Day v. West Coast Holdings, Inc.

699 P.2d 1067, 101 Nev. 260, 1985 Nev. LEXIS 409
CourtNevada Supreme Court
DecidedMay 21, 1985
Docket15208
StatusPublished
Cited by20 cases

This text of 699 P.2d 1067 (Day v. West Coast Holdings, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Day v. West Coast Holdings, Inc., 699 P.2d 1067, 101 Nev. 260, 1985 Nev. LEXIS 409 (Neb. 1985).

Opinion

*261 OPINION

Per Curiam:

Respondent West Coast Holdings, Inc. (“West Coast”) filed a complaint against appellants (Ronald J. Day, individually, and dba R.J. Construction Company, and Frank Gonzales) (“R.J”) seeking recovery for breach of a landscaping contract, for slander of title, and to discharge a mechanic’s lien. R.J. counterclaimed *262 seeking recovery for West Coast’s breach of contract, or alternatively, unjust enrichment. The district court awarded R.J. damages but reduced and offset the original contract price. 1 The district court denied R.J. recovery for extra services and materials, prejudgment interest and costs. The district court found in West Coast’s favor on its cause of action for slander of title but did not award any damages. This appeal and cross-appeal followed.

THE FACTS

In March, 1982, Frank Gonzales, an employee of R.J., negotiated a subcontract for landscaping Newport Cove III, a condominium project, with West Coast’s construction manager. Prior to the execution of the contract Gonzales informed West Coast that while R.J. did have a Nevada general contractor’s license, it did not yet have a specialty landscaping license. On March 31, 1982, R.J. and West Coast executed the landscaping subcontract. The contract provided for R.J. to supply landscaping services and materials for a contract price of $78,000 with a completion date of April 15, 1982.

There was a nine-day delay attributable to West Coast before R.J. commenced work. R.J. began performance on April 9 and finished the work on May 17, 1982. Other than the initial nine days, West Coast did not excuse any other delays. There is no evidence that West Coast suffered any monetary damages as a result of any delays.

After completing its work on May 17, 1982, R.J. demanded payment for the balance due under the contract. West Coast refused. On May 21, 1982, R.J. filed a mechanic’s lien claiming $44,311.20 as the balance due under the contract. West Coast filed suit and R.J. counterclaimed. 2

REDUCTION OF PROFIT AND OVERHEAD

In calculating the amount due R.J. under the contract, the district court reduced the contract price of $78,000 to $58,500 by deducting an amount attributable to R.J.’s 10% profit and 15% overhead. The district court stated that the basis for this reduction *263 was the unexcused delay by R.J. in completing the contract and R.J.’s tactics in filing an amended lien for extra services and materials. R.J. contends, and we agree, that the district court erred.

The only evidence of any pecuniary damage to West Coast due to faulty workmanship by R.J. was a repair estimate of $2,444. Further, the only damages ever claimed by West Coast for faulty performance was the repair estimate of $2,444. There is simply no evidence in the record that West Coast suffered any other damages. Where there is no substantial conflict in the evidence on any material point and the decision is manifestly contrary to the evidence, the reviewing court is bound to take remedial action. Avery v. Gilliam, 97 Nev. 181, 182, 625 P.2d 1166, 1168 (1981), Cardan Overseas, Ltd. v. Harris, 92 Nev. 62, 64, 544 P.2d 1202, 1203 (1976). The district court’s reduction of the contract price by the 10% profit and 15% overhead is not supported by substantial evidence. This reduction may therefore not be sustained on appeal.

EXTRA SERVICES AND MATERIALS

The district court found that the extra services and materials provided by R.J. to West Coast were gratuitous. R.J. contends, and we agree, that the district court erred in refusing to award R.J. the reasonable value of its extra services and materials.

At trial, uncontroverted testimony established that West Coast verbally requested R.J. to perform extra services and materials not covered within' the original contract. Uncontroverted testimony also established that both parties understood that R.J. was not rendering these services and materials gratuitously. Where services are requested a presumption arises that the beneficiary promises to pay the reasonable value of the services. Checker, Inc. v. Zeman, 86 Nev. 216, 467 P.2d 100 (1970). Furthermore, the extra services were actually performed, extra materials provided, all of which benefited West Coast. Through its conduct West Coast accepted R.J.’s extra services and materials. The record reveals no evidence to even suggest that the additional services were gratuitous. The district court’s ruling to this effect is clearly erroneous. Unionamerica Mtg. v. McDonald, 97 Nev. 210, 211, 626 P.2d 1272, 1273 (1981).

PREJUDGMENT INTEREST

The district court awarded legal interest to R.J. as of the date of judgment. R.J. contends that the district court erred in not award *264 ing prejudgment interest under the provisions of NRS 17.130. We agree. 3 There is no evidence supporting the district court’s denial of prejudgment interest. R.J. was awarded judgment under the contract between the parties. The district court erred in failing to award prejudgment interest. Udevco, Inc. v. Wagner, 100 Nev. 185, 678 P.2d 679 (1984).

FAILURE TO AWARD COSTS

The district court held that each party should bear its own costs. R.J. claims that NRS 18.020 is applicable and mandates the award of costs to R.J. 4

In an action at law, not equity, the allowance of costs is mandatory and not subject to the court’s discretion. See Randono v. Turk, 86 Nev. 123, 133, 466 P.2d 218, 224 (1970). R.J. was the prevailing party in an action on the contract and sought to and did recover more than $1,250. R.J.’s claim falls within the provisions of NRS 18.020. The district court erred in failing to award costs.

THE CROSS-APPEAL

The district court held that NRS 624.320 did not preclude R.J. from recovering under the contract. 5 The court also found that *265

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Genho v. Riverdale Hot Springs, LLC
560 P.3d 1041 (Idaho Supreme Court, 2024)
Ace Pipe Cleaning, Inc. v. Hemphill Construction Co.
134 So. 3d 799 (Court of Appeals of Mississippi, 2014)
Solley v. NAVY FEDERAL CREDIT UNION, INC.
723 S.E.2d 597 (Court of Appeals of South Carolina, 2012)
Kourafas v. Basic Food Flavors, Inc.
88 P.3d 822 (Nevada Supreme Court, 2004)
Trees v. Kersey
56 P.3d 765 (Idaho Supreme Court, 2002)
INTERSTATE COMMERCIAL BLDG. SERV. v. Bank of Amer.
23 F. Supp. 2d 1166 (D. Nevada, 1998)
Gillmor v. Cummings
904 P.2d 703 (Court of Appeals of Utah, 1995)
Foley v. Kennedy
885 P.2d 583 (Nevada Supreme Court, 1994)
Schwartz v. Estate of Greenspun
881 P.2d 638 (Nevada Supreme Court, 1994)
Michelsen v. Harvey
866 P.2d 1141 (Nevada Supreme Court, 1994)
Govert Copier Painting v. Van Leeuwen
801 P.2d 163 (Court of Appeals of Utah, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
699 P.2d 1067, 101 Nev. 260, 1985 Nev. LEXIS 409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/day-v-west-coast-holdings-inc-nev-1985.