Bertozzi v. McCarthy

323 A.2d 553, 164 Conn. 463, 1973 Conn. LEXIS 945
CourtSupreme Court of Connecticut
DecidedMarch 7, 1973
StatusPublished
Cited by107 cases

This text of 323 A.2d 553 (Bertozzi v. McCarthy) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bertozzi v. McCarthy, 323 A.2d 553, 164 Conn. 463, 1973 Conn. LEXIS 945 (Colo. 1973).

Opinion

House, C. J.

In July, 1965, the plaintiff, a building contractor, and the defendants, husband and wife, entered into a contract whereby the plaintiff, having title to a lot in Ridgefield, agreed to construct on the lot a house according to certain specifications and on its completion to convey the house and lot to the defendants for an agreed price. The expected date of occupancy was November, 1965. Several circumstances, including the failure of the plaintiff to obtain a construction mortgage and changes in plans induced by the defendants, delayed occupancy until July, 1966. The house at that time was substantially completed, but the plaintiff had not totally discharged his obligation in that the specified garage had not been built and various ancillary construction and cleanup work had not been performed. In addition, the artesian well drilled pursuant to the contract failed to provide potable water.

The defendants refused to pay a portion of the contract price and the plaintiff sued for this balance. The defendants filed a counterclaim for their additional expenses and for damages alleged to have resulted from the delay and from the unfitness of the well water.

The court found that the original contract had been modified by a series of mutual oral agreements and that when the defendants occupied the house in July, 1966, “the contract was substantially performed but with much left to be done which was the obligation of the plaintiff under the terms of the contract.” In rendering its judgment on the complaint and the counterclaim, the court took into *466 consideration, so far as it found that they had been proved by a fair preponderance of the evidence, the “extras” provided by the plaintiff, the “credits” to be extended to the defendants, the reasonable extra expenses the court found to have been incurred by the defendants because of the delay, and the cost of the garage which had not been built. The judgment awarded $8765 to the plaintiff on the complaint and $5181.25 to the defendants on the counterclaim. Neither interest nor costs were awarded to any party. From the judgment the plaintiff and the defendants have appealed to this court.

The plaintiff has preserved two claims on appeal. The first is that the court erred in not awarding interest on the judgment from the time that the defendants occupied the house until the date of judgment. In this connection, the court expressly found that the amounts due the parties on the complaint and the counterclaim, respectively, were not liquidated until the date of trial.

“ ‘The determination of whether or not interest is to be recognized as a proper element of damage, is one to be made in view of the demands of justice rather than through the application of any arbitrary rule.’ Bernhard v. Rochester German Ins. Co., 79 Conn. 388, 398, 65 A. 134. The real question in each case is whether the detention of the money is or is not wrongful under the circumstances.” Cecio Bros., Inc. v. Feldmann, 161 Conn. 265, 275, 287 A.2d 374; Wells Laundry & Linen Supply Co. v. Acme Fast Freight, Inc., 138 Conn. 458, 463, 85 A.2d 907; Campbell v. Rockefeller, 134 Conn. 585, 591, 59 A.2d 524. Basically, the question is whether the interests of justice require the allowance of interest as damages for the loss of use of money. Goldman v. Coppola, 149 Conn. 317, 328, 179 A.2d 817; Wells Laun *467 dry & Linen Supply Co. v. Acme Fast Freight, Inc., supra. Whether a sum. in certain circumstances has been liquidated may, of course, be a useful although not necessarily controlling criterion. Capitol City Lumber Co. v. Sudarsky, 95 Conn. 336, 340-41, 111 A. 349; 22 Am. Jur. 2d 256, 263, Damages, §§ 179, 185; cf. Loomis v. Gillett, 75 Conn. 298, 300-1, 53 A. 581. The allowance of interest as an element of damages is, thus, primarily an equitable determination and a matter lying within the discretion of the trial court.

In the circumstances of the present case, the trial court clearly acted within the scope of its discretion. Upon finding that the underlying contract had been orally modified in many respects, that it had been substantially performed but that the plaintiff had failed to fulfill his full obligation, and that many of the difficulties and delays were the result of the plaintiff’s conduct, the court could reasonably conclude, as it impliedly did, that the defendants had not wrongfully deprived the plaintiff of a sum of money. The findings support a conclusion that the plaintiff was at least partly responsible for the defendants’ refusal to pay a portion of the amount due on the contract. Accordingly, we do not find that there was any abuse of the court’s discretion.

The plaintiff’s second properly preserved claim is that the court erred in determining the allowance due the defendants for the construction of a garage in substitution for the one which the plaintiff failed to construct. The defendants sought and received a “credit” for the cost of building their own garage, which was of a type different from that specified in the contract. The plaintiff testified that his cost of constructing the garage as specified in the contract would have been $1500. The court, however, *468 awarded a credit of $2400. The plaintiff claims that the award of the higher figure was erroneous in that there was no evidence to support an award greater than $1500.

As a general rule, contract damages are awarded to place the injured party in the same position as he would have been in had the contract been fully performed. Bachman v. Fortuna, 145 Conn. 191, 194, 141 A.2d 477; Lee v. Harris, 85 Conn. 212, 214, 82 A. 186. We recognize that “[t]here is no unbending rule as to the evidence by which such compensation is to be determined”; Bachman v. Fortuna, supra, Lee v. Harris, supra; and that damages may be based on “reasonable and probable estimates.” Kay Petroleum Corporation v. Piergrossi, 137 Conn. 620, 624, 79 A.2d 829. But it is equally clear that damages must be based on evidence. “In the ordinary contract action the court determines the just damages from evidence offered.” Norwalk Door Closer Co. v. Eagle Lock & Screw Co., 153 Conn. 681, 689, 220 A.2d 263. Damages, moreover, may not be based on hearsay. Toti Contracting Co. v. A. J. Orlando Contracting Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sutera v. Washton, No. 556177 (Mar. 14, 2003)
2003 Conn. Super. Ct. 3366 (Connecticut Superior Court, 2003)
Overhead Door Co. v. Chere Arch., No. Cv97-014 24 05 S (Mar. 26, 2001)
2001 Conn. Super. Ct. 4664 (Connecticut Superior Court, 2001)
Overhead Door Co. v. Chere Architects, No. Cv97-014 24 05 S (Mar. 8, 2001)
2001 Conn. Super. Ct. 3165 (Connecticut Superior Court, 2001)
Celentano v. the Oaks Condominium, No. X01 Cv 94 0159297 (Jan. 11, 2001)
2001 Conn. Super. Ct. 655 (Connecticut Superior Court, 2001)
Barron v. Benton Auto Body, Inc., No. Cv97-0573293-S (Dec. 21, 2000)
2000 Conn. Super. Ct. 15663 (Connecticut Superior Court, 2000)
Aubin v. Miller and Munson Builders, No. Cv99035 57 68 S (Apr. 10, 2000)
2000 Conn. Super. Ct. 4093 (Connecticut Superior Court, 2000)
Johnson v. Anderson, No. Cv 98 04901 66s (Jul. 26, 1999)
1999 Conn. Super. Ct. 9854 (Connecticut Superior Court, 1999)
Bouchard v. Boyer, No. 543089 (May 17, 1999)
1999 Conn. Super. Ct. 6067 (Connecticut Superior Court, 1999)
Tuthill Finance v. Greenlaw, No. Cv91 0115439 (May 4, 1998)
1998 Conn. Super. Ct. 5832 (Connecticut Superior Court, 1998)
Adams v. Piccirillo, No. Cv-97 8032 (Apr. 9, 1998)
1998 Conn. Super. Ct. 4540 (Connecticut Superior Court, 1998)
Boiano v. Pinnacle Decision Systems, No. Cv 97 65309 S (Feb. 11, 1998)
1998 Conn. Super. Ct. 1634 (Connecticut Superior Court, 1998)
Adamczyk v. Barberino Bros., Inc., No. Cv95-0371536 (Apr. 29, 1997)
1997 Conn. Super. Ct. 3806 (Connecticut Superior Court, 1997)
Grande v. Behling, No. Cv95-0250416s (Apr. 24, 1997)
1997 Conn. Super. Ct. 4768 (Connecticut Superior Court, 1997)
Smith v. Bridgeport Futures Initiative, Inc., No. 326697 (Aug. 13, 1996)
1996 Conn. Super. Ct. 5744 (Connecticut Superior Court, 1996)
Southern New Eng. T. v. Henkels McCoy, No. Cv-94-0538045-S (Jul. 16, 1996)
1996 Conn. Super. Ct. 5163-BBBBB (Connecticut Superior Court, 1996)
Ab Small Business Investment v. Husser, No. Cv 94 0065741 (Nov. 9, 1995)
1995 Conn. Super. Ct. 12554-AA (Connecticut Superior Court, 1995)
Cie v. West Haven Buckle Co., No. 323965 (Aug. 23, 1995)
1995 Conn. Super. Ct. 9423 (Connecticut Superior Court, 1995)
Morelli v. Kablik, No. Cv93 05292205 (Mar. 1, 1995)
1995 Conn. Super. Ct. 1788 (Connecticut Superior Court, 1995)
Ercole v. Cuomo, No. Cv 93-0456963s (Jun. 15, 1994)
1994 Conn. Super. Ct. 6294 (Connecticut Superior Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
323 A.2d 553, 164 Conn. 463, 1973 Conn. LEXIS 945, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bertozzi-v-mccarthy-conn-1973.