Romero v. Parker

2009 NMCA 047, 207 P.3d 350, 146 N.M. 116
CourtNew Mexico Court of Appeals
DecidedMarch 25, 2009
Docket27,027
StatusPublished
Cited by9 cases

This text of 2009 NMCA 047 (Romero v. Parker) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Romero v. Parker, 2009 NMCA 047, 207 P.3d 350, 146 N.M. 116 (N.M. Ct. App. 2009).

Opinion

OPINION

WECHSLER, Judge.

{1} Plaintiff Jessie Romero (Romero) appeals from the district court’s summary judgment in favor of Defendants Robert Parker (Parker) and Sivad Enterprises, LLC (Sivad). We address whether the Construction Industries Licensing Act (the CILA), NMSA 1978, §§ 60-13-1 to -59 (1967, as amended through 2007), which precludes an unlicensed contractor from seeking compensation for construction work that can only be performed by a licensed contractor, also bars an unlicensed subcontractor from recovering compensation for construction work from the general contractor. We hold that it does. We also address whether the CILA bars a general contractor who did not act responsibly in hiring an unlicensed subcontractor from recovering compensation already paid to the unlicensed subcontractor, and, again, we hold that it does. Additionally, we hold that equitable principles do not apply in this situation. We further hold that Parker was not an agent for an undisclosed principal, Sivad, and is thus not personally liable to Romero. We affirm in part and reverse in part.

BACKGROUND

{2} Romero, who is in the business of construction, performed work for Sivad, operating a backhoe, laying stone, and performing other masonry work without a contractor’s license. Sivad is a general contractor. Parker was Sivad’s agent for contracts and construction projects, and Steve Davis (Davis) was Sivad’s member/manager. Romero dealt primarily with Parker and Davis and claims to have not known about Sivad until after a conflict arose. Although Romero claims that he worked for Parker, and much of Romero’s dealings were with Parker, he, in fact, worked for Sivad, and Parker was Sivad’s agent. Romero did not bid on any work, and there were no written contracts. Sivad had Romero working on construction projects at five residences (the construction projects) at once, each with several assignments. Romero prepared invoices for payment, which show a variety of billing methods including per hour, per load, per square foot, and per item. Romero was paid for a portion of his work and filed a complaint for breach of the construction contracts for the remainder. Romero alleges that he fully performed all work under the contracts, demanded payment, and was refused. Defendants filed a motion for summary judgment, claiming that Romero could not recover compensation under the complaint because he was operating as an unlicensed contractor contrary to the CILA requirements. Romero argued that genuine issues of material fact still existed and that his compensation claims were not barred because Parker knew that Romero was not licensed and nevertheless allowed Romero to continue work with reasonable expectation that he would be fairly compensated at the conclusion of each job assignment. Parker denies knowing that Romero was not licensed at the time the work was assigned.

{3} The district court granted Defendants’ motion for summary judgment on four of the five construction projects, finding that some portion of Romero’s work at those construction projects required a contractor’s license, that he did not have one, and that, therefore, he was barred from recovering compensation pursuant to the CILA and Gamboa v. Urena, 2004-NMCA-053, 135 N.M. 515, 90 P.3d 534. In response to Romero’s motion to amend the complaint to add an equitable estoppel claim, the district court denied the motion on the basis that Gamboa made the amendment “futile.” The order was certified for interlocutory appeal, and this Court denied the application.

{4} Sivad then asserted a counterclaim for a refund of the money that Sivad had already paid Romero for his work on the construction projects. Romero filed a second motion to amend the complaint to add a claim of damages against Parker for misrepresentation, claiming that Parker falsely represented himself, not Sivad, as the general contractor. Thereafter, Sivad filed a motion for summary judgment on its counterclaim, arguing that the CILA, Gamboa, and Mascarenas v. Jaramillo, 111 N.M. 410, 806 P.2d 59 (1991), mandated that Sivad receive a full refund of compensation already paid to Romero. The district court denied Romero’s second motion to amend the complaint, again on the basis that “[t]he proposed amendment of the Complaint is futile under New Mexico law.” Sivad’s motion for summary judgment on its counterclaim was stricken without prejudice as untimely filed under the scheduling order.

{5} Romero’s answer to Sivad’s counterclaim asserted as affirmative defenses essentially the same equitable claims he had sought to bring by way of his first and second motions to amend the complaint. Romero alleged that Parker knew Romero was unlicensed, that Parker had misrepresented to Romero that Romero did not need a contractor’s license to work on the construction projects, and that Parker had assured Romero that he would be paid regardless. Romero also asserted that Sivad was not entitled to a refund of amounts already paid to Romero under its counterclaim because Sivad is not the “innocent consumer” protected by the CILA and applicable case law. Romero added that “[t]he equitable doctrines of unclean hands, unjust enrichment, estoppel and implied covenant ... should apply herein.” Although the district court had previously stricken Sivad’s motion for summary judgment as untimely, it apparently granted a hearing on the motion at a later date. As a result of that hearing, the district court granted in part and denied in part Sivad’s motion for summary judgment on the counterclaim, ruling that, under New Mexico law, Sivad was entitled to be reimbursed for compensation already paid to Romero, an unlicensed contractor.

{6} In its final judgment, the district court adopted Defendants’ proposed findings and conclusions and noted the summary judgments already granted against the complaint and in favor of the counterclaim. The district court ruled that Parker, as Sivad’s agent, was not individually liable to Romero and required Romero to reimburse Sivad for work on four of the five construction projects, minus the amount owed to Romero for the fifth construction project, at which no unlicensed work was completed by Romero. Romero appeals.

STANDARD OF REVIEW

{7} “Summary judgment is appropriate [when] there are no genuine issues of material fact and the movant is entitled to judgment as a matter of law.” Montgomery v. Lomos Altos, Inc., 2007-NMSC-002, ¶ 16, 141 N.M. 21, 150 P.3d 971 (internal quotation marks and citation omitted). “We review the [district court’s] application of the law to the undisputed facts de novo.” Gamboa, 2004-NMCA-053, ¶ 7, 135 N.M. 515, 90 P.3d 534.

RECOVERY BY AN UNLICENSED CONTRACTOR

{8} The New Mexico Legislature “casts a harsh eye on contracting without a license.” Id. ¶ 12; see also Mascarenas, 111 N.M. at 414, 806 P.2d at 63 (stating that unlicensed contractors may not retain payments as a matter of public policy, even if the consumer had knowledge that the contractor was unlicensed). Section 60-13-30(A) states that “[n]o contractor shall ... bring or maintain any action ... for the collection of compensation for the performance of any act for which a license is required ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kemp v. JJJ Painting
New Mexico Court of Appeals, 2025
S & H Development LLC v. Parker
New Mexico Court of Appeals, 2017
Little v. Baigas
2017 NMCA 27 (New Mexico Court of Appeals, 2016)
Ground Control, LLC v. Capsco Industries, Inc.
120 So. 3d 365 (Mississippi Supreme Court, 2013)
Ground Control, LLC. v. Capsco Industries, LLC
Mississippi Supreme Court, 2011
Preferred Builders v. Ghaffari
New Mexico Court of Appeals, 2011
Parr v. Eridon
New Mexico Court of Appeals, 2011
Ontiveros v. Silva
New Mexico Court of Appeals, 2011

Cite This Page — Counsel Stack

Bluebook (online)
2009 NMCA 047, 207 P.3d 350, 146 N.M. 116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/romero-v-parker-nmctapp-2009.