Argentinis v. Gould

579 A.2d 1078, 23 Conn. App. 9, 1990 Conn. App. LEXIS 295
CourtConnecticut Appellate Court
DecidedAugust 28, 1990
Docket8454
StatusPublished
Cited by71 cases

This text of 579 A.2d 1078 (Argentinis v. Gould) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Argentinis v. Gould, 579 A.2d 1078, 23 Conn. App. 9, 1990 Conn. App. LEXIS 295 (Colo. Ct. App. 1990).

Opinion

Spallone, J.

This is an appeal from the judgments rendered on consolidated actions. In the first captioned action, Takis Argentinis sought damages for breach of a construction contract and of an express warranty by the defendants, Paul L. Gould and Paul L. Gould, Inc. In the second captioned action, Gould sought to foreclose a purchase money mortgage granted by Argentinis and his wife, the defendants in that action, P. A. (Takis) Argentinis and his wife, Ourania Argentinis, securing the final payment due on the contract.1

After a trial to an attorney trial referee, the reported findings were accepted and judgments rendered for [11]*11Argentinis on both the contract action and on the foreclosure action. On appeal, Gould challenges the court’s acceptance of the trial referee’s findings (1) that Argentinis was entitled to both compensatory damages for breach of contract and a judgment in the foreclosure action, (2) that Gould had not substantially performed under the terms of the construction contract, (3) that Gould had the burden to prove the soundness of the structural plans, and (4) that Gould was personally liable for contract damages. Gould also claims that the court should not have accepted findings that did not comply with the rules of practice. We affirm the judgments.

The evidence introduced at trial supports the following facts. In November, 1980, Gould individually and as president of Paul L. Gould, Inc., entered into a contract with Argentinis for the construction of a custom designed house in Fairfield. The agreement incorporated the house plans and specifications prepared for Argentinis by professional architects. The contract contained Gould’s various express warranties, including a warranty against water leakage into the premises for one year after closing. The house was to be ready for occupation by May 1, 1981.

The closing took place in April, 1981. Gould took from Argentinis a purchase money mortgage for the final $50,000 of the total sales price of $344,000. Although a certificate of occupancy had been issued, the Argentinis family was unable to occupy the house as scheduled because some forty to fifty items of construction remained unfinished. After further negotiation, the parties reached a supplemental agreement modifying the terms of the mortgage. Argentinis received a credit of $4000 toward the final $50,000 due. The parties agreed to a modified promissory note and mortgage for [12]*12$43,000 and a cash payment of $3000 which was to be released on the completion of those construction items recognized to be unsatisfactory.

The Argentinis family moved into the house in early July, 1981, and the cash payment and documents were released to Gould from escrow. Some items due for completion later that month or “within a reasonable period of time” had not yet been performed. Of principal concern to Argentinis was the lack of water pressure in the house and the contaminated well water. It was subsequently discovered that the well had been placed, without a permit, too near a septic system and a sewer drain. Argentinis was without potable tap water for three months. Structural defects soon became manifest. Particularly, the basement was vulnerable to flooding during rains. Storm flooding occurred within the warranty period, again in June, 1982, and twice more in April, 1983, causing substantial damage to personal and real property.

■ Argentinis made repeated demands upon Gould within the warranty period to rectify the problems of the improperly sited well, the flooding basement and numerous other significant deficiencies. Gould refused to repair the defects unless given an unconditional release for all defects and the right to determine those defects for which he was responsible. Argentinis refused to give this release, refused to make payments on the outstanding debt, and brought suit against Gould for breach of contract and of express warranties. Gould sought to foreclose the $43,000 mortgage.

The consolidated actions were tried before an attorney trial referee who found for Argentinis on the contract claims, awarding $73,068.75 in damages. The referee also found for Argentinis on Gould’s foreclosure action, ruling that Gould was not entitled to the final contract payment because he had not substantially com[13]*13pleted construction. The trial court accepted the referee’s report in September, 1989, and rendered judgments consistent with the report. This appeal followed.

I

Gould first challenges the referee’s findings that Argentinis was entitled both to compensatory damages for breach of contract and to judgment in the foreclosure action. Gould argues that the balance due on the mortgage and promissory note should have been set off against the damage award. He asserts that in finding for Argentinis on both claims, the referee awarded Argentinis a double recovery of more than $154,600; $73,068.75 in breach of contract damages and $43,000, plus interest, owed on the promissory note.

In refusing to set off the balance due under the contract against the damage award, the referee relied on Edens v. Kole Construction Co., 188 Conn. 489, 450 A.2d 1161 (1982). In Edens, the plaintiff sued for breach of a construction contract and the defendant counterclaimed for the unpaid portion of the purchase price and for foreclosure of a mechanic’s lien. Id., 491. Our Supreme Court approved the trial court’s treatment of these claims as distinct and separate issues. In Edens, as here, no challenge was mounted to the determination that the builder had breached the contract or to the calculation of the resulting damages. Id., 493. The builder, as here, challenged only the court’s failure to find that he was entitled to the total purchase price. Id. That issue turned wholly on whether the builder had proved his claim to the balance due by virtue of his having substantially performed the contract. Id. The Edens court, finding no substantial performance, ruled that the builder was not entitled to any amount over that already paid and thus awarded the buyer contract damages and also forgave the balance due. Id., 496.

[14]*14Contrary to Gould’s first claim, Edens makes it clear that it is not per se improper both to award damages and to forgive the outstanding debt. Setoff is proper only if the contract has been substantially performed; the buyer will not be forced to pay for value not received. Id.

II

Gould next claims that the referee’s conclusion that construction was not substantially completed is against the weight of evidence. He states that Argentinis’ architects had performed inspections as the work progressed and had approved the materials and workmanship. The town building inspector had found that the project met all but one minor code requirement and had issued a valid certificate of occupancy. We do not agree that this evidence forces a conclusion that Gould substantially performed under the terms of the contract.

A party cannot recover on a contract unless he has performed his obligations or has a legal excuse for not performing. Mayfair Roofing & Renovating Co. v. Rameo Technologies, Inc., 18 Conn. App. 682, 686, 560 A.2d 464 (1989).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Absolute Plumbing & Heating, LLC v. Edelman
77 A.3d 889 (Connecticut Appellate Court, 2013)
Intercity Development, LLC v. Andrade
901 A.2d 731 (Connecticut Appellate Court, 2006)
Carmel Homes, Inc. v. Bednar, No. Cv 99-0079393 S (Mar. 26, 2001)
2001 Conn. Super. Ct. 4317 (Connecticut Superior Court, 2001)
Holt v. People's Bank, No. Cv 96 0153281 (Aug. 24, 1999)
1999 Conn. Super. Ct. 11764 (Connecticut Superior Court, 1999)
Krondes v. Montagnese, No. Cv 95 0143692 (Aug. 10, 1999)
1999 Conn. Super. Ct. 11052 (Connecticut Superior Court, 1999)
Bankers Trust of California v. Monies, No. Cv 94 0137217 (Jul. 30, 1999)
1999 Conn. Super. Ct. 9927 (Connecticut Superior Court, 1999)
Greene v. Perry, No. Cv 97 0057091s (Jun. 9, 1999)
1999 Conn. Super. Ct. 6679 (Connecticut Superior Court, 1999)
Bouchard v. Boyer, No. 543089 (May 17, 1999)
1999 Conn. Super. Ct. 6067 (Connecticut Superior Court, 1999)
Isaac v. Truck Service, Inc.
727 A.2d 755 (Connecticut Appellate Court, 1999)
Rowland Ironworks v. 1200 Post R. E Assoc., No. Cv 97 0156531 (Dec. 4, 1998)
1998 Conn. Super. Ct. 14266 (Connecticut Superior Court, 1998)
Rainbow v. Moran, No. Cv 970157465 (Nov. 3, 1998)
1998 Conn. Super. Ct. 12478 (Connecticut Superior Court, 1998)
Darien Asphalt Paving, Inc. v. Giordano, No. Cv 90 0107529 (Oct. 30, 1998)
1998 Conn. Super. Ct. 12372 (Connecticut Superior Court, 1998)
Selvaggio v. Miron, No. Cv95 032 56 38 S (Oct. 28, 1998)
1998 Conn. Super. Ct. 12394 (Connecticut Superior Court, 1998)
Landmark Builders, Inc. v. Brower, No. Cv95 0049114s (Mar. 23, 1998)
1998 Conn. Super. Ct. 4004 (Connecticut Superior Court, 1998)
Paulus v. Lasala, No. Cv 87 0089213 (Jan. 20, 1998)
1998 Conn. Super. Ct. 844 (Connecticut Superior Court, 1998)
National Loan Inv. v. Heritage Square, No. Cv 95 0147511 (Jan. 5, 1998)
1998 Conn. Super. Ct. 1213 (Connecticut Superior Court, 1998)
One Sylvan Rd. v. Lark Int'l Ltd., No. Cv94 031 05 85 S (Dec. 31, 1997)
1997 Conn. Super. Ct. 12783 (Connecticut Superior Court, 1997)
Seftner v. W.B. Wood Company, Inc., No. Cv 95 0143367 (Dec. 4, 1997)
1997 Conn. Super. Ct. 13718 (Connecticut Superior Court, 1997)
Friedman v. Town of Westport, No. Cv95-0325665s (Mar. 12, 1997)
1997 Conn. Super. Ct. 2135 (Connecticut Superior Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
579 A.2d 1078, 23 Conn. App. 9, 1990 Conn. App. LEXIS 295, Counsel Stack Legal Research, https://law.counselstack.com/opinion/argentinis-v-gould-connappct-1990.