trial motions, and entered a Judgment. (Dkt. 117, 118, 119, 120.) The Judgment awarded Plaintiff a total amount of $2,279,108.55, comprised of

trebled damages for unpaid wages pursuant to the IWCA; the damages awarded on the breach of the implied covenant claim; and pre-judgment interest. (Dkt. 46, 117, 118, 119,

1 Because the factual and procedural history are well known to the parties and the Court, they are not recited in full here. 120.) On November 30, 2023, the Clerk taxed costs in the amount of $6,100.94. (Dkt. 144.) On March 28, 2024, the Court awarded Plaintiff attorney fees in the amount of $911,643.42, and entered an Amended Judgment. (Dkt. 155, 156.) On April 11, 2024,

Plaintiff filed a motion for supplemental attorney fees and a motion to amend/correct the judgment. (Dkt. 158, 159.) Defendants filed Notices of Appeal on October 20, 2023, and April 24, 2024. (Dkt. 122, 160.) On June 13, 2024, the Court entered a Memorandum Decision and Order awarding Plaintiff supplemental attorney fees in the amount of $25,585.00, and issued an indicative

ruling regarding Plaintiff’s motion to amend/correct the judgment. (Dkt. 165.) On November 5, 2024, the Ninth Circuit Court of Appeals issued a decision reversing in part, affirming in part, vacating in part, and remanding the case for further proceedings. (Dkt. 166.) The Ninth Circuit concluded the Agreement provided for liquidated damages, not wages, and therefore reversed the portions of the Court’s judgment trebling the breach of

contract damages under the IWCA and awarding fringe benefits. (Dkt. 166.) The award of attorney fees was vacated and remanded, because the calculation was based on the size of the damages award. The mandate was filed on November 27, 2024. (Dkt. 167.) DISCUSSION The parties have identified two issues that require resolution by the Court on

remand: 1) calculations of pre-judgment and post-judgment interest; and 2) the award of attorney fees. (Dkt. 171, 174, 175, 176, 177.) The Court will address each issue in turn below. 1. Calculation of Interest The parties agree that the $660,000.00 award of damages is subject to pre- judgment interest at the Idaho statutory rate of 12% beginning on the date the contract

damages became due, June 26, 2020. (Dkt. 171.) However, the parties disagree as to the calculations of pre-judgment and post-judgment interest, and dispute the total amount of interest accrued. Specifically, the parties dispute the dates and judgments from which pre- judgment and post-judgment interest should begin and end. A. Legal Standard

“While the entry of judgment is the traditional dividing line between when pre- judgment interest ends and post-judgment interest begins, it can be blurred by post- judgment litigation and a delay in the payment of a damages award.” Trendsettah USA Inc. v. Swisher Intl. Inc., 2023 WL 8263365, at *3 (C.D. Cal. Nov. 17, 2023). “The general rule is that when an appellate court reverses a judgment of the district court and

directs that a money judgment in favor of a claimant be entered upon remand, pre- judgment interest runs through the date of the newly-entered judgment.” Am. Tel. & Tel. Co. v. United Computer Sys., Inc. (AT&T), 98 F.3d 1206, 1209 (9th Cir. 1996) (citing Fed. R. App. P. 37). However, “an exception to this rule is made when a legally sufficient

determination of damages had been made at the time of some prior judgment, which the judgment upon remand essentially reinstates.” Id. (citing and discussing Northrop Corp. v. Triad Intl. Marketing, S.A., 842 F.2d 1154, 1156 (9th Cir. 1988)). In determining whether to deviate from the general rule, courts consider: “(1) at what point damages are sufficiently ascertained, (2) whether the pre-judgment or post-judgment interest rate is higher, and (3) whether the prevailing or losing party is responsible for the delay.” Trendsettah, 2023 WL 8263365, at *3-4 (citing AT&T, 98 F.3d at 1210–11 and Barnard

v. Theobald, 649 Fed. Appx. 414, 416 (9th Cir. 2016)). B. Pre-Judgment Interest Plaintiff argues pre-judgment interest should be calculated, based on equitable principles, to begin on June 26, 2020, and continue until the date the Court enters judgment on remand. (Dkt. 175.) This, Plaintiff contends, will most fully compensate the

prevailing party. Defendants, on the other hand, argue pre-judgment interest should be calculated to begin on June 25, 2020, and end on the date of the initial Judgment, October 6, 2023, because the Ninth Circuit’s remand reinstated the jury’s award of $660,000.00 and the damages were sufficiently ascertainable at the time of the jury’s verdict. (Dkt. 174.) Having carefully reviewed the entire record, the Court finds that the accrual of pre-

judgment interest began June 26, 2020, and ended October 6, 2023, for the reasons explained below.2 The damages to be awarded on remand, $660,000.00, were decided by the jury’s verdict at the time the October 6, 2023 Judgment was entered. The Ninth Circuit’s remand did not disturb the jury’s award of damages. (Dkt. 166.) Thus, a legally sufficient

2 Although the Joint Memorandum states the parties agree that pre-judgment interest begins on June 25, 2020, the parties apply different start dates in their briefing of June 25, 2020 and June 26, 2020. (Dkt. 171, 174-177.) It is undisputed that Defendants were obligated to remit the contract payment due to Plaintiff by June 25, 2020, and breached the contract by failing to do so on that day. (Dkt. 175.) Therefore, the contract damages to which pre-judgment interest applies began accruing the following day, June 26, 2020.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaiser Aluminum & Chemical Corp. v. Bonjorno
494 U.S. 827 (Supreme Court, 1990)
Oakes v. Boise Heart Clinic Physicians, PLLC
272 P.3d 512 (Idaho Supreme Court, 2012)
Schroeder v. Partin
259 P.3d 617 (Idaho Supreme Court, 2011)
Hobson Fabricating Corp. v. SE/Z Construction, LLC
294 P.3d 171 (Idaho Supreme Court, 2012)
McEnroe v. Morgan
678 P.2d 595 (Idaho Court of Appeals, 1984)
Brooks v. Gigray Ranches, Inc.
910 P.2d 744 (Idaho Supreme Court, 1996)
Dunn & Black, P.S. v. United States
492 F.3d 1084 (Ninth Circuit, 2007)
Winterrowd v. American General Annuity Insurance
556 F.3d 815 (Ninth Circuit, 2009)
Rockefeller v. Grabow
39 P.3d 577 (Idaho Supreme Court, 2001)
Sun Valley Potato Growers, Inc. v. Texas Refinery Corp.
86 P.3d 475 (Idaho Supreme Court, 2004)
Eighteen Mile Ranch, LLC v. Nord Excavating & Paving, Inc.
117 P.3d 130 (Idaho Supreme Court, 2005)
Smith v. Mitton
104 P.3d 367 (Idaho Supreme Court, 2004)
Keith A. Sims v. Dan S. Jacobson
342 P.3d 907 (Idaho Supreme Court, 2015)
Francois Tabi v. Lazaro Ortega
649 F. App'x 413 (Ninth Circuit, 2016)
Charles Barnard v. Greg Theobald
649 F. App'x 414 (Ninth Circuit, 2016)
Wadsworth Reese, PLLC v. Siddoway & Co, PC
445 P.3d 1090 (Idaho Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Ivanov v. Fitness Elite Training Center, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ivanov-v-fitness-elite-training-center-inc-idd-2025.