Ground Control, LLC. v. Capsco Industries, LLC

CourtMississippi Supreme Court
DecidedApril 4, 2011
Docket2011-IA-00928-SCT
StatusPublished

This text of Ground Control, LLC. v. Capsco Industries, LLC (Ground Control, LLC. v. Capsco Industries, LLC) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ground Control, LLC. v. Capsco Industries, LLC, (Mich. 2011).

Opinion

IN THE SUPREME COURT OF MISSISSIPPI

NO. 2011-IA-00928-SCT

GROUND CONTROL, LLC

v.

CAPSCO INDUSTRIES, INC., W.G. YATES & SONS CONSTRUCTION COMPANY AND HARRAH’S ENTERTAINMENT, INC.

DATE OF JUDGMENT: 04/04/2011 TRIAL JUDGE: HON. ROGER T. CLARK COURT FROM WHICH APPEALED: HARRISON COUNTY CIRCUIT COURT ATTORNEY FOR APPELLANT: BLEWETT W. THOMAS ATTORNEYS FOR APPELLEES: R. MARK ALEXANDER, JR. MATTHEW W. McDADE NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: REVERSED AND REMANDED - 06/06/2013 MOTION FOR REHEARING FILED: MANDATE ISSUED:

EN BANC.

WALLER, CHIEF JUSTICE, FOR THE COURT:

¶1. Ground Control, LLC, seeks review of summary judgment granted in favor of Capsco

Industries and other defendants. The circuit court held in part that Ground Control’s failure

to obtain a certificate of responsibility, as required by Mississippi Code Section 31-3-15,

rendered its construction contract with Capsco null and void. While we affirm the court’s

finding that the lack of certificates of responsibility rendered the parties’ contract null and

void, we reverse the grant of summary judgment in part and remand this case for further proceedings on whether Ground Control is entitled to recover based on claims of unjust

enrichment and quantum meruit. We also reverse the grant of summary judgment in favor

of Harrah’s and Yates because of inadequate notice of the conversion from a motion to

dismiss to a motion for summary judgment.

FACTS AND PROCEEDINGS BEFORE THE TRIAL COURT

¶2. The plaintiff and counterdefendant below, Ground Control, LLC, an Alabama

corporation, entered into a contract with Capsco Industries, Inc., also an Alabama

corporation, to perform construction on the “Margaritaville Spa and Hotel” in Biloxi, on

behalf of Harrah’s Entertainment, Inc. W.G. Yates and Sons Construction Company served

as the general contractor. Capsco was employed as a subcontractor, and Capsco

subcontracted in-ground construction work to Ground Control.

¶3. Capsco entered into its contract with Ground Control on December 19, 2007; neither

Yates nor Harrah’s was a party to the contract. Ground Control was to perform work related

to in-ground installation of water, sewage, and storm-drain lines. It is undisputed that neither

party obtained a certificate of responsibility as required by Mississippi Code Section 31-3-21.

Ground Control worked on the project until October 28, 2008, when Yates terminated it from

the project for alleged safety violations and failed drug tests of its employees.

¶4. On August 25, 2009, Ground Control filed its complaint against the defendants in

Harrison County Circuit Court. On December 4, 2009, Capsco counterclaimed and filed a

third-party claim against Ground Control’s president, Frank Beaton, alleging that Ground

Control breached the contract and that Beaton had committed acts of fraud. On December

8, 2009, Harrah’s and Yates jointly moved to dismiss for lack of privity. On December 29,

2 2009, Ground Control filed a supplemental complaint alleging various extracontractual

claims. On January 2, 2012, Capsco filed a motion for summary judgment, and a hearing

subsequently was held on Harrah’s and Yates’ joint motion to dismiss as well as Capsco’s

motion for summary judgment. On April 4, 2011, the trial court granted summary judgment

to Capsco and to Harrah’s and Yates, even though the latter two jointly had moved to dismiss

and not for summary judgment. The record shows that Ground Control never received notice

that Yates’ and Harrah’s motion to dismiss would be converted to a motion for summary

judgment until the trial court issued its order granting summary judgment. Ground Control

timely filed this appeal.

DISCUSSION

¶5. This Court applies a de novo standard of review to a circuit court’s grant or denial of

summary judgment. Kilhullen v. Kan. City S. Ry., 8 So. 3d 168, 174 (Miss. 2009). Upon

review, this Court must view the evidence “in the light most favorable to the party against

whom the motion has been made.” Id. (quoting Daniels v. GNB, Inc., 629 So. 2d 595, 599

(Miss. 1993)).

¶6. On appeal, Ground Control asks the court to consider multiple issues pertaining to the

three defendants. Because some of the issues are very closely related to one another, we

have consolidated the arguments for the sake of clarity into the following issues: (1) whether

Ground Control’s failure to acquire the proper certification pursuant to statute barred any

claim for recovery against Capsco and (2) whether the trial court properly converted Yates’

and Harrah’s motion to dismiss to one for summary judgment.

I. WHETHER GROUND CONTROL’S FAILURE TO ACQUIRE THE PROPER

3 CERTIFICATION UNDER SECTION 31-3-15 BARRED ANY CLAIM FOR RECOVERY AGAINST CAPSCO.

¶7. The contract between Capsco and Ground Control falls within Mississippi Code

Section 31-3-15, which requires contractors to have certificates of responsibility. It states:

No contract for public or private projects shall be issued or awarded to any contractor who did not have a current certificate of responsibility issued by said board at the time of the submission of the bid, or a similar certificate issued by a similar board of another state which recognizes certificates issued by said board. Any contract issued or awarded in violation of this section shall be null and void.

Miss. Code Ann. § 31-3-15 (Rev. 2010) (emphasis added).

¶8. The stated purpose of requiring certificates of responsibility “is to protect the health,

safety and general welfare of all persons dealing with those who are engaged in the vocation

of contracting and to afford such persons an effective and practical protection against

incompetent, inexperienced, unlawful and fraudulent acts of contractors.” Miss. Code Ann.

§ 31-3-2 (Rev. 2010) (emphasis added). Clearly, the statute was intended to protect both

parties to the contract. Furthermore, the penalties that serve to deter parties from entering

illegal contracts—such as voiding the contract and imposing fines—apply to both parties.1

¶9. Both Ground Control and Capsco were required by statute to obtain certificates of

1 The statutory penalties for entering a contract where one or both of the parties have no certificate of responsibility are (1) to void the contract, (2) find the violators guilty of a misdemeanor, (3) fine up to $1,000, or imprison for no more than six months or impose both such fine and imprisonment. In addition, the State Board of Contractors may issue an order of abatement directing the contractor to cease all actions until Mississippi state law is complied with, require the violator to pay to the board a civil penalty of not more than three percent of the total contract being performed by the contractor, and require the violator to perform community service for a specified number of hours as determined by the board. Miss. Code Ann. §§ 31-3-15; 31-3-21(1) and (2); and 31-3-21(4) (Rev. 2010).

4 responsibility. Both failed to do so.

¶10. This Court has never determined whether a party to an illegal contract is barred from

recovery under theories of unjust enrichment or quantum meruit. We are not dealing with

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hubbard v. United States
514 U.S. 695 (Supreme Court, 1995)
National Federation of Independent Business v. Sebelius
132 S. Ct. 2566 (Supreme Court, 2012)
Romero v. Parker
2009 NMCA 047 (New Mexico Court of Appeals, 2009)
Dew v. Langford
666 So. 2d 739 (Mississippi Supreme Court, 1995)
Coleman v. Bossier City
305 So. 2d 444 (Supreme Court of Louisiana, 1974)
Hydrotech Systems, Ltd. v. Oasis Waterpark
803 P.2d 370 (California Supreme Court, 1991)
Thigpen v. Kennedy
238 So. 2d 744 (Mississippi Supreme Court, 1970)
State v. Loewen
647 P.2d 489 (Washington Supreme Court, 1982)
A.K. & R. Whipple Plumbing & Heating v. Aspen Construction
1999 UT App 87 (Court of Appeals of Utah, 1999)
Magill v. Lewis
333 P.2d 717 (Nevada Supreme Court, 1958)
Golberg v. Sanglier
639 P.2d 1347 (Washington Supreme Court, 1982)
M. Arthur Gensler, Jr., & Associates, Inc. v. Larry Barrett, Inc.
499 P.2d 503 (California Supreme Court, 1972)
JIPAC, NV v. Silas
800 A.2d 1092 (Supreme Court of Vermont, 2002)
Twiehaus v. Rosner
245 S.W.2d 107 (Supreme Court of Missouri, 1952)
City of Damascus v. Bivens
726 S.W.2d 677 (Supreme Court of Arkansas, 1987)
Davis v. City of Clarksdale
18 So. 3d 246 (Mississippi Supreme Court, 2009)
Sullivan v. Tullos
19 So. 3d 1271 (Mississippi Supreme Court, 2009)
Kilhullen v. Kansas City Southern Railway
8 So. 3d 168 (Mississippi Supreme Court, 2009)
Morrissey v. BOLOGNA
123 So. 2d 537 (Mississippi Supreme Court, 1960)
Koval v. Koval
576 So. 2d 134 (Mississippi Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Ground Control, LLC. v. Capsco Industries, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ground-control-llc-v-capsco-industries-llc-miss-2011.