Absolute Plumbing & Heating, LLC v. Edelman

77 A.3d 889, 146 Conn. App. 383
CourtConnecticut Appellate Court
DecidedOctober 15, 2013
DocketAC 34438
StatusPublished
Cited by5 cases

This text of 77 A.3d 889 (Absolute Plumbing & Heating, LLC v. Edelman) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Absolute Plumbing & Heating, LLC v. Edelman, 77 A.3d 889, 146 Conn. App. 383 (Colo. Ct. App. 2013).

Opinion

Opinion

DiPENTIMA, C. J.

This appeal arises from consolidated actions brought by subcontractors to foreclose on mechanic’s liens placed on the defendant’s property to secure the value of their labor and services on ahorne improvement project. The defendant, Alison Edelman, individually and as executrix of the estate of her mother, Claudia Pearl,1 appeals from the trial court’s judgment [386]*386accepting a report by the attorney trial referee (referee) awarding damages, interest, and attorney’s fees to the plaintiff subcontractors,2 Absolute Plumbing & Heating, LLC (Absolute Plumbing), and JR Remodeling, LLC (JR Remodeling). On appeal, the defendant claims that the trial court improperly adopted the referee’s report because (1) it failed to consider the applicability of the Home Improvement Act (act), General Statutes § 20-418 et seq., to the validity of the plaintiffs’ hens, and (2) the evidence presented did not support either the referee’s factual finding as to the contract price agreed to by the defendant and the general contractor or his finding that the construction work agreed to under the contract had been substantially completed. The defendant further claims that the trial court improperly awarded attorney’s fees to the plaintiffs. We affirm in part and reverse in part the judgment of the trial court.

The following facts and procedural history are relevant to this appeal. On December 27, 2006, the defendant entered into a contract with Schott Construction, LLC (Schott), as general contractor, to make renovations on the residential property located at 61 Maple Avenue North in Westport (property). The contract stated an estimated total price of $454,341.80. Over the course of construction, the contract was modified, in accordance with its terms, by numerous “construction summaries.” These summaries reflected additions to the scope of the project and corresponding increases in the contract price, which had been discussed with and orally agreed to by the defendant. After becoming dissatisfied with the general contractor’s performance, the defendant terminated the contract with Schott on September 19, 2006. The defendant subsequently hired [387]*387other general contractors, DeFelice Contracting (DeFelice) and Bella Cucina Design, LLC, to continue and expand the work on the project.

During the course of its work on the project, Schott engaged the plaintiffs as subcontractors to perform work on the premises. Absolute Plumbing was hired to perform the heating and plumbing work and JR Remodeling was hired to perform the carpentry work. The defendant was aware that this work was being performed by the plaintiffs. When the defendant unilaterally terminated the contract with Schott, she directed the plaintiffs to leave the premises. After the contract was terminated, Schott sent a letter to the defendant on October 13, 2006, demanding full payment under the terms of the contract. The amount so demanded included $16,837.20 that Schott owed to Absolute Plumbing and $9460 that it owed to JR Remodeling for work performed by them on the project. The defendant took no action in response to this demand letter. The plaintiffs subsequently filed separate certificates of mechanic’s hen for the amounts they were owed for their work on the project.3 In December, 2007, the plaintiffs brought separate actions to foreclose on their respective mechanic’s hens, which the defendant answered by denying ah liability. Additional facts will be set forth as necessary.

The plaintiffs’ separate actions were consohdated by a March 10, 2010 court order.4 The parties then elected to proceed to trial before an attorney trial referee on August 13, 2010. On the first day of trial, the defendant sought to file special defenses, alleging that they had [388]*388paid Schott in excess of the contract price and that the plaintiffs had not properly presented their claims to the defendant as executrix of the estate of Pearl. Upon the plaintiffs’ objection the referee did not allow the special defenses, finding the request untimely and procedurally defective. Thereafter, the referee concluded that the plaintiffs were entitled to the foreclosure of their mechanic’s liens. The referee found that the defendant owed Absolute Plumbing a total of $30,192.49 and JR Remodeling a total of $18,635.74, which sums included amounts for their respective hens and costs, plus prejudgment interest of 10 percent per year from September 19, 2006. Finally, the referee determined that the plaintiffs were entitled to attorney’s fees, but made no findings as to the amounts of those fees.

Pursuant to Practice Book § 19-14, the defendant objected to these findings of fact and to the acceptance of the referee’s report, claiming that no lienable fund existed from which the plaintiffs could recover. The defendant also contended that the referee should have applied the act to its analysis of the plaintiffs’ actions and that the referee improperly determined that (1) the plaintiffs had made proper service of process upon her, (2) the hens were in the correct amounts, (3) Schott’s work under the contract had been substantially completed, and, therefore, the hens were enforceable, and (4) the plaintiffs were entitled to attorney’s fees. In its June 9, 2011 memorandum of decision, the trial court accepted the referee’s report with respect to all findings therein, but did not determine the issue of attorney’s fees, as the parties had agreed to reserve that issue for a later hearing. The court denied the defendant’s subsequent motion to reargue or reconsider that decision.

Following a July 6, 2011 evidentiary hearing on the issue of attorney’s fees, the trial court issued a supplemental memorandum of decision. The court awarded [389]*389attorney’s fees in the amounts of $16,691.50 and $29,707.51 to JR Remodeling and Absolute Plumbing, respectively. This appeal followed.5

I

The defendant first claims that the trial court improperly accepted the referee’s report because the referee failed to analyze the defendant’s claims pursuant to General Statutes § 20-429, which sets forth the contract provisions required under the act.6

[390]*390The standard of review in cases referred to attorney trial referees is well settled. “[B]ecause the attorney trial referee does not have the powers of a court and is simply a fact finder, [a]ny legal [determinations] reached by an attorney trial referee have no conclusive effect. . . . The reviewing court is the effective arbiter of the law and the legal opinions of [an attorney trial referee], like those of the parties, though they may be helpful, carry no weight not justified by their soundness as viewed by the court that renders judgment. . . . [When] legal [determinations] are challenged, [the reviewing court] must determine whether they are legally and logically correct and whether they find support in the facts found by the . . . referee.” (Internal quotation marks omitted.) FCM Group, Inc. v. Miller, 300 Conn. 774, 796, 17 A.3d 40 (2011).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pittu v. Bugaj Contractors Co., LLC
234 Conn. App. 28 (Connecticut Appellate Court, 2025)
Wells Fargo Bank, N.A. v. Lorson
192 A.3d 439 (Connecticut Appellate Court, 2018)
21st Century North American Ins. Co. v. Perez
173 A.3d 64 (Connecticut Appellate Court, 2017)
Grovenburg v. Rustle Meadow Associates, LLC
165 A.3d 193 (Connecticut Appellate Court, 2017)
Generation Partners, L.P. v. Mandell
85 A.3d 49 (Connecticut Appellate Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
77 A.3d 889, 146 Conn. App. 383, Counsel Stack Legal Research, https://law.counselstack.com/opinion/absolute-plumbing-heating-llc-v-edelman-connappct-2013.